Clean Development Mechanism: Synergies with ESCO Business

Clean Development Mechanism: Synergies with ESCO Business International Conference on ESCO Opportunities in India 1-2 June 2005 Presented by: Mohan Reddy, Director, ZenithEnergy (Hyderabad) Urs Brodmann, Partner, Factor Consulting + Management, Zurich www.zenithenergy.com www.factorag.ch.

asta
Télécharger la présentation

Clean Development Mechanism: Synergies with ESCO Business

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Clean Development Mechanism: Synergies with ESCO Business International Conference on ESCO Opportunities in India1-2 June 2005 Presented by:Mohan Reddy, Director, ZenithEnergy (Hyderabad)Urs Brodmann, Partner, Factor Consulting + Management, Zurichwww.zenithenergy.comwww.factorag.ch

  2. STRUCTURE OF PRESENTATION • Introduction to CDM • CDM Market – Status and Prospects • CDM Opportunities in ESCO Business

  3. Kyoto Protocol global reduction of greenhouse gases by 5.2% (1990 - 2010) reduction commitments by developed (Annex 1) countries National Policies direct regulations market instruments enterprises: incentives and/or obligations to reduce net emissions of greenhouse gases direct reductions indirect measures Options technicalmeasures Joint Implemen-tation Clean Development Mechanism International Emissions Trading CDM and the Kyoto Protocol

  4. Annex I Country Joint Implementation ( between Annex I Countries ) Emission Reduction Units sharing ERUs CDM vs. JI Clean Development Mechanism (CDM) ( Annex I / Non-Annex I) Certified Emission Reductions CERs

  5. Baseline project Baseline emissions 30'000 ( t / year ) 20'000 Certified Emission Reductions (CERs) 2 CO 10'000 Project emissions 0 1 5 10 15 year CDM project crediting time Emission Reductions in CDM Projects

  6. CDM Statistics (15 May 2005) • Projects registered: 5 • 1 landfill gas capture, Brazil • 2 small-scale hydro energy, Honduras • 2 HFC-23 decomposition, India & Korea • Projects submitted for registration: 8 • Including 1 biomass power generation in India • Including 3 projects under review by CDM EB • Projects submitted to CDM EB for approval of baseline methodology: 115

  7. CDM Project Cycle CDM ExecutiveBoard ProjectOwner Project Idea Registration Project Owner Monitoring ofEmission Reductions* ProjectOwner Project Design Document Operational Entity Verification & Certificationof Emission Reductions* DNA Host Country Approval CERIssuance * CDM ExecutiveBoard ApprovalBaseline Methodology* * CDM ExecutiveBoard Operational Entity * periodically during crediting time* * unless approved method. is used Validation

  8. Timing of CDM and Conventional Project Cycle

  9. CDM Additionality Tool (Large-Scale Projects)Adopted by CDM Executive Board, Oct. 2004 A CDM project is additional if it is not the baseline scenario, i.e. the project would not happen without the CDM incentive. • Step 0: Eligibility for “early CDM” • Step 1: Identify lawful project alternatives • Step 2: Investment analysis, or • Step 3: Barrier analysis • Step 4: Common practice analysis • Step 5: Impact of CDM Registration

  10. Crediting Periods; Timing • CERs can be generated as from now: • Banking by buyer for use towards compliance in 2008-12 • Banking by project proponent for sale in later years • Start of crediting period: • Usually the later of (i) CDM registration, and (ii) start of project operation • Emission reductions achieved since 2000 can be credited under certain conditions (demonstration of additionality, registration before end of 2005) • Duration of crediting periods: • Fixed crediting period of up to 10 years, or • Renewable crediting periods of up to 7 years (maximum = 3 x 7 years)

  11. Small-Scale CDM Projects • Size limits for for small-scale projects: • Electricity generation from renewable sources, up to 15 MW • Energy efficiency projects saving up to 15 GWh p.a. • Projects reducing, and emitting themselves, up to 15,000 t CO2e p.a. • SSC projects benefit from simplified rules and procedures: • Simplified PDD • Simplified additionality test: Demonstrate that barriers would have led to higher emissions in absence of CDM • 15 pre-approved baseline methodologies (as per 15 May 2005) • Same operational entity may undertake validation and verification / certification

  12. STRUCTURE OF PRESENTATION • Introduction to CDM • CDM Market – Status and Prospects • CDM Opportunities in ESCO Business

  13. Current Market Volume for project-based emission reductions Jan–May Source: World Bank State of the Carbon Market, 2005

