The Calorimeter of the T2K-ND280 Detector System

The Calorimeter of the T2K-ND280 Detector System. Athans Hatzikoutelis Lancaster University UK June 24, 2009. Outline. The T2K (Tokai to Kamioka) experiment. The ND280 (Near Detector) Project. The Electro-magnetic tracking calorimeter. The current sub-systems The future. 2.

barton
Télécharger la présentation

The Calorimeter of the T2K-ND280 Detector System

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Calorimeter of the T2K-ND280 Detector System AthansHatzikoutelis Lancaster University UK June 24, 2009

  2. Outline • The T2K (Tokai to Kamioka) experiment. • The ND280 (Near Detector) Project. • The Electro-magnetic tracking calorimeter. • The current sub-systems • The future. 2 A. Hatzikoutelis , T2K Collaboration

  3. The T2K experiment • Tokai-to-Kamioka neutrino oscillation experiment appearance of electron neutrinos in a muon neutrino beam • 30 GeV protons of 750 kWproduced at the new JPARC complex • integrated exposure of 100 kW*1e7 s starting in April 2009. 3 A. Hatzikoutelis , T2K Collaboration

  4. Key measurement in ν physics • A positive measurement of sin2(2θ13) > 0.01 • possibility to study CP violation in the lepton sector • the determination of the neutrino mass • hierarchy with upgraded conventional super-beams • No evidence for sin2(2θ13) • trigger intense discussions on how to best proceed below sin2(2θ13) ≈ 0.01 4 A. Hatzikoutelis , T2K Collaboration

  5. The Near detector • Understand the neutrino beam. • On – Axis Detector • Beam monitoring • Beam direction • Off – Axis Detector • Understand the neutrino beam to SK. • Beam Flux • Beam ne Contamination • Background Processes • Cross Sections neutrino beam On-axis Detector INGRID 5 A. Hatzikoutelis , T2K Collaboration

  6. Off-axis technique J-PARC  n p Off-axis Near Detector Far Detector (SK) Target 2.5º • Intense & narrow-band beam • 2.5º off-axis • Energy peak ~ 0.7 GeV • Statistics at Far Detector • ~1600 nm CC int./22.5kt/year (0.75 MW beam, no oscillation ) • Purity of nm beam • Beam ne contamination ~0.4% at nm peak energy • Running time: 5 years @ 750 kW proton beam intensity m &Horns On-axis detector Decay pipe Muon monitor Near Detector 0m 120m 280m 295 km Oscillation Prob. @ Dm2 = 3.010-3 n energy spectrum (Flux X-section) OA0 OA2 OA2.5 OA3 6 A. Hatzikoutelis , T2K Collaboration

  7. Off-axis detector • Arrays housed in UA1 magnet with 0.2 T. 280 m downstream of the target operators 7 A. Hatzikoutelis , T2K Collaboration

  8. Five detector arrays • Pi-zero Detector (PØD) • measures NC p0 interactions. • Tracking System: • fine-grained detector (FGD) • time projection chambers (TPC) • Targets of 16O and 12C for the v. • Measure CC interactions. • Electromagnetic calorimeter (ECAL). • Total energy and particle id. • Side muon-range detector (SMRD). • Cosmics veto. • Side-going muon id. 8 A. Hatzikoutelis , T2K Collaboration

  9. P0D • Active Scintillator Neutrino Target • water + scintillator • NC π° • reconstruction efficiency ~30% • signal to noise ~2.3 • E&M resolution ~15%/√E (GeV) • Is build and being installed • Primary Measure Goals • NC and CC π° production ν Simulated 440 MeV/c π˚ Distance in P0D 9 A. Hatzikoutelis , T2K Collaboration

  10. 2.5 m 2.5 m TPC FGD tracker detectors • 3D tracking for pattern recognition. • Measure momenta and charge of charged particles • Distinguish electrons and muons/pions and protons. • B=0.2 T . • Micromegas technology was selected to provide the gas amplification for readout νμ 10 A. Hatzikoutelis , T2K Collaboration

  11. Down-stream Calorimeter • After the tracker detectors. • Perpendicular to the v beam. v beam DsEcal 11 A. Hatzikoutelis , T2K Collaboration

  12. Calorimeter 4x2 m2 x 0.5 m • Energy resolution from simulations. • Dominated by sampling fluctuations. • Est: 7.5% √E(GeV). • up to 5 GeV. • Good electron pion separation. • 90% elec efficiency with • 95% pion rejection. Barrel EcaL P0D Ecal FGD & TPC trackers DsEcal 2x2m2 x 0.5 m P0D v beam P0D Ecal Barrel Ecal 12 A. Hatzikoutelis , T2K Collaboration

