Expand boundaries : Gulf of Guinea experience

Expand boundaries : Gulf of Guinea experience. Thierry MONMONT . Cameroon : The global picture. An historic oil producer : Mainly from Rio del Rey, starting 1977. Production peaked at 180 kbopd in 1986, current ~ 80 kbopd. No valorization of associated gas, about 3 MMm 3 /d flared today

PamelaLan
Télécharger la présentation

Expand boundaries : Gulf of Guinea experience

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Expand boundaries : Gulf of Guinea experience Thierry MONMONT

  2. Cameroon : The global picture • An historic oil producer : • Mainly from Rio del Rey, starting 1977. • Production peaked at 180 kbopd in 1986, current ~ 80 kbopd. • No valorization of associated gas, about 3 MMm3/d flared today • Cameroon National Gas Strategy (2005) : • Reduction of flaring • Gas supply for domestic use (mainly for power plants) • Liquids extraction (C5+, LPG) • Dry gas export to Equatorial Guinea LNG plant • Boost exploration activities

  3. Cameroon gas within the regional picture NLNG (start-up 1999, 30 MMt/y 2012) Brass (under preparation,10 MMt/y 2011) Okolola (under preparation,11 MMt/y 2011) Nigeria • RESOURCES (TCF) * : • Nigeria : 130 – 200+ • Cameroon : 2.5 – 6+ • Equatorial Guinea : 6 – 10+ S a n d y g a s 6 0 k m EGLNG supports the Cameroon Gas Project by monetising gas and therefore allows flare reduction Equatorial Guinea Bioko (Start-up 1Q07, T1=3.7 MMt/y, T2 2011?) *From various sources (Woodmac, Cedigaz, …)

  4. CAMEROON CAMEROON GAS ( GAS ( Tcf Tcf ) ) Y Y # # Y Y # # Y Y # # Reserves Reserves / / Resources Resources : 2.2 to 3.9 : 2.2 to 3.9 North Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # (Rio Del Rey) Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y Y Y Y Y Y Y Y Y # # # # # # # # # # Y Y # # Y Y # # • • Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Rio Del Rey : 1.2 to 2.4 Rio Del Rey : 1.2 to 2.4 Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y Y Y # # # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y Y Y # # # # Y Y # # Y Y # # Y Y # # Y Y Y Y # # # # Y Y Y Y # # # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # • Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Sanaga/ Kribi : 1 to 1.5 Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y Y Y Y Y # # # # # # Y Y # # Y Y # # Y Y # # Limbe Hub Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Alba Y Y # # Y Y # # Y Y # # NIGERIA Exploration Potential (n.r) : 1 to 5 Y Y # # Y Y # # Y Y # # ? Y Y # # Y Y Y Y # # # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # Y Y # # 200 to 250 MMSCFD Y Y # # Y Y # # Y Y # # EQUATORIAL GUINEA LNG PLANT BIOKO ISLAND T1: 3.7 Mtpy / mid 07 South T2 : 4.4 Mtpy / 2011 - 2012 ? (Sanaga/ Kribi ) Feed Gas T1+T2: 1250 MMSCFD Y Y # # Y Y # # Y Y # # ( Of which ALBA : 510 MMSCFD ) The Cameroon Gas Project today CAMEROON GAS ( Tcf ) Reserves / Resources : 2.2 to 3.9 North North (Rio Del Rey) (Rio Del Rey) • Rio Del Rey : 1.2 to 2.4 • • Sanaga/ Sanaga/ Kribi Kribi : 1 to 1.5 : 1 to 1.5 Limbe Limbe Hub Hub Alba Alba NIGERIA Exploration Exploration Potential Potential (n.r) : 1 to 5 (n.r) : 1 to 5 ? ? 200 to 250 MMSCFD 200 to 250 MMSCFD 200 to 250 MMSCFD EQUATORIAL GUINEA EQUATORIAL GUINEA LNG PLANT BIOKO ISLAND LNG PLANT BIOKO ISLAND T1: 3.7 T1: 3.7 Mtpy Mtpy / / mid mid 07 07 South South T2 : 4.4 T2 : 4.4 Mtpy Mtpy / 2011 / 2011 - - 2012 ? 2012 ? (Sanaga/ (Sanaga/ Kribi Kribi ) ) Feed Feed Gas Gas T1+T2: 1250 MMSCFD T1+T2: 1250 MMSCFD ( ( Of Of which which ALBA : 510 MMSCFD ALBA : 510 MMSCFD ) ) Limbe hub functions : Supply local market gas for power, LPG & condensates Export dry gas to Equatorial Guinea

  5. Equatorial Guinea situation • LNG plant (T1) on stream 1Q 2007. • On-going engineering studies for train T2. • On-going talks with Cameroon & Nigeria to secure gas supply for T2 and further trains. • MoU Nigeria/Eq Guinea : early 2006 • MoU Cameroon/Eq Guinea : early 2006 • HoA Nigeria/Eq Guinea : december 2006

  6. Short term Cameroon Gas Project planning

  7. Project impact on Rio del Rey flaring AG production 5 • In 2011, associated gas production will range between 1 and 3 MMsm3/d. • The project will significantly reduce the potential flaring of associated gas, by at least 50% 4 3 MMsm3/d 2 Mini case Maxi case 1 0 2008 2012 2014 2010 2011 2013 2009 2015 2016 2007 2005 2006

  8. Project challenges • Complex project : • Multi countries • Multi players • Dispersed gas resources with impact on technical cost • But : • All stakeholders committed to gas flaring reduction • Good momentum among stakeholders to take advantage of regional & international opportunities

  9. Conclusions • The development of a successful Cameroon Gas Project requires: • a regional approach instead of national approach to gas flaring reduction • an appropriate fiscal & legal frame work • a pragmatic technical and commercial approach between the stakeholders

More Related