1 / 20

PLANNING FOR WIND AND QUEUE MANAGEMENT

PLANNING FOR WIND AND QUEUE MANAGEMENT. Turkish Electricity Transmission Corporation(TEIAS) prepared by Gül Okan & Nurhan Ozan. 400 kV Network. BULGAR İSTAN. KARADENİZ. DIMODICHEV. HABİPLER. BATUM. GÜRCİSTAN. BABAESKİ. HAMİTABAT. ALİBEYKÖY. AHALTSIKHE. İKİTELLİ. A.ALANI.

becky
Télécharger la présentation

PLANNING FOR WIND AND QUEUE MANAGEMENT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PLANNING FOR WIND AND QUEUE MANAGEMENT Turkish Electricity Transmission Corporation(TEIAS) prepared by Gül Okan & Nurhan Ozan

  2. 400 kV Network BULGARİSTAN KARADENİZ DIMODICHEV HABİPLER BATUM GÜRCİSTAN BABAESKİ HAMİTABAT ALİBEYKÖY AHALTSIKHE İKİTELLİ A.ALANI BOYABAT SAMSUN DGKÇ BORASCO AMASRA HOPA Y.TEPE YUNANİSTAN D.PAŞA BEYKOZ FILIPPI KAPTAN PAŞAKÖY BORÇKA EREĞLİ Z.KÖY ÇARŞAMBA GUMRI OSMANCA AMBARLI ÇANKIRI UNIMAR DERİNER ÜMRANİYE ADA-GEBZE TEPEÖREN İÇDAŞ ARKUN ERMENİSTAN KARS KARABİGA ADAPAZARI BAĞLUM YUSUFELİ KALKANDERE TİREBOLU ÇAYIRHAN H.UĞURLU KAYABAŞI ORDU-2 İSPİR SİNCAN GÖKÇEKAYA IĞDIR İÇDAŞ K.KALE DGKÇ BURSA AKINCI GÖLBAŞI AĞRI BALIKESİR ÇAN TEMELLİ SİVASDEÇEKO TUNÇBİLEK BABEK İÇANADOLU DGKÇ HORASAN KANGAL ÖZLÜCE SOMA D.BEYAZIT SEYİTÖMER ERZURUM KAYSERİ BAZARGAN VAN KEBAN KOCATEPE KHOY ELBİSTAN ALİAĞA İRAN KARAKAYA MANİSA YEŞİLHİSAR ÇETİN DİYARBAKIR KONYA HİLVAN SİİRT IŞIKLAR BATMAN DENİZLİ UZUNDERE YEDİGÖZE ATATÜRK ILISU AYDIN ANDIRIN SİLOPİ TES KAVŞAK SEYDİŞEHİR V.ŞEHİR PS3 YENİKÖY G.ANTEP Ş.URFA YATAĞAN ADANA CİZRE OYMAPINAR BİRECİK KIZILTEPE ERZİN ZAKHO KEMERKÖY ERMENEK KAYRAKTEPE IRAK MERSİN AKSA VARSAK İSDEMİR İSKENDERUN MUSUL TEİAŞ-APK 2010 TS (PLANLANAN) HATAY HALEP TS (MEVCUT) HES (PLANLANAN) AKDENİZ SURİYE HES (MEVCUT) TL (MEVCUT) TL (PLANLANAN) 220 kV EİH 154 kV EİH

  3. Profile of System (end of 2010) NUMBER OF SUBSTATIONS: 400 kV 184 (35020 MVA) 154 kV 1034 (58015 MVA) 66 kV 54 (637 MVA) TOTAL 1272 INSTALLED CAPACITY (93672 MVA) LENGTH OF TRANSMISSION LINES (km): 400 kV 14,623 154 kV 31,932 220 kV 84,5 66 kV 508,5 154 kV Cable 170,9 380 kV Cable 22,3 TOTAL47,148

  4. Generation & Demand (for the year of 2010) • Installed Capacity48.500 MW • Hydro+Renewable34.4 % • Hydro 32.1 %&Renewables 2.7 % • Thermal 65.2 % • Annual Consumption208 TWh • Peak Demand 33.500 MW • (13 August 2010)

  5. Topics • Brief history of interconnection queue • Challenges while planning • Tariff Policy • Queue Management • Future Efforts

  6. Brief History of Queues • First WPP commissioned in: 1998 • Number of the wind pp’s in operation are: 39 and total capacity: 1320 MW • Current Licensed wind generation: 3483 MW • Date: 1th November 2007 Number of the wind pp’s: 722 Total capacity: 78.000 MW • According to the system available capacity for connecting wind generation which is equal to 8474 MW a bidding code was prepared by TEIAS which includes the requirements for the applications. • According to the bidding document the wind owner which will get the right to use the open capacity has to pay an amount to TEIAS for 20 years since connecting to the system which is equal the amount which will be calculated for per kwh generation of the wind power plant.