  14. Current Market Prices for CDM/JI Credits • Average price in 2004: 5.6 €/t CO2e • Source: World Bank, State and Trends of Carbon Market 2005 • Prices are for forward trades • Typical price range for CERs: 4-7 €/t CO2e • Risks and their distribution are key for CER price: • Risk relating to CDM registration of project • Counterparty risk: Credit rating of seller and buyer • Whether partial upfront payment is made • Penalties in case of non-delivery

  15. Locations of Emission Reduction projects by share of volume Jan 2003 – Dec 2004 Jan 2004 – April 2005 Source: World Bank State of the Carbon Market, 2005

  16. Current Demand (May 2005) on CDM and JI market for Selected Major Buyers (million $) Source: Environmental Finance, May 2005, plus own research • Total CDM/JI demand currently: over USD 2 billion • Graph excludes corporate OTC demand

  17. STRUCTURE OF PRESENTATION • Introduction to CDM • CDM Market – Status and Prospects • CDM Opportunities in ESCO Business

  18. Selection of Approved Methodologies Relevant for ESCO Business

  19. Selection of Approved Methodologies Relevant for ESCO Business (2) • ACM0002: Consolidated baseline methodology for grid connected electricity generation from renewable sources Approved small-scale methodologies e.g: • AMS II.D: Energy efficiency and fuel switching measures for industrial facilities • To qualify for this small-scale methodology, aggregate energy savings should not exceed 15 GWh per year • AMS III.B: Switching fossil fuels • To qualify for this small-scale methodology, measures should directly reduce, and emit, less than 15,000 t CO2e annually

  20. Energy Efficiency Measures:Potential for CDM (Illustration) Ideal measures for CDM:CERs needed to reach benchmark (#3), or to mitigate financial risks (#2)

  21. CER Ownership • In CDM projects, the owner of the installation generating the emission reductions typically owns the CERs • E.g., a CDM project for demand-side saving of electricity delivers CERs to the company taking the efficiency measures • In ESCO schemes, ownership of CERs can vary • The contractor (ESCO firm) or the contracting company (client) can be the primary owner of the CERs, depending on precise arrangement • CDM can increase the viability of energy efficiency measures, irrespective of ownership issues • Details of CER ownership need to be addressed in contractual framework for ESCO schemes

  22. Conclusions • CDM can increase the financial viability of ESCO schemes • A real demand for carbon credits has emerged internationally • India is likely to become a leading seller of carbon credits • Relevant project types: energy efficiency and renewable energy • The additionality criterion restricts the range of CDM-eligible measures • Measures “on the margin” (i.e. just below critical profitability threshold) are best suited for CDM: Can be lifted above threshold by carbon revenues • CDM eligibility should be carefully assessed by professionals at the outset of any relevant activity • CDM transaction costs are relevant but not prohibitive • CER ownership issues need to be addressed under ESCO schemes • CDM baseline & monitoring methodologies allow for quantification of energy savings using internationally accepted protocols • CDM is an opportunity worth a try for any ESCO firm

  23. Thank You Factor Consulting + Management AG Switzerland www.factorag.ch ZenithEnergy Hyderabad, India. www.zenithenergy.com

  24. Timeline • Project Design Document • Large scale : 2 to 3 months • Small scale PDD : 1 to 2 months • Host country approval : 2 to 4 months • Validation • Adopt an approved methodology : 2 to 4 months • Propose a new methodology : 6 to 12 months • Small scale PDD : 2 to 4 months • Registration • Large scale : 8 weeks after submission unless revision is requested by the parties • Small scale PDD : 4 weeks after submission unless revision is requested by the parties

  25. Transaction Costs • Transaction costs are those investment which the project proponent shall invest to monetize the CDM Benefits. • Transaction costs mainly include • Costs towards consultants for developing CDM project (PDD) • Costs towards validation of the CDM project • Costs towards registration of the CDM project with EB • Costs towards monitoring of emission reductions • Costs towards verification of CERs and transaction costs • Apart from the above, CDM EB deducts 2% of the CDM revenues to Adaptation fund. • Any other expenses as incurred by the project proponent towards CDM development • Transaction costs varies between 5% to 25% of the total revenues depending on the type and size of the project.

  26. Estimated full market potential till 2012 Source: World Bank, IEA, IETA (2004) • Assumptions: • Countries such as Canada and Japan which have ratified Kyoto actually strive to meet targets • No participation of Australia and the United States • Restricted sales of surplus Kyoto units by Russia and the Ukraine. • Demand for CERs in 2010 of 250 Mt CO2e (range 50 to 500 Mt CO2e) • Price 2010: $11.00 /t CO2e (range +/- 50%). • Total demand of 1'250 Mt CO2e by 2012 (cumulative). • Failure to ensure a market value for post-2012 emission reductions would limit the CDM to an annual supply of 50 to 90 MtCO2e in 2010; and to total supply of 250 to 450 Mt CO2e up to 2012.