1 / 26

Overview CQC Asphalt Specifications

Overview CQC Asphalt Specifications. In a Nutshell…. Payment based on Contractor’s Quality Control tests. FDOT runs verification tests at a lesser frequency. Payment is based on roadway density, air voids, asphalt content and gradation. Uses Percent Within Limits (PWL) statistical specs.

apria
Télécharger la présentation

Overview CQC Asphalt Specifications

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Overview CQC Asphalt Specifications

  2. In a Nutshell…. • Payment based on Contractor’s Quality Control tests. • FDOT runs verification tests at a lesser frequency. • Payment is based on roadway density, air voids, asphalt content and gradation. • Uses Percent Within Limits (PWL) statistical specs. • Separate Master Production Range to catch outliers. • Began with July 2002 workbook.

  3. Basics • Standard Lot size: • 4,000 tons for dense mix or 2000 tons for OGFC. • Four sublots per Lot. • Plant Lot & Roadway Lot same. • Engineer establishes sampling points. • Random basis. • Use Excel spreadsheet. • Directs Contractor when to sample. • Contractor does all the sampling.

  4. Basics • QC = Quality Control = Contractor • VT = Verification Test = FDOT Project personnel (typically a consultant) • IV = Independent Verification = FDOT District Materials personnel • RT = Resolution Testing = FDOT District Materials personnel

  5. Typical 1,000 ton Sublot - composed of 50 truckloads (20 tons each)

  6. Random Sample Numbers by Sublot Lot 1, sublot 1 50 trucks, 20 tons each = 1,000 ton sublot

  7. QC Testing at Plant LOT = 4,000 Tons Sublot 1 Sublot 2 Sublot 3 Sublot 4 Tons 487 1133 2696 3728 QC randomly tests one per sublot. VT randomly tests one split per Lot. RT splits held until Lot is verified.

  8. Gmb Gmm Ext/Grd Sample Splits QC VT RT

  9. Master Production Range for Quality Control

  10. If Quality Control Test Does Not Meet Tolerances: 334-5.4.4 (for MPR) • Terminate Lot if: • One sublot failure for Air Voids. • One sublot density failure. • Two consecutive sublot density failures for fine mix. • Two consecutive sublot failures for gradation. • Two consecutive sublot failures for asphalt content. • 2 individual core densities for coarse mix less than 91.00% Gmm.

  11. Verification Testing334-5.5 • At completion of each Lot • Test VT sample for randomly selected sublot • Split from QC sample • Use test method precision for comparison • Excel spreadsheet • If everything compares favorably… • Calculate pay based on QC results • If not….go to Resolution testing • District Materials Office

  12. VT Testing LOT = 4,000 Tons Sublot 1 Sublot 2 Sublot 3 Sublot 4 QC tests one per sublot. VT randomly tests one split per Lot.

  13. Between-Laboratory Precision Values Table 334-6

  14. Resolution Testing334-5.6 • If the verification testing does not compare on a pay property • Resolution samples tested by third party lab for the property in question • All sublots are tested • Use test method precision for comparison to QC • Excel spreadsheet • If everything compares favorably… • Calculate pay based on QC results • If the sample does not compare • Resolution results are used to calculate pay for that property

  15. RT Testing LOT = 4,000 Tons Sublot 1 Sublot 2 Sublot 3 Sublot 4 Tons 487 1133 2696 3728 QC randomly tests one per sublot. VT randomly tests one split per Lot. RT tests non-comparison property for each sublot.

  16. Roadway Acceptance334-5.4.3 • Roadway and Plant Lot the same. • 6-inch diameter cores . • Five cores per sublot. • Randomly located (stratified manner). • Use spreadsheet. • Minimum of 3 cores/sublot. • Retain QC cores for VT & RT.

  17. Density Testing Exceptions334-5.1.2 • Density testing not required for: • Total quantity of hot mix < 2,000 tons. • Widening or shoulders with a width of 5 ft or less. • FC-5 • Misc. Asphalt , Variable thickness or overbuild layers . • Leveling, Bridge Decks, Approach slabs. • First lift of asphalt placed on subgrade. • Bike/shared use paths. • Crossovers or intersections. • Any course thickness < 1 inch or specified spread rate converts to < 1 inch.

  18. Density Testing Exceptions (continued)334-5.1.2 • Testing not required for the following areas when they are less than 1,000 feet long: • Turning lanes • Acceleration lanes • Deceleration lanes • Shoulders • Parallel parking lanes • Ramps • Use rolling procedure (equipment and pattern) as approved by the Engineer. • Density testing required everywhere else.

  19. Calculate Payment334-8 • If two or less sublots: • Use Small Quantity Pay Table based on average deviations from target. • If three or more sublots: • Use Percent Within Limits (PWL) for the Lot. • Calculate Pay Factor for: • Density, Air Voids, AC Content, P-200, P-8

  20. Payment….334-8 • Pay factor for each characteristic is determined. • Composite Pay factor is based on: • 35% Density • 25% Air Voids • 25% AC Content • 10% P-200 • 5% P-8 • Calculations done by spreadsheet.

  21. Minimum Acceptable Quality Levels 334-5.9 • Individual Pay Factors Below 0.90 • First time correct, 2 consecutive – cease. • Composite Pay Factor 0.80 to 0.89 • Cease until problem is resolved. • Composite Pay Factor 0.75 to 0.79 • Handle per 334-5.9.5 (EAR). • Composite Pay Factor Less than 0.75 • Remove and Replace.

  22. Defective Material 334-5.9.5 • Contractor must remove & replace…OR • Engineering Analysis Report… • If approved by Engineer / Paid by contractor. • Independent Lab approved by Engineer. • Remain in place at composite pay factor, or as determined by Engineer. • Can be waived by Engineer. • Delineation testing by Contractor • Only for asphalt content, density, and gradation.

  23. Independent Verification Testing334-5.7 • Handled by the District Materials Office. • One sample per 4,000 tons. • Sampled by Contractor with FDOT supervision. • Compare IV results with QC (test precision). • Use Master Production Range Table 334-5. • IF IV fails MPR, cease production until problem resolved and then evaluate in-place material.

  24. Friction Course 337 • FC 9.5 and FC 12.5 • Handled in same manner as 334 HMA. • FC 5 (OGFC) • Same concepts but different material properties: • Asphalt content, Gradation (P-3/8, P-4, P-200)

  25. Questions/ Comments?

More Related