  13. Calorimeter : General Design • Multiple layers of scintillator lead. • Extruded plastic from Fermi National Labs. • Similar to K2K-Scibar and Minos. • X-Y orientation change between even and odd numbered layers. • One Y11 Kuraray fibre (WLS) per bar. • Double- and single-ended photo-sensor readout per fibre. • MPPC from Hamamatsu. • 1st large deployment. Plastic scintillator Bar: 4cmx1cmx200cm Centre hole :1mmx2mm elliptical 13 A. Hatzikoutelis , T2K Collaboration

  14. Light Attenuation • Dominated by the properties of the fibers. • Tested with cosmics and 137Cs as function of distance from the end. • Light yield ~ 12.5pe/mip (with PMT) • The solid curves are double exponentials of attenuation lengths. • Short=0.52m, • Long= 4.2m • Each channel of the calorimeter • Individual check (qual. assur.). • Labeled and logged. • Construction and calibration database. The errors in distance-axis come from the size of the trigger-scintillator pads. Radiation source activating a scintillator • MPPC readout : • integral of current output 14 A. Hatzikoutelis , T2K Collaboration

  15. The P0D Ecal The Barrel Ecal • Surrounds the P0D array. • Detects escaping photons, muons. • 6 scintillator bar layers. • 4 lead sheets 5mm. • 4 X0 radiation lengths. • Single-ended readout. • Low requirement for energy and spatial resolution. • Effective depth. • Surrounds the tracking detectors. • Measures particles that leave the volume. • Separated in 6 parts to move with the opening of the magnet. • 32 scintillator bar layers thick. • 31 lead sheets x 1.75mm • 10.5 X0 radiation lengths. • 18,000 double- and single-ended readout. • Good reconstruction efficiency for pions. • Good spatial resolution for photons. 15 A. Hatzikoutelis , T2K Collaboration

  16. ECAL construction(DsEcal example) • The first part of the Ecal to be constructed. • Area 2 x 2 m 2 • 34 scint-lead layers, 1.75mm lead sheets. • 11 X0 radiation lengths. • 3400 double-ended readout. • Kuraray Y11, straight canes 16 A. Hatzikoutelis , T2K Collaboration

  17. Photo sensors • MultiPixel-PhotoCounters. • 100~1600 small avalanche photo diodes( APD ) • 1.3mm2 sensitive region. • Magnetically unaffected. • New device, first large scale deployment. • 50,000 in ND280. • 23,000 for the Ecal. • Each individually checked and labelled. Sensitive region of MPPC 400pixel type 50 micron 2 50 micron 2 17 A. Hatzikoutelis , T2K Collaboration

  18. Basic performance of MPPC MPPC raw signal • Twice the PDE (efficiency) than PMT’s. • We can observe 1p.e, 2p.e, etc, signal peaks. • High noise rate , ~80kHz. prototyped and characterized at Kyoto univ. 1pe 2pe 3pe 4pe? Pedestal 1pe Digitized MPPC signal 2pe 3pe 18 A. Hatzikoutelis , T2K Collaboration

  19. Light Injection System Top view Side view • Monitoring MPPC gain and fibre integrity. • Positioned in the cavity between the detector frames and the bulkhead. • Specifically tuned driver boards. • Illuminate uniformly the exposed fibres. Drive boards Layer 001 WLS fiber LED strips Layer 001 Layer 001 19 A. Hatzikoutelis , T2K Collaboration

  20. http://www.hep.lancs.ac.uk/~scanner/T2KPIX/pix070708/SS850481.AVIhttp://www.hep.lancs.ac.uk/~scanner/T2KPIX/pix070708/SS850482.AVIhttp://www.hep.lancs.ac.uk/~scanner/T2KPIX/pix070708/SS850481.AVIhttp://www.hep.lancs.ac.uk/~scanner/T2KPIX/pix070708/SS850482.AVI 137Cs Module Scanner Y x • Programmable motor control. • Sliders give the arm motion in two dimensions. • Arm places the source 14mm from top of lead sheet of layer. • 3mCu 137Cs source. • Run along each bar. • Define the detector limits. Scan direction Quick return 20 A. Hatzikoutelis , T2K Collaboration

  21. Front –End Readout • 4 Trip-t chips. • Ethernet 1MB comm. • 64 channels per front-end board. • 2 ADC and 1 TDC output per channel. • All power and cooling on board. 21 A. Hatzikoutelis , T2K Collaboration

