Minnesota Department of Transportation Mn/DOT’s Gradual Shift from Profile Index to IRI

Minnesota Department of Transportation Mn/DOT’s Gradual Shift from Profile Index to IRI. Chronology of Shift to IRI. 1999 : Participated in FHWA’s Lightweight Profiler Study, hosting various vendors at MnRoad site

adli
Télécharger la présentation

Minnesota Department of Transportation Mn/DOT’s Gradual Shift from Profile Index to IRI

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Minnesota Department of Transportation Mn/DOT’s Gradual Shift from Profile Index to IRI

  2. Chronology of Shift to IRI • 1999: • Participated in FHWA’s Lightweight Profiler Study, hosting various vendors at MnRoad site • Overall, LWP devices involved in study demonstrated moderate repeatability and poor reproducibility

  3. Chronology of Shift to IRI • 2001: • Purchased Ames Lightweight Profiler and ARRB Walking Profiler • Began performing random Quality Assurance on projects with ride incentive determined from 0.2” blanking band Profile Index

  4. Mn/DOT’s Lightweight Profiler

  5. Chronology of Shift to IRI • 2002: • Initiated Profile Index Smoothness Measuring Device Program in spring • During QA on job sites, experienced problems replicating contractors’ 0.2” blanking band Profile Index values

  6. 0.2” Blanking Band PI vs. IRI • Empirical Data: • Projects with 0.2” blanking band PI value of 0.0 possessed IRI values ranging from roughly 27 - 42 in/mi • Projects with 0.2” blanking band PI value of 1.0 possessed IRI values ranging from roughly 29 - 46 in/mi

  7. Chronology of Shift to IRI • 2002 - 2003: • Analyzed extensive certification and construction data, finding a very weak correlation between 0.0” and 0.2” blanking band Profile Index results

  8. Chronology of Shift to IRI • 2004: • Let three bituminous IRI pilot construction projects • 2005: • Let 13 additional bituminous IRI pilot construction projects

  9. Chronology of Shift to IRI • 2006: • Let three concrete IRI pilot projects (results pending) • Switched to IRI exclusively on bituminous construction projects • Began using Pathways High Speed Profiler for Quality Assurance purposes

  10. Mn/DOT’s High Speed Profiler

  11. Bituminous Ride Incentive Equations

  12. Bituminous Ride Incentive Equations Incentive per 528-Foot Segment

  13. Bituminous IRI % Improvement Table

  14. Ride Incentive Information • Incentive/disincentive calculated for each 528-foot segment • Payment is based on right wheel path IRI values (9 feet from left stripe) • IRI data collected by contractor with certified profiler • Bump/dips established with profilograph

  15. Chronology of Shift to IRI • 2007: • Will use IRI exclusively to determine ride incentive for all construction projects

  16. Any Questions?