1 / 15

20130805 Crab Cavities FPC & Power Amplifiers status

20130805 Crab Cavities FPC & Power Amplifiers status. Amplifiers. We have 6 x 352 MHz amplifiers 1 x 400 MHz amplifier We have started test with a first 352 MHz Due to Long Shutdown 1 no water -> on hold We will restart in September

aqua
Télécharger la présentation

20130805 Crab Cavities FPC & Power Amplifiers status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 20130805Crab Cavities FPC &Power Amplifiers status

  2. Amplifiers • We have6 x 352 MHz amplifiers1 x 400 MHz amplifier • We have started test with a first 352 MHz • Due to Long Shutdown 1no water -> on hold • We will restart in September • We should qualify our first400 MHz amplifierbefore end 2013 • We will launch modification of3 additional 400 MHz amplifiers(4 in total) beginning 2014 SPS 352 MHz amplifier 1994-2000

  3. Amplifiers Transmission lines Final Driver FPC Cryo module LLRF

  4. Amplifiers • Regarding full reflection operation we need a circulator • We are in contact with suppliers, should not be a problem except some additional integration difficulties Transmission lines (WG or Coax) Final Circulator Driver FPC Cryo module LLRF

  5. FPC vacuum side • Will be the same window for all 3 couplers • Titanium flange • AL2O3 - 99.6% disk ceramic • 3D forged OFE Copper antenna • 3D forged OFE Copper Body with Stainless Steel flanges • 2 vacuum gauge ports • OD= 62 mm • ID = 27 mm • Windows raw material under procurement • Expected by end 2013

  6. FPC water cooled • Regarding Power levels,50 kW CW full reflection,i.e. 200 kW CW locallyinner antenna water cooled • Helicoflex 8” • OD/ID = 195/88.5 mm • 400 MHz – 137 kW • Helicoflex 9” • OD/ID = 216.7/99.4 mm • 400 MHz – 287 kW • Crab FPC antenna OD = 27 mm • Water tube • Antenna OD/ID = 27/21 mm • Water tube OD/ID=17/13 mm • CERN rule for couplers • No soldering, welding,… between water and vacuum • We will have an exception on the ceramic side End-shape EBW Water/vacuum End-shape EBW Copper/copper

  7. End-shape antenna Quarter Wave Double Ridge 4 rods 14.5 mm rounding on the tip

  8. Double Walled Tube • Not included in the FPC • Part of the cryomodule • Length still to be defined (regarding cryomodule design) • Cavity flanges tbcby cryomoduleteam • RF OD 62 mm tbd tbd tbd 114 mm 62 mm

  9. Test box & WG • Test box design • completed for 4 rods • To be completed for Double ridge and forQuarter Wave • Coaxial to Waveguide transition design completed • Antenna length awaiting DT design ?

  10. Integration • Still a lot to do, but we are confident that whatever the space available, we will be able to match with it • Key parameter is the distance between beam axis and the water inlet on the top of the waveguide • Cryomodule design must take it into account 1108 DT 2308 maximum 1200

  11. Schedule (December 2012) 2013 2014 2015 2016 February • Cavities to be installed in SPS in December 2015 • Cryostat fully tested Q3-2015 • Cryostat fully dressed Q2-015 • Couplers available for cryostat Q1-2015 • Couplers RF processed 50 kW SW cw all phases Q4-2014 • Couplers assembled in clean room Q2-2014 onto test box • Special processes FPC + Test Box (Cleaning, Brazing, EB welding, Gold plating, Ti coating) completed Q1-2014 • All couplers + Test Box parts machined Q4-2013 • All raw material delivered Q2-2013 • All raw material ordered Q1-2013 • (common) Coupler design completed February 2013 (+ Test Box !)

  12. Schedule August 2013 2013 2014 2015 2016 February October • Cavities to be installed in SPS in December 2015 • Cryostat fully tested Q3-2015 ? • Cryostat fully dressed Q2-2015 ? • Couplers available for cryostat Q1-2015 Q3-2015 • Couplers RF processed 50 kW SW cw all phases Q4-2014 Q2-2015 • Couplers assembled in clean room Q2-2014 onto test box Q4-2014 • Special processes FPC + Test Box (Cleaning, Brazing, EB welding, Gold plating, Ti coating) completed Q1-2014 Q3-2014 • All couplers + Test Box parts machined Q4-2013 Q2-2014 • All raw material delivered Q2-2013 Q4-2013 • All raw material ordered Q1-2013 Q2-2013 • Coupler design completed February October 2013 (+ Test Box !)

  13. Schedule August 2013 2013 2014 2015 2016 February October • Cavities to be installed in SPS in December 2015 • Cryostat fully tested Q3-2015 ? • Cryostat fully dressed Q2-2015 ? • Couplers available for cryostat Q1-2015 Q3-2015 • Couplers RF processed 50 kW SW cw all phases Q4-2014 Q2-2015 • Couplers assembled in clean room Q2-2014 onto test box Q4-2014 • Special processes FPC + Test Box (Cleaning, Brazing, EB welding, Gold plating, Ti coating) completed Q1-2014 Q3-2014 • All couplers + Test Box parts machined Q4-2013 Q2-2014 • All raw material delivered Q2-2013 Q4-2013 • All raw material ordered Q1-2013 Q2-2013 • Coupler design completed February October 2013 (+ Test Box !) Urgent to decide the DT design

  14. Schedule FPC key dates • 3D drawings for approval :February October 2013 • 2D drawings (EDMS): March November 2013 • Prototypes ready for tests: March December 2014 • Couplers ready for cavity assembly : December 2014 June 2015

  15. Conclusion • Next steps : • DT definition • Launch couplers & test boxes construction • Amplifier tests • Deal with integration issues

More Related