1 / 26

SPX Cryomodules WBS CD2DR-U1.02.01.03.05

SPX Cryomodules WBS CD2DR-U1.02.01.03.05 . John Mammosser Jefferson Lab SRF R&D DOE Lehman CD-2 Review of APS-Upgrade 4-6 Decem ber 2012. Outline. Science / Technical Significance WBS Scope of this system Staff / Org Chart Requirements Design Interfaces

arvin
Télécharger la présentation

SPX Cryomodules WBS CD2DR-U1.02.01.03.05

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SPX CryomodulesWBS CD2DR-U1.02.01.03.05 John Mammosser Jefferson Lab SRF R&D DOE Lehman CD-2 Review of APS-Upgrade4-6 December 2012

  2. Outline • Science / Technical Significance • WBS Scope of this system • Staff / Org Chart • Requirements • Design • Interfaces • Value Engineering (as applicable) • Risks considered (as applicable) • ES&H • Cost • Schedule DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  3. Science Case / Technical Motivation • The technological development of superconducting deflecting crab cavities, leverages current SRF technology for the production of short pulse X-Rays that’s both effective and compact. DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  4. SPX Cryomodules Scope / Cost Summary Cryomodule Scope: Design, Fabricate and Qualify (2) Superconducting Cryomodules Designed To Chirp (Sector 5) and Unchirp (Sector 7) the APS Beam for the Development of Short Pulse X-Rays Two Cryomodule Operational Configurations: Beam Ready for the production of Short Pulsed X-Rays, Cavities at 2K Parked Configuration where Cavities are Detuned and at 80K DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 4

  5. Milestones – 1.02.01.03 & 1.03.03SPX Cryomodules / Cavities DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  6. High Level Cryomodule Requirements: Stable Operation Installed in APS • Low trip rates when operating with beam currents up to 150mA while chirping beam for experiments are run (gain experience with SPX-0) • Thermally stable operation in a parked configuration, cavities detuned (cooling to remove heat generated from beam operations) • No adverse affects to APS beam during operations (fast detuning of cavities in fault condition) Chirping (Beam Deflecting Mode) • Independent control of cavities to provide 2MV of beam chirp and unchirp (gain experience with SPX-0) Critical Alignment of Cavities • Design must minimize coupling out of beam power from misalignment (remote alignment scheme will be employed to meet requirements) • Beam based alignment required at setup and for drifts (signal feed back for control) DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  7. SPX Cryomodules Design Requirements: Physics parameters Value Unit Total crabbing voltage 2 MV Total de-crabbing voltage 2 MV Beam current ≤150 mA Number of cryomodules 2 Length of section, including magnetic elements 3.034 m Cryomodule length beam-line flange to flange TBD Number of cavities per cryomodule 4 Cavities Type Superconducting Duty cycle CW (8th harmonic of APS storage ring frequency) Design Mark II Operating Frequency Deflecting Mode 2815.488 MHz Geometric factor 227.5 W R/Q’ 18.6 W Operating deflecting voltage 0.5 MV Active length 53.24 mm End flange to end flange distance 389.76 mm DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 7

  8. SPX Cryomodules Alignment Requirements: Alignment per module for APS installation Value Units X misalignment (Horizontal) ±500 µm Y misalignment (Vertical) ±200 µm Z misalignment (Longitudinal) ±1000 µm Yaw misalignment ±10 mrad Pitch misalignment ±10 mrad Roll misalignment ±10 mrad Alignment per cavity in cryomodule Value Units X misalignment (Horizontal) ±500 µm Y misalignment (Vertical) ** ±200 µm Z misalignment (Longitudinal) ±1000 µm Yaw misalignment ±10 mrad Pitch misalignment ±10 mrad Roll misalignment ±10 mrad ** with remote alignment DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 8

  9. String Design Concept HOM Absorber RF Tuner RF Window 4 Crab Cavities Providing 2MV Chirp (Deflection) to the APS Beam DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 9

  10. Cryomodule Concept Warm RF Tuner Vacuum Vessel Shielded Valves Fundamental Power Coupler SRF Cavity Beam Line DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 10

  11. Cryomodule Concept Spaceframe HOM Load Helium Gas Return Header Cold Tuner LOM Window DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 11

  12. Alignment Concept 1 Alignment Procedure for Cryomodule • Fiducialize each cavity to the electrical center on CMM using the stretched wire setup (scan a wire in vertical “Y” plane, measure mechanical center in the horizontal “X” plane) • Cavity flanges machined for fiducial balls (shown in pink) DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 12

