1 / 10

Hardware Integration of the Prototype

Hardware Integration of the Prototype. Wes Grammer NRAO. Outline. Hardware integration flow chart Integration steps and associated tests Proposed schedule. Hardware Integration Flowchart. Timing Subsystem Integration. Install modules in Timing/LO rack, cables per subsystem diagram

aletta
Télécharger la présentation

Hardware Integration of the Prototype

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Hardware Integration of the Prototype Wes Grammer NRAO EOVSA Prototype Review

  2. Outline • Hardware integration flow chart • Integration steps and associated tests • Proposed schedule EOVSA Prototype Review

  3. Hardware Integration Flowchart EOVSA Prototype Review

  4. Timing Subsystem Integration • Install modules in Timing/LO rack, cables per subsystem diagram • Power up and initialize PRD-16 via RS-232 port (script file on ACC, or standalone Labview GUI) • Power up TGD module: • Check 10 MHz output ports w/spectrum analyzer • Check 50 Hz and 1PPS outputs with digital oscope • Measure 1PPS optical power at patch panel (16) • At cRIO in antenna servo cabinet: • Measure 1PPS pulse output width and amplitude • Measure pulse latency at each antenna (necessary?) EOVSA Prototype Review

  5. LO Subsystem Integration(1 of 2) • Install modules in Timing/LO rack, all cables per subsystem diagram • LO1-A synthesizer tests: • Verify basic monitor and control interface functions, using spectrum analyzer. • Test list tuning mode with spectrum analyzer or counter at lower switching rate. • Verify frequency switching and output power settling at 50 Hz rate (how to do this?) EOVSA Prototype Review

  6. LO Subsystem Integration(2 of 2) • LO Distribution Module tests • Connect LO1-A, terminate LO1-B input port • Record LO1 and LO2 power at end of each LO cable, on Downconverter side, with constant LO1-A drive power setting, at each LO1 frequency. • Set up tuning table to remove loss slope in LO1 cables, run it and re-check power. • Adjust LO2 drive amplifier level as needed (pad swap) • Check RS-485 bus for proper function and reliable operation, using looped R/W test on ACC. • Verify monitor and control functions using ACC control software, with power meter or spectrum analyzer on outputs. • Temporarily connect synthesizer to LO1-B input, and repeat above tests for LO1 (tuning tables may differ) EOVSA Prototype Review

  7. Downconverter Integration • Install power supply panel • Install subracks and cooling fans • Install Downconverter and all associated cables, including M&C bus termination. • Attach a loopback jumper to spare fiber in Auxiliary cabinet at the corresponding antenna. Use RF synthesizer w/laser transmitters + diplexer to provide test source. • Verify all basic monitor and control functions with ACC over RS-485 bus • Measure bus trigger latency, verify if < 10 us. • Add detector calibration formula to control software, to obtain correct dB scale readout of 1st mixer input power. • Vary input power, and check that ACC software is adjusting attenuator to level output power to Correlator EOVSA Prototype Review

  8. Front End Assembly Integration(1 of 2) • Recheck voltages on Front End power cables • Install Front End module and apex mounting plate, connect all cables; DC power is off. • Connect laptop to TE controller in Auxiliary chassis, run monitoring software • Power the TE +24V and +12V, verify correct temperature control system operation at several setpoints. • Power up the remaining supplies, and verify stable internal temperature. • Verify basic function of Ethernet M&C interface with cRIO EOVSA Prototype Review

  9. Front End Assembly Integration(2 of 2) • Check for cable stresses, module clearance over range of telescope movement • Point at a strong fixed in-band sources (L-band RFI, Ku-band, verify signal presence at IF output with spectrum analyzer. • Verify proper focal point position for feed, adjust • Test monitor and control functions, trigger signal, using IF output level • Move dish off-source: • Check detected power in Downconverter, at nominal Front End attenuator settings, to verify expected system gain. • Measure Tsys on both polarizations • Use attenuators to verify correct polarization correspondance EOVSA Prototype Review

  10. Proposed Integration Schedule • Timing subsystem: end of October 2012, or after racks arrive and outfitted for AC power • LO subsystem: end of November 2012. Assumes LO rack is ready for module install. • Downconverter #1 and #2: early December 2012 • Front Ends 1-3, Downconverter #3: January 2013 EOVSA Prototype Review

More Related