Data Communications Program

Data Communications Program. DCL Trials DCIT Update MEM ATCT. To: DCIT Plenary From: Matt Maki Date: 12.06.2012. Agenda. DTAP Development Status: DTAP Development/Milestone Deliveries Trials Schedule Update On-Going / Completed Trials Activities Status: DTAP Certification

baina
Télécharger la présentation

Data Communications Program

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Data Communications Program DCL Trials DCIT Update MEM ATCT To: DCIT Plenary From: Matt Maki Date: 12.06.2012

  2. Agenda • DTAP Development Status: • DTAP Development/Milestone Deliveries • Trials Schedule Update • On-Going / Completed Trials Activities Status: • DTAP Certification • MEM Training & Procedures • Trials Metrics Development • Trials CSP Service Update • EWR Trials – Schedule/Planning Discussion

  3. DTAP Milestone Deliveries • SE2020 Deliverables / DTAP Development: • Limited Trials Build undergoing Functional Testing @ WJHTC • Fixes previous HIGH/MED-HIGH level PTRs • Installed @ MEM ATCT 12/3 for continued Functional /FDX-UPS Testing • CAF, UM80, UM79 (Non INT), AOC DM (non SI Doc compliant) • Full Trials Build scheduled estimated for delivery to the WJHTC on Jan 22 • Initial UM79 requirement included (ERAM FIR Boundary limits) • UM83 and discovered ‘out of scope’ minimum Trials requirements included • Additional requirements from testing included • Represents ‘full fleet’ Trials functionality

  4. MEM Limited Ops Trials (~ 3 Ops/Day - 2 Weeks) • Nov 27: • Limited Ops Build installed on WJHTC Data Comm lab DTAP • Limited Ops Build installed on designated Training DTAP3 • Dec 3-14 (WJHTC & MEM Functional/Pre-SAT Testing) • Limited Ops Build installed on MEM ATCT DTAP • Limited Ops Build Functional Testing @ MEM ATCT (Bench and FDX/UPS aircraft avionics planned) • Limited Ops Build WJHTC Functional Test summary review • Dec 17-20 Boeing / Airbus Bench Testing Window • Dec 24-Jan 1 (Holiday Break) • Jan 2-7: - OT2 @ MEM (Jan 2) • Limited MEM ATC Training (DTAP3 Training machine) • Formal MEM SAT (Jan 3-4) • Trials Start Checkpoint – Go/No Go (Jan 7) • Jan 7-21: Buffer • Jan 22 – TRIALS START (Jan 14 Target Start Option)

  5. MEM Limited Ops Trials Timeline Functional Testing @ WJHTC & MEM 11/27 – 12/14 Additional Functional Testing BUFFER 12/14 – 12/24 Holiday Break 12/24 – 1/2 OT2, ATC Training, SAT @ MEM 1/2 – 1/7 BUFFER 1/7 – 1/21 Limited Ops Trials Window (TBD Ops/Day – 2 Weeks) 1/22 – 2/10 FEB DEC NOV JAN

  6. MEM Full Functionality Trials Ops • Dec 10-17: • Final DTAP SE2020 Contract Build 6 Requirements/Delivery Date Implementation • Jan 22-Feb 6: • Full Functionality Build installed on WJHTC DTAP – Functional Testing Window • FDX Pilot Training 30 Day Notice Given (FF Build Accepted for Trial Ops – 2/4) • Jan 29-Feb 8: -Conduct OT3 @ MEM (1/29) - Conduct Formal ATC DTAP Training @ MEM • Feb 10-Feb 15: - END OF LIMITED OPS TRIALS (2/10) • Install Full Functionality Build on MEM DTAP (2/11) • Pre-SAT, Functional Testing Activities • FDX GOC Training 2 Week Notice Given • Feb 18-22: • Formal Full Functionality Build SAT @ MEM • Full Trials Go/No-Go Checkpoint (2/22) • March 4: FULL FUNCTIONALITY TRIALS START ~50 flights (2/25 Target Start Option) - Trials Procedures Shake Out

  7. MEM Full Functionality 24x7 Ops Trials • April 4 MEM Full Fleet Trials • Starts 120 Day Trials Review Checkpoint Timer

  8. MEM Full Ops Trials Timeline FDX Pilot Training 30 Day Notice – 2/4 FDX GOC Training 14 Day Notice – 2/15 Functional Testing @ WJHTC 1/22 – 2/6 End of Limited Ops Trials, MEM DTAP Upgrade 2/10 – 2/15 SAT @ MEM, Trials FF GO Checkpoint 2/18 – 2/22 Buffer Full Functionality Trials Start, Procedures Shake Out (~50 DCL Flights) 3/4 – 4/4 Full Functionality 24x7 Trials Ops 4/4 + 120 Days OT3 & ATC Training @ MEM 1/29 – 2/8 APR FEB MAR JAN

  9. Tech Ops DTAP Certification • Certification on Track to enable Trials start: • Tech Ops reps completed draft DTAP Certification procedures at the WJHTC lab on 10/10 & 11 • Procedures / FAM Training complete • AJW-13 to propagate Notice to field / trials sites • FSEP office notified FTI that Cert / FAM procedures are satisfactory: • Allows FSEP DTAP log entry & FTI check-off • Train MEM Tech Ops Scheduled for December 17: • Trained MEM Tech Ops reps credentialed via District Mgr.

  10. MEM Training and Procedures • MEM Training and SAT Procedures complete: • Limited MEM DTAP Training scheduled for Jan 2-7 2013 • Full MEM DTAP Training planned for Jan 29 – Feb 8 • MEM Trials SAT draft released for internal review 12/3 • FDX Training: • FDX AOC/Dispatch training (2 weeks advance notice req) • FDX Pilot training (30 day advance notice req) • FAA CMO LOA (2 weeks advance notice req)

  11. Trials Metrics Development • DTAP log file analysis underway: • Thales to provide tools for decoding/presenting DTAP log file data • Summary Trials data analysis planned • DCIT Plenary Update • Independent Safety Assessment Office (AJI-321) planning Trials evaluation and analysis: - Trials team to provide ISA with Trials procedures, metrics and test plans

  12. Trials CSP Service Update • ARINC/SITA Current Agreements: • ARINC Trials service being extended from current 12/31 POP end • Additional ARINC extensions available if required • SITA service contract extended on month x month basis

  13. EWR Trials Schedule/Planning • Verify limited Trials start @ EWR can commence before the MEM 120 day review checkpoint • EWR Trials Start in April is a challenge for DCP: • EWR ATC accepts final MEM DTAP functionality for initial Trials implementation (Dec, DCIT Ops Mgt) • EWR CHI functionality updated utilizing a TBD DTAP release • EWR May-Sept Implementation Freeze Out • EWR Trials Implementation Activities Underway: • Meeting at facility with ATC and Tech Ops Mgt (12/17) • FTI Telco/Network Connectivity Order Initiated • DTAP ZNY HADDS/OARS interface configuration Initiated • HADDS, FDIO Test NCP development Initiated • Equipment Implementation goal in March • Initial operators include UAL, FDX, UPS, LFT

  14. Questions ? KMEM