Manpower, Cost and Schedule. Masahiro Morii, Harvard U. Manpower Cost and Deliverables Schedule. Executive Summary. Adequate manpower has been identified UK cost £212K awaits PPRP approval US cost $142K + 1.5 engineering FTE Significant (~$30K) uncertainty in ZPD FPGAs

bern
Télécharger la présentation

Manpower, Cost and Schedule

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Manpower, Cost and Schedule Masahiro Morii, Harvard U. Manpower Cost and Deliverables Schedule Manpower, Cost, Schedule

  2. Executive Summary • Adequate manpower has been identified • UK cost £212K awaits PPRP approval • US cost $142K + 1.5 engineering FTE • Significant (~$30K) uncertainty in ZPD FPGAs • Aim to install in 09/01/02 • TSF schedule ~2 months late • ZPD schedule just in time Manpower, Cost, Schedule

  3. Manpower – UK Manpower, Cost, Schedule

  4. Manpower – US physicists Manpower, Cost, Schedule

  5. Manpower – US engineers Manpower, Cost, Schedule

  6. Deliverables • Want to keep 1 spare + 1 in test benchwhen 1 is being repaired Type X and Y areinterchangeable. Manpower, Cost, Schedule

  7. Cost – TSF • TSF cost is paid by the UK funding • Pending PPRP approval Manpower, Cost, Schedule

  8. Cost – ZPD • Cost is dominated by the FPGAs for the AE • MegaBus prototype tests the on-board bus technology (LVDS vs. single-ended) • 1.25 FTE needs to be paid by the project Manpower, Cost, Schedule

  9. ZPD Algorithm Engines Baseline design • Prices quoted for “when volume production starts” = Nov–Dec 2001 • Size and # of FPGAs affect cost greatly • More FPGAs for timing margin  +$27k • Larger FPGAs less likely but even more costly Manpower, Cost, Schedule

  10. Cost – TSFi, ZPDi, GLTi • 0.25 FTE needs to be paid by the project Manpower, Cost, Schedule

  11. Total Cost 2 special 9-U VME creates for system tests Manpower, Cost, Schedule

  12. Schedule • Goal: install at BABAR on 9/1/02 • Take advantage of summer shutdown • August ’02 will be spent in system tests • Connect all components and run simulated data • All deliverables must arrive by August ’02 • Test bench must be ready, too • Requires prototypes of all components to arrive as early as possible  June ’02? Manpower, Cost, Schedule

  13. Schedule – TSF • Current schedule later than ideal • PPRP approval in Oct ’01 • Partial prototypes in June ’02 • Full production no later than Aug/Sept ’02 • Integration into BABAR in Oct ’02 • Earlier schedule being worked out • Must save ~2 months Manpower, Cost, Schedule

  14. Schedule – ZPD et al • ZPD production schedule OK • Full prototype built by 6/4/02 • Build 2 for parallel testing at Harvard/SLAC? • Full production by 8/6/02 • Board-level functional testing included • TSFi, ZPDi, GLTi and cables likely OK • Much easier than TSF and ZPD • Must set schedule nonetheless Manpower, Cost, Schedule

  15. Schedule – Fallback • Install new crates for TSF/ZPD in BABAR • Next to (not replacing) existing TSF/PTD • Split fibers from DCH if possible • Feed new and old systems at the same time • Commission while taking data • Almost decouples upgrade from shutdown • Even if fiber splitters don’t work, switching will require only ~1 shift Manpower, Cost, Schedule

  16. Executive Summary • Adequate manpower has been identified • UK cost £212K awaits PPRP approval • US cost $142K + 1.5 engineering FTE • Significant (~$30K) uncertainty in ZPD FPGAs • Aim to install in 09/01/02 • TSF schedule ~2 months late • ZPD schedule just in time Manpower, Cost, Schedule