All-Pairs Shortest Paths (26.0/25)

All-Pairs Shortest Paths (26.0/25). HW: problem 26-1, p. 576/25-1, p. 641 Directed graph G = (V,E), weight E   Goal: Create n  n matrix of s-p distances (u,v) Running Bellman-Ford once from each vertex O( ) = O( ) on dense graphs

atalo
Télécharger la présentation

All-Pairs Shortest Paths (26.0/25)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. All-Pairs Shortest Paths (26.0/25) • HW: problem 26-1, p. 576/25-1, p. 641 • Directed graph G = (V,E), weight E   • Goal: Create n  n matrix of s-p distances (u,v) • Running Bellman-Ford once from each vertex O( ) = O( ) on dense graphs • Adjacency-matrix representation of graph: • n  n matrix W = (wij) of edge weights • assume wii = 0 i, s-p to self has no edges in absence of negative cycles

  2. Dynamic Programming (26.1/25.1) • dij(m) = weight of s-p from i to j with  m edges dij(0) = 0 if i = j and dij(0) =  if i  j dij(m) = mink{dik(m-1) + wkj} • Runtime = O( n4) because n-1 passes each computing n2 d’s in O(n) time  m-1 j i  m-1

  3. Matrix Multiplication (26.1/25.1) • Similar: C = A  B, two n  n matrices cij = k aik  bkj O(n3) operations • replacing: ‘‘ + ’’  ‘‘ min ’’ ‘‘  ’’  ‘‘ + ’’ • gives cij= mink {aik + bkj} • D(m) = D(m-1) ‘‘ ’’ W • identity matrix is D(0) • Cannot use Strassen’s because no subtraction • Time is still O(n  n3 ) = O(n4 ) • Repeated squaring: W2n = Wn Wn Compute W, W2 , W4 ,..., W2k , k= log n, O(n3 log n)

  4. Floyd-Warshall Algorithm (26.2/25.2) • Also dynamic programming but faster (by log n) • cij(m) = weight of s-p from i to j with intermediate vertices in the set {1, 2, ..., m}  (i, j)= cij(n) • DP: compute cij(n) in terms of smaller cij(n-1) • cij(0) = wij • cij(m) = min {cij(m) , cim(m-1) + cmj(m-1) } intermediate nodes in {1, 2, ..., m} cmj(m-1) m cim(m-1) j i cij(m-1)

  5. Floyd-Warshall Algorithm (26.2/25.2) • Difference from previous: we do not check all possible intermediate vertices. • Code: for m=1..n do for i=1..n do for j = 1..n do cij(m) = min {cij(m-1) , cim(m-1) + cmj(m-1) } • Runtime O(n3 ) • Transitive Closure G* of graph G: • (i,j)  G* iff  path from i to j in G • Adjacency matrix, elements on {0,1} • Floyd-Warshall with ‘‘ min ’’  ‘‘OR’’ , ‘‘+’’  ‘‘ AND ’’ • Runtime O(n3 ) • Useful in many problems

  6. Johnson’s Algorithm (26.3/25.3) • Johnson’s = Bellman-Ford + Dijkstra’s (or Thorup’s) • Re-weighting of the graph G=(V,E,w): • assign weights to all vertices h: V   • change weight of edges w’(u,v) = w(u,v) + h(u) - h(v) • then for any u,v: ’(u, v) = (u,v) + h(u) - h(v) • Addition of auxiliary vertex s: • V  V + s • E  V + {(s,v), v  V} , w(s,v) = 0 • Run Bellman-Ford: find h(v) = (s,v) (or negat. cycle) • w’(u,v)  0 since h(v)  h(u) + w(u,v) and w’(u,v) = w(u,v) + h(u) - h(v)  0

  7. Johnson’s Algorithm (26.3/25.3) • Since all weights are nonnegative, apply Dijkstra’s for each source and find all modified distances ’(u, v) • Restore actual distances from modified using (u, v) = ’(u,v) - h(u) + h(v) • Runtime: • O(VE) = V times O(E) - M.Thorup’s algorithm • O(V(E+V log V)) = V times Dijkstra’s with Fibonacci heaps • O(VE log V) = V times Dijkstra’s with binary heaps (faster for sparse graphs) • To find s-p for a single pair = s-p from single source = all pairs shortest paths.