  13. Cryomodule Alignment • Weld helium vessels on the four cavities and recheck vertical alignment on CMM DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 13

  14. Cryomodule Alignment • With string assembly tooling align the four cavities with laser tracker (mock assembly out side cleanroom) • Clean all components and process cavities • Qualify cavities individually in vertical test • Perform string assembly and align with laser tracker • Build out cold mass (instrumentation, magnetic shielding, MLI) DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 14

  15. Cryomodule Alignment 2 • Insert cold mass into space frame (support structure) • Transfer alignment to space frame (fiducial features on space frame) DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 15

  16. Cryomodule Alignment 3 • Complete cryomodule assembly (access ports for checking alignment) • Transfer alignment to vacuum shell (fiducial features outside shell) • Align cryomodule in APS, support stand adjustment of cryomodule in place • Perform low power beam test and use active alignment to positions cavities and optimize alignment • Remote alignment concept • (4) Nitronic rods support the cavity • External mechanical adjustment • Allows for 2 mm movement of each rod Cavity Nitronic rod External Remote Alignment Adjustment DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 16

  17. Cryomodule Design • Cryomodule design will be based on the SNS redesign: • Vacuum vessel will be the pressure boundary • End cans and Vacuum Shell will be pressure stamped to meet 10CFR851 • Cryogenic heat exchanger inside end can SNS First Spare HB Cryomodule Vacuum Vessel Pressure Stamped in Industry!! DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  18. SPX Cryomodule Org Chart DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  19. Interfaces • Cryomodule Installation Major Interfaces • Cryogenic system and controls • Deflecting Cavity RF System and Controls • Tunnel Utilities (Water cooling etc.) • Tunnel Alignment • Fabrication Interfaces • ANL will provide the HOM/LOM loads and waveguides • ANL will provide RF cables and instrumentation and safety controls DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  20. SPX Cryomodule Risks / Contingency • Stability of cryomodule performance in ring operations does not meet APS beam availability or quality expectations • Mitigation: SPX-0 ring test should identify critical issues and the schedule will allow time for resolution of these issues before production modules are needed • Alignment of cavity electrical centers after cool down can not be compensated with the remote alignment scheme • Mitigation: Removal and rework of cavity alignment possible if tunnel adjustment of cavity alignment unsuccessful • Cavity performance degraded due to contamination • Mitigation: Cavities are independently driven by RF and an individual cavity voltage can be compensated by the other cavity voltages first order • Mitigation: Helium and plasma processing can be applied during maintenance periods to gain back performance DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  21. Cryomodule ES&H • Integrated Safety Management System (ISMS) • APS-U Project following Argonne’s ISMS program requirements • Argonne Integrated Safety Management System (ISMS) Description recently revised and submitted to DOE ASO • Describes framework for integrating ESH requirements with mission objectives • References Argonne LMS procedures which implement specific portions of the ISMS • General Safety Requirements for SPX Cryomodule Design and Fabrication • Cryomodule must comply with 10 CFR 851 worker safety and health requirements • Pressure safety ASME Boiler and Pressure Vessel Code • ASME B31.3 pressure piping • Vacuum safety • Ionizing radiation safety • ANL Safety Requirements • Jlab Safety Requirements DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  22. BOE Contingency – 1.02.01.03 & 1.03.03SPX Cryomodules / Cavities DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012 22

  23. SPX Cryomodules Value Engineering • The cryomodule vacuum shell design will be a modified SNS design where pressure vessel design is applied to this component (fabricated and pressure stamped from industry) • Existing VAT RF shielded valves will be used for the warm and cold valves (off the shelf) DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  24. Cryomodule Cost Summary Chart by FY Design and Fab SPX-0 Testing of SPX-0 Procurement and Fab of SPX Cryomodules Commissioning of SPX DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  25. Work between CD-2 and CD-3 • Complete the SPX Cryomodule Design • Develop Cavity Remote Alignment Design and Procedure • Develop the Engineering Design and Document • Procure all Cryomodule Major Components • Fabricate and Deliver SPX-0 Cryomodule DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

  26. Summary • The critical design concepts for the SPX Cryomodule will be fully tested during the SPX-0 R&D phase • What is learned from the SPX-0 testing will provide the guidance for SPX cryomodule design improvements and the operational knowledge to provide stable operation for an APS installation • SPX Cryomodule Design Concept is well underway • All significant technical issues are being addressed • We are ready for CD2 DOE Lehman CD-2 Review of the APS Upgrade Project 4-6 December 2012

More Related