1 / 16

SCD Computing Center Expansion

SCD Computing Center Expansion. Aaron Andersen SCD User Forum 5/18/2005. Phase 1: SCD Internal Analysis. Growing Model Complexity. Power problem: P = C V 2 f Frequency (clock) increase driving Moore’s Law Decreasing voltage increases gate delay (hurts performance)

apu
Télécharger la présentation

SCD Computing Center Expansion

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SCD Computing Center Expansion Aaron Andersen SCD User Forum 5/18/2005

  2. Phase 1: SCD Internal Analysis

  3. Growing Model Complexity

  4. Power problem: P = C V2 f Frequency (clock) increase driving Moore’s Law Decreasing voltage increases gate delay (hurts performance) Capacitance increases as gate count increases. Chip power consumption will increase 30% over 5 years. Processor costs decreasing at 29%/year. Chips: Faster, Cheaper but Hotter

  5. Mesa Lab Power Limit

  6. The Problem with the Mesa Lab Facility • NCAR’s machine room was built during the era of low power/high cost computing systems (1976). • 13000 sq ft • 1.2 MW computer power limitation • 80 W/sq ft cooling design • We live in an era in which high power/low cost computing systems are available. • It is not cheap to modify the power infrastructure of Mesa Lab Computing Facility, nor does it make sense without expanding the machine room floor. • Site situated on bedrock. • If we do nothing, the Mesa Lab power and design limitations will become a serious constraint on NCAR’s scientific computing capacity. This is true for both future vector and microprocessor systems.

  7. Recap of Phase 1 Conclusions • Three Driving Issues for a Facility Expansion • Geoscience: Exponential demand for supercomputing • Technology: CMOS is getting hotter and cheaper • Engineering: Mesa Lab facility design is obsolescent • Recommended responses on three timescales • Short term (1 year): • Mesa Lab risk mitigation (RMH, Inc.) • Medium term (2 years): • Lease options (Staubach Real Estate) • Colocation (Inflow, Inc., Level 3) • Long term (3-5 years): • Refurbishment of existing structures (RNL Design, Inc.) • New construction (Uptime Institute, Inc.)

  8. Phase 2: Analysis of Facility Options

  9. Phase 2 Conclusions • Center Green 3 was not as capable as hoped • $26M to create a CG3 data center smaller than ML facility. • No room for expansion • Existing Computer Room Spaces on Market • Most not adequate for anticipated power densities or loads. • One that was acceptable was purchased by another entity. • Strategy Moving Forward • Act to maximize life and capabilities of Mesa Lab facility, • Move forward on building a data center expansion.

  10. Preservation of theMesa Lab Facility • Perform a Risk Assessment • Ensure capability of reliably housing ~ 1 – 1.2 MW of computing • Evaluate the capabilities of infrastructure equipment

  11. Phase 3: Facility Design Process

  12. Land for 20 Years Building Shell for 10 Outfit for 5 Design Concepts Strategy preserves initial capital investment as computing hardware evolves rapidly. Majority of cost in this type of facility in outfitting mechanical and electrical systems.

  13. M/E Space Computers Staff/Support Facility Design Concept 20,000 sq. ft. 4MW 20,000 sq. ft. 4 MW 20,000 sq. ft. 4 MW 20,000 sq. ft. 4 MW 20,000 sq. ft. 4 MW 20,000 sq. ft. 4 MW 20,000 sq. ft. 20,000 sq. ft. 20,000 sq. ft. Module 2 Module 3 Initial Module Expand laterally

  14. Mechanical /Electrical Data Center Network Operation Center Office Space Architectural Detail

  15. Phase 2 Addition Phase 3 Addition Architectural View

  16. Next Steps • Conceptual Design & Cost Estimate is due as I present this • Developing full report on findings • Develop funding strategies/options • UCAR Management • Board of Trustees • NSF

More Related