  22. Commissioning cosmics RAL ISIS Hall • Hardware Commissioning • Commissioning of the data acquisition and light injection systems. • Tuning the cosmic trigger. • Software Commissioning • Indicative spectrum of cosmics • Bar (arbcoice) at the center of the calorimeter • over 16 hours at 55Hz Low energy noise from the MPPC m.i.p. signal distribution. Mean 25 p.e. ADC chn (arb units) 22 A. Hatzikoutelis , T2K Collaboration

  23. Hit density distribution (Hit-map) Top view cosmic • Tuning the cosmic trigger. • Calibration of all channels and pixels with cosmic muons. • Self-triggered on the front half. x Front cosmic Side view Front, cosmic Front 40000 cosmic triggers sample 23 A. Hatzikoutelis , T2K Collaboration

  24. Tuning Reconstruction& PID. First physics analysis using observed data Calibration with cosmics Iso-view Left TOP Event dispaly of cosmic muon (2-4MeV) The bars that are hit are clearly lighted up with Signal clearly above the MPPC noise. 24 A. Hatzikoutelis , T2K Collaboration

  25. Test-beam @ CERN CERN , PS, T9, pions,muons,electrons • Calibration with test-beam. • CERN T9 beam-line at East area Hall. • Library of clean data profiles at energies 0.4 to 4GeV. • hadronic and • electromagnetic shower Beam composition (%) electrons pions prelim. Beam energy (GeV) 25 A. Hatzikoutelis , T2K Collaboration

  26. ECAL PID • Particle Identification algorithm • uses an artificial neural network. • discriminate between electromagnetic showers, hadronic showers and tracks. muon + pion, 3.2GeV shower 3d event view collected on test-beam run of May 7 ‘09 26 A. Hatzikoutelis , T2K Collaboration

  27. particle id with ECAL(preliminary) Simulated medium energy electron shower. Event display of beam electrons Medium energy Beam e side view 600MeV e Top view 600MeV e 27 A. Hatzikoutelis , T2K Collaboration

  28. Tracks PID (preliminary) • Tracks come from mips. • Relatively small spread in charge deposits. • narrow, • long shape • uniform charge deposition. Simulated muon 940 MeV Beam muon 800MeV 28 A. Hatzikoutelis , T2K Collaboration

  29. Pions ID in ECAL (prelim) Simulated hadronic showers Charged beam pions 1GeV Top view 3GeV Side view 29 A. Hatzikoutelis , T2K Collaboration

  30. Time cuts (prelim) Top view Clearly a pion • Charged beam 2.2GeV particles coincident in the detector. Side view Clearly a stopped muon Side view 30 A. Hatzikoutelis , T2K Collaboration

  31. 31 A. Hatzikoutelis , T2K Collaboration

  32. Conclusions 32 • The T2K experiment will measure • How small is θ13 ? • Does θ23 represent maximal mixing? • Can we search for CP violation in the lepton sector? • ND280 off-axis detector will aim to address • energy spectrum, backgrounds, neutrino interactions • The Electromagnetic calorimeter will assist the measurements by helping id the beam profile. • The first part of the Ecal is ready for calibration. • The rest of the Ecal is on target for construction. A. Hatzikoutelis , T2K Collaboration

  33. February 2006 J-PARC accelerator 50 GeV Synchrotron (MR) Neutrino beam line Neutrino beam (to Super-K) 3 GeV Synchrotron (RCS) LINAC 33 A. Hatzikoutelis , T2K Collaboration

  34. Sensitivity sin2(2θ13) < 0.01 (90%C.L.) after 5 years at nominal intensity. A plan to upgrade the power to 1.6 MW has been presented in the KEK roadmap, opening the path towards an upgraded Asian long-baseline neutrino The T2K beamlineis designed for MW power and has successfully started commissioning in April 2009 and the first • Expecetd sensitivity • sin2(2θ13) < 0.01 (90%C.L.) • after 5 years at nominal intensity. • • T2K uses high intensity 30 GeV protons produced at the new JPARC complex. • measure nm→ντdisappearance, • Atmospheric parameter q23 and Dm223(~Dm213) • search for nm ne appearance, i.e. non-zero q13 34 A. Hatzikoutelis , T2K Collaboration

  35. T2K start-up Schedule • Neutrino beam will start in Apr. 2009 • ND280 on-axis detector will be ready for data taking when n beam starts • ND280 off-axis detector will be installed by fall 2009 to be ready for data taking • A plan to upgrade the Main Ring to 1.6 MW has been presented in the KEK roadmap • These experiments are the « Phase II » 35 A. Hatzikoutelis , T2K Collaboration

  36. T2K ND280 purpose 36 A. Hatzikoutelis , T2K Collaboration