1 / 16

Feasibility Study Cost Estimates

Feasibility Study Cost Estimates. ©2002 Dr. Bradley C Paul. Feasibility Study. Processes are actually worked out and planned checked for technical flaws checked for permit flaws Format Pre-feasibility may give you a lot of factored cost estimates

bailey
Télécharger la présentation

Feasibility Study Cost Estimates

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Feasibility Study Cost Estimates ©2002 Dr. Bradley C Paul

  2. Feasibility Study • Processes are actually worked out and planned • checked for technical flaws • checked for permit flaws • Format • Pre-feasibility may give you a lot of factored cost estimates • Start Shifting big ones to itemized cost estimates • Itemized estimates become more detailed

  3. Feasibility Study Overviews • Major Cost Items are Identified • Quotes are secured on major cost items • Minor items tend to be listed with general comparison cost estimates attached. • Important error avoid - missing and double counting.

  4. Pre-Feasibility/ Feasibility Contrast • Major Cost Items from Pre-Feasibility move either to Itemized Cost format or are expanded • Example - Our Mine Shaft could easily be a big cost • Advance rate likely to be 8 feet per day using 3 eight hour shifts in solid • Only get 2 feet day through first 200 feet of unconsolidated • Lets Detail the crew

  5. Shafting Crew • Typical Sinking Crew would be 5 people • 4 laborers – 1 supervisor • doing rounds, support ect. (from SERPA) • wages $15.46/hr (1997 base from WMCS) • 4*24*$15.46 = $1,484/day • Time 100 days for first 200 ft • 69 days more for next 550 ft through solid rock • 169 days at $1,484/day = $250,823 • I’ll deal with supervisor later

  6. Support People • Engineering/Technical Crew • 1 person (some would use 2) (3 for 3 shifts) SERPA • $16.15/hr 1997 cost WMCS • $388/day * 169 days = $65,504 • Mechanical Crew • 2 people (6 for 3 shifts) SERPA • $20.98/hr 1997 cost WMCS • $1007/day*169 days = $170,190

  7. Surface Crews • Surface and Yard Workers 2 • Rate $11.89/hr • 2*$11.89*24*169 = $96,452 • Sinking Hoist Operator • $16.50/hr*24*169 = $66,924

  8. Supervisory Crews • 1 supervisor/shift $23.94/hr • $23.94*24*169 = $97,101 • Total Labor Cost • $746,994 say $747,000 • Indexing Labor • $747,000* 17.89/16.15 = $827,500

  9. The Burden of Burden • Workers get fringe benefits • health, vacation time etc. • government mandated programs • social security / medicare / unemployment / workers compensation • Often Expressed as a percentage of wage • Quarries around 30% • Metals commonly around 40% • Some coal may be 60% • WMCS estimates 36% for Shaft Sinking

  10. Dropping the Burden on the Project • $827,500 * 1.36 = $1,125,000 • Explosives Cost • Rounds at 4 lbs/ton • Need to know concrete thickness • have about 15 inch thick (some squeeze for horizontal stress) • for 20 ft finished diameter - need 22.5 feet • with some over-excavation 23 feet • Rock density about 170 lb/ft^3 • 35.3 tons per foot of Advance

  11. Having a Blast • 35.3 tons/ft * 4 lbs/ton = 141 lbs of explosive per foot of advance • 106,000 lbs @ $1.54/lb = $163,000 • At about 1 round shot/day • 110 caps/day * 169 days = 18,590 caps • @$1.81 each = $33,650 • Chord and Supplies about 50% of caps (no boosters here) • $16,824

  12. Breaking Cost • $213,500 for explosives • Drilling Consumables at about 25% of explosives • $53,400 • Breaking Cost (less labor counted elsewhere) • $267,000 • Index to end 2002 • $267,000 * 149.7/149.1 = $268,000

  13. Non-Labor Mucking Costs • At $2.50/ton (include disposal) • 35.3 tons/ft * $2.5 = $88.30/ft • for 750 ft $66,216 (current cost) • Concrete Cost • 23 ft outside diam - 20 ft inside • 3.75 cubic yard per foot of advance • Concrete at $80/cubic yard delivered to site • $225,000 for concrete

  14. Other Supplies • Steel cost at about 1.5 times concrete • $337,500 • includes materials to advance utilities down shaft and put in guides for skips • Concrete and Steel • $562,500 • 10% for misc supplies • $56,250 total • Supplies Subtotal $618,750

  15. Direct Cost of Shaft • Labor $1,125,400 + Breaking $268,000 + Mucking $66,200 + Supplies $618,750 • $2,078,350 • 10% contingency $2,286,200 • 15% contractor mark-up and mobilization • $2,629,000 • Note that we did consider some site specific problems with large amounts unconsolidated Overburden and ground stresses

  16. Pre-Feasibility / Feasibility Contrast • At Order of Magnitude just scaled off of someone elses approximate cost • Pre-Feasibility was either a factored cost estimate or a simple itemized cost estimate (ie cost per foot of shaft) • At Feasibility stage it became a much more carefully itemized exercise • we were still flakey on cost of service lines pipes • As move to Budget Authorization likely bring in contractors to bid specifically on the job

More Related