Highway 7 Expansion (Twinning) Phase 3

Highway 7 Expansion (Twinning) Phase 3. Meeting with Lanark County March 7, 2007 6:00 p.m. From 2.5km West of Ashton Station Road Westerly to McNeely Avenue (Carleton Place). Introduction. Expansion of Highway 7 from Hwy 417 (City of Ottawa) to Town of Carleton Place

Samuel
Télécharger la présentation

Highway 7 Expansion (Twinning) Phase 3

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Highway 7 Expansion (Twinning) Phase 3 Meeting with Lanark County March 7, 2007 6:00 p.m. From 2.5km West of Ashton Station Road Westerly to McNeely Avenue (Carleton Place)

  2. Introduction • Expansion of Highway 7 from Hwy 417 (City of Ottawa) to Town of Carleton Place • 2-lane rural highway to 4-lane rural freeway • Overall expansion to be phased-in under 3 contracts • Construction of Phase I (WP 256-99-00) starting at 417…. started in August 2006 • Construction of Phase III (WP 252-99-00) scheduled to start in 2010

  3. Scope of Work – WP 252-99-00 • Expansion of 2-lane facility to 4-lane rural freeway divided (RFD) • 4-lane freeway to 4-lane urban highway transition zone • New interchange at Co. Rd. 17 • New commuter parking lot • Full illumination for urban transition section, partial illumination at interchange ramp exits and terminals • Drainage, culvert replacements, storm water mgt • Roadside safety improvements • Landscape design

  4. Highway 7 2-lane rural highway posted speed limit of 80 km/h 2 at-grade signalized intersections McNeely Avenue County Road 17 Existing Conditions

  5. New Highway Geometry – Urban Section McNeely Intersection Section with Concrete Barrier

  6. Transition Plan • Approved Highway 7 Transition Measures: • Speed reductions: 1008060 km/h • Two 6000m-radius horizontal curves • “Freeway Ends” signing • Peripheral transverse edge lines • Overhead “traffic lights ahead” sign with continuous flashing amber beacons • Transition from 30m median to 5m median with concrete barrier or curb & gutter • Full illumination: for transition from McNeely Ave. to wide median • Partial illumination: Co. Rd. 17 exit ramps & ramp terminals

  7. Staging Overview • Stage I • Construction of new WBL & EBL, west and east of County Road 17 respectively • Start of interchange construction • New temporary intersection for County Road 17 south detour – Hwy 7 to SSR

  8. 1 2 1 1 1 2 1 1 Staging Overview – Stage I

  9. Staging Overview • Stage II • County Road 17 closed between NSR & SSR, traffic detours in effect • Two-way Hwy 7 traffic diverted to WBLs from McNeely to temporary Co. Rd. 17 detour intersection • EBL under construction from 200m east of McNeely to median cross-over, just east of County Road 17 • Remaining sections of interchange, including bridge superstructure completed • Permanent singing installed, line painting completed

  10. Temporary Detour Intersection 1 1 2 SSR 1 1 2 Staging Overview – Stage II

  11. Stage II Detour Routes Advance Notification Signs PVMS Sign CO RD 17 N CLOSED DETOUR VIA D-1

  12. Staging Overview • Stage III • EBL & WBL fully operational • Removal of temporary detour intersection and median cross-over • Concrete median under construction, light standards installed (with single temporary lane closure per direction)

  13. 2 2 2 2 2 2 2 2 Staging Overview – Stage III

  14. County Road 17 Bridge – Plan View Hwy 7 EBL Hwy 7 WBL

  15. County Road 17 Bridge – Profile & Section