(Strategy for) SIS100 Dipole Magnet Procurement. Peter Spiller FAIR - Machine Advisory Committee Meeting 9.5.2011. German inkind proposal for SIS100. Delivery 1: Preseries Dipole and Dipole Series including cryostats, supports and vaccum chamber, tested an integrated as a whole

acantu
Télécharger la présentation

Peter Spiller FAIR - Machine Advisory Committee Meeting 9.5.2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. (Strategy for) SIS100 Dipole Magnet Procurement Peter Spiller FAIR - Machine Advisory Committee Meeting 9.5.2011

  2. German inkind proposal for SIS100 • Delivery 1: • Preseries Dipole and Dipole Series • including cryostats, supports and vaccum chamber, tested an integrated as a whole • Delivery 2: (strongly linked and with the need of synchronisation) • Upgrade of the existing magnet test facility for the single layer coil, preseries dipole magnet • Dipole series test facility, set-up at GSI (including two test benches, power converters and cryogenic plant) • > enabling the option of setting up the string test near by

  3. The goal is to establish the fastest process with as risks as minimum as possible.

  4. Strategic Comments • The procurement of the SIS100 dipole series is linked to the upgrade of the existing magnet test stand and the build-up of the series test stand. • A clear guideline could be estabilished after the decision was made to separate the discussion on the dipole testing from the quadrupole and Super-FRS magnet testing ( a long phase of discussion on where to test the magnets has been conducted through the last years). • The dipole series and the magnet testing (common systems) are proposed to become german a inkind contribution, thus decision can be taken as soon as the formal steps are obtained. Without the need to consider more/other complicated boundary conditions which do not yet allow decisions. • The established project plan is the best concering its time schedule and ends already a little after the building readiness has been reached. • The project plans contains a number of risks, which may be acceptable, but have consequences in case of problems.

  5. Immediate Actions • The agreement and permit to start the series tendering must be achieved now. • The agreement to test the dipole series at GSI and to use the Detectors Lab Building must be achieved now. • The budget for the upgrade of the existing magnet test stand must be provided now. • The tendering of the new dipole power converter and the current leads must be started now. • The tendering of the cryogenic plant for the series test stand must be started now.

  6. Parallel Actions • The steel for the dipole chamber series must be procured in parallel to the preseries dipole production. • The wire for the s.c. cable must be procured in parallel to the preseries dipole production. • The toolings for the series production must be build in parallel to the preseries production. • The series test stand must be build up in parallel to the preseries magnet production.

  7. Contract Strategy • The series production including the preseries magnet will be tendered. • The contract is organized in two parts: a) production of preseries dipole magnet and b) production of dipole series. • After delivery of the preseries dipole, there is a production break for half a year, which is used for testing. The second part of the contract is cancelled if major problems with the basic functionality of the preseries magnet show up. • The toolings (owned by GSI) must be stored until the problems habe been solved. • The chambers are tendered in separate and provided by GSI, giving the option to take control of the chamber quality (also for the quadrupoles by GSI). • The s.c. wire is tendered in separate and provided by GSI.

  8. Magnet Procurement Strategy • The magnets will be deliverd assembled, including the UHV chamber. • The field measurements must be performed at GSI including the chamber. • The production time of the chambers is of the same order as of the dipoles. Thus each chamber as it is build must be send to the magnet manufacturer. • Two options for the UHV chambers are still under consideration and investigation: Pipe and conduction cooling.

  9. Wire Procurement Strategy • The wire procurement starts with an immediate tendering of three billets from three independend manufacturer. • After the delivery (in about one year) the parameters will be compared (especially jc), the best manufacturer will be asked to produce the missing billets (12).

  10. Wires with CuMn interfilamentary matrix Red numbers indicate values below specification

  11. Project Schedule Procurement and Testing of SIS100 Dipole

  12. Risks

  13. Thanks to the magnet group for the input and the good collaboration.