  7. Wind power plant application areas

  8. Recent Situation for Wind Generation in Turkey • 3483 MW of wind applications has been licensed by EMRA • 1320 MW is in Operation • 2283 MW is Underconstruction • 8488 MW is under evaluation • The amount of the available wind generation capacity can be connected to the system until 2013 is 12000 MW • In the strategydocument it is foreseen that the total wind generation capacity will reach to 20.000 MW until 2023.

  9. The available wind generation capacity around 8488 MW is under evaluation

  10. Marmara & Thrace Region available wind generation capacity ~ 2745 MW is under evaluation

  11. Aegean Region available wind generation capacity around 2499 MW is under evaluation

  12. Hatay Region available wind generation capacity around 190 MW is under evaluation

  13. Challenges while planning • Available system reserve • The required reinforcements for connecting WPP’s into power system. • The difficulty to guess their production time of wind power plants. • Who pays the investments and how it will be recovered • Beside load flow, voltage profile, short-circuit and contingency studies; the %5 of the short circuit power of the substation which WPP will be connected is applied as a restriction criteria in order to keep the overall system security by now. • Detailed dynamic studies for determining the connection capacities are going on.

  14. INCENTIVES FOR RENEWABLE POWER PLANTS The Turkey’s Parliament approved a new law 29 December 2010 on regulating the renewable energy resources market in Turkey. The incentives which are applied for Renewable Power Plants with the new law guarantees a price of: • Hydro PPs and WPPs are paid at system marginal price, but minimum 7.3 US$ /MWh is guaranteed • Geothermal PPs are paid at system marginal price, but minimum 10.5 US$ /MWh is guaranteed • Biogas PPs and Solar PPs are paid at system marginal price, but minimum 13.3 US$ /MWh is guaranteed • Those tariffs shall be valid for the PPs which came into service between 18 May 2005 to 31 December 2015 and will be applied for 10 years. • After 31 December 2015, new tariff shall be given by the Government but the new tariff shall not exceed the tariff above.

  15. Queue Management • Process: • The available capacity for connecting wind generations are published by TEİAS. • WPP applications are forwarded to EMRA (Turkish Regulatory Agency) for these capacities. • These applications are forwarded to TEIAS for studying connection opportunities. • TEIAS gives its comment concerning the availability.If the application is alone in the substation, EMRA gives license to those applications. • If there are multiple applications, bidding process is done by TEIAS to determine the owner of the capacity. • After taking license the investor sign a connection agreement with TEIAS. • Project will be approved by MENR after the realization of the project System Usage Agreement will be done with TEIAS.

  16. Queue Management • Principle of connection cost sharing in between TSO and investor: If the investor pays for the connection line then the TSO will pay back to the investor this amount in 10 years from the investment budget. Otherwise, TSO will put the required investment for the connection of the power plant in it’s yearly investment plan and these procedures takes approximately 3-5 years for bidding (plus constructing period)

  17. Planning Process by TEIAS • Turkish Electricity Transmission Corporation responsible from the WPP integration studies and to define the available capacity for connecting wind generation • According to the results of load flow, contingency analyses and short circuit power calculations, the estimation for capacity for each substation and each region which will be available for connecting wind generation are defined by TEIAS • Concentrated small wind generations in one region are collected in one substation (example: Çeşme Region) • We have a specific grid code which defines the connection criteria for wind generation but it will be revised for future power system conditions.

  18. ÇEŞME REGION WIND PROJECTS: 460 MW 21 km 380 kV 3 Cardinal 55 km 380 kV 3 Cardinal 380/OG kV Karaburun SS 380/OG Çeşme HAVZA SS 380/154 kV Uzundere SS 380/OG 125 MVA 380/OG 150 MVA 16,2 km 380 kV 2 Cardinal 31 km 154 kV 2x1272 MCM 154/OG URLA HAVZA SS OG OG Zeytineli-2 RES 49,5 MW 7 km 10 km ~ ~ 154/OG 50 MVA 154/OG 50 MVA 154/OG 50 MVA Karaburun RES 120 MW 12 km ~ Karadağ RES 16,25MW 14 km ~ Mordoğan RES 13,8 MW OG OG OG 17 km Ovacık RES 18 MW 10 km ~ Urla RES 15 MW ~ 5 km ~ Mordoğan RES 30,75 MW Çeşme RES 16 MW 11 km 26 km ~ 10 km Seferihisar RES 14 MW ~ ~ Alaçatı RES 16 MW 9 km ~ Yaylaköy RES 15 MW 9 km ~ Seferihisar RES 16 MW Germiyan RES 10,8 MW 4 km ~ Korkmaz RES 24 MW 11 km ~ ~ 13 km Urla RES 13 MW Sarpıncık RES 32 MW ~ 6 km Demircili RES 40 MW ~ SS TOTAL CAP: 211,55 MW SS TOTAL CAP: 139,55 MW SS TOTAL CAP: 109 MW

  19. Future Efforts • The wind forecast system has been developed by Turkish StateMeteorological Service which is available to provide information about the wind forecasts for different heights and for 48 hours with 4 km. solubility all around Turkey. The trial tests are going on in order to improve the system. • Specific monitoring system for wind generation will be installed and the procedures are going on with consultant company

  20. Thank You for Your Attention !

More Related