Chapter 7: Project Cost Management

Chapter 7: Project Cost Management. Information Technology Project Management, Fifth Edition. Learning Objectives. Understand the importance of project cost management Explain basic project cost management principles, concepts, and terms

bernad
Télécharger la présentation

Chapter 7: Project Cost Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 7:Project Cost Management Information Technology Project Management, Fifth Edition

  2. Learning Objectives • Understand the importance of project cost management • Explain basic project cost management principles, concepts, and terms • Discuss different types of cost estimates and methods for preparing them Information Technology Project Management, Fifth Edition, Copyright 2007

  3. Learning Objectives (continued) • Understand the processes involved in cost budgeting and preparing a cost estimate, and budget for an information technology project • Understand the benefits of earned value management and project portfolio management to assist in cost control • Describe how project management software can assist in project cost management Information Technology Project Management, Fifth Edition, Copyright 2007

  4. The Importance of Project Cost Management • IT projects have a poor track record for meeting budget goals • The CHAOS studies found the average cost overrun (the additional percentage or dollar amount by which actual costs exceed estimates) ranged from 180 percent in 1994 to 43 percent in 2002; other studies found overruns to be 33-34 percent Information Technology Project Management, Fifth Edition, Copyright 2007

  5. What Went Wrong? • The U.S. Internal Revenue Service (IRS) continues to provide examples of how not to manage costs • A series of project failures in the 1990s cost taxpayers more than $50 billion a year • In 2004, CIO Magazine reported problems with the IRS’s $8 billion modernization project • In 2006, the IRS was in the news for a botched upgrade to its fraud-detection software, costing $318 million in fraudulent refunds that didn’t get caught • The United Kingdom’s National Health Service IT modernization program was called the greatest IT disaster in history by a London columnist, with an estimated $26 billion overrun • Incompatible systems; resistance from physicians who felt they were not consulted enough about system features; arguments amoung contractors regarding responsibility Information Technology Project Management, Fifth Edition, Copyright 2007

  6. What is Cost and Project Cost Management? • Cost is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange • Costs are usually measured in monetary units like dollars • Project cost management includes the processes required to ensure that the project is completed within an approved budget • Project managers must make sure their projects are well defined, have accurate time and cost sestimates and have a realistic budget that they were involved in approving Information Technology Project Management, Fifth Edition, Copyright 2007

  7. Reasons for Cost Overruns • Not emphasizing the importance of realistic project cost estimates from the outset • Many of the original cost estimates for IT projects are low to begin with and based on very unclear project requirements • Many IT professionals think preparing cost estimates is a job for accountants when in fact it is a very demanding and important skill that project managers need to acquire • Many IT projects involve new technology or business processes which involve untested products and inherent risks Information Technology Project Management, Fifth Edition, Copyright 2007

  8. Project Cost Management Processes • There are three project cost management processes: • Cost estimating: developing an approximation or estimate of the costs of the resources needed to complete a project • Cost budgeting: allocating the overall cost estimate to individual work items to establish a baseline for measuring performance • Cost control: controlling changes to the project budget Information Technology Project Management, Fifth Edition, Copyright 2007

  9. Project Cost Management Summary Information Technology Project Management, Fifth Edition, Copyright 2007

  10. Basic Principles of Cost Management • Most members of an executive board better understand and are more interested in financial terms than IT terms, so IT project managers must speak their language • Profits are revenues minus expenditures • Profit margin is the ratio of revenues to profits • $2 profit per $100 revenue  2% profit margin • Life cycle costing considers the total cost of ownership, or development plus support costs, for a project • A project could take 2 years to build and be in place for 10 years; costs and benefits must be estimated for the entire lifetime of the project Information Technology Project Management, Fifth Edition, Copyright 2007

  11. Cost of Software Defects • It is much more cost-effective to spend money on defining user requirements and doing early testing on IT projects than to wait for problems to appear after implementation • If it would cost $1,000 to repair a software defect in the requirements and analysis phase but it would cost $30,000 to fix it in the post-product release phase Information Technology Project Management, Fifth Edition, Copyright 2007

  12. What Went Right? • A leading telecommunications company estimated the cost of a software bug or defect at three stages: after coding, after manual inspection, and after beta release • The costs to correct the defect increased with each stage from $2,000 to $10,000 to $100,000 • The company estimated that when it released one million lines of new code, it had an average of 440 defects in the early stage, 250 in the middle stage, and 125 in the late stage, costing more than $15 million • They decided to implement an automated inspection process, which reduced costs for fixing bugs by more than $11 million Information Technology Project Management, Fifth Edition, Copyright 2007

  13. Basic Principles of Cost Management • Cash flow analysis determines the estimated annual costs and benefits for a project and the resulting annual cash flow • Too many projects with high cash flow needs in the same year may not be able to be supported which will impact profitability • Tangible costs or benefits are those costs or benefits that an organization can easily measure in dollars • A task that was allocated $150,000 but actually costs $100,000 would have a tangible benefit of $50,000 if the assets allocated are used for other projects • Intangible costs or benefits are costs or benefits that are difficult to measure in monetary terms • Costs – resources used to research related areas of a project but not billed to the project • Benefits – goodwill, prestige, general statements of improved productivity not easily translated in dollars Information Technology Project Management, Fifth Edition, Copyright 2007

  14. Basic Principles of Cost Management • Direct costs are costs that can be directly related to producing the products and services of the project • Salaries, cost of hardware and software purchased specifically for the project • Indirect costs are costs that are not directly related to the products or services of the project, but are indirectly related to performing the project • Cost of electricity, paper towels • Sunk cost is money that has been spent in the past; when deciding what projects to invest in or continue, you should not include sunk costs • To continue funding a failed project because a great deal of money has already been spent on it is not a valid way to decide on which projects to fund • Sunk costs should be forgotten Information Technology Project Management, Fifth Edition, Copyright 2007

  15. Basic Principles of Cost Management • Learning curve theory states that when many items are produced (or tasks are performed) repetitively, the unit cost of those items decreases in a regular pattern as more units are produced (or more tasks performed) • Reserves are dollars included in a cost estimate to mitigate cost risk by allowing for future situations that are difficult to predict • Contingency reserves allow for future situations that may be partially planned for (sometimes called known unknowns) and are included in the project cost baseline • Recruiting and training costs for expected personnel turnover during a project • Management reserves allow for future situations that are unpredictable (sometimes called unknown unknowns) • Extended absence of a manager; supplier goes out of business Information Technology Project Management, Fifth Edition, Copyright 2007

  16. Cost Estimating • After developing a good resource requirements list, PMs and their teams must develop several estimates of the costs for these resources • Project managers must take cost estimates seriously if they want to complete projects within budget constraints • It’s important to know the types of cost estimates, how to prepare cost estimates, and typical problems associated with IT cost estimates Information Technology Project Management, Fifth Edition, Copyright 2007

  17. Cost Estimating • A rough order of magnitude (ROM) estimate provides an estimate of what a project will cost. • Also referred to as a ballpark estimate, a guesstimate, a swag, or a broad gauge. • Done very early in a project, often three or more years prior to project completion, or even before a project is officially started to help PMs make project selection decisions. • Accuracy is typically -50 percent to +100 percent, meaning the project’s actual costs could be 50 percent below the ROM estimate or 100 percent above. • A ROM estimate that actually cost $100,000 would range between $50,000 to $200,000. The accuracy range is often much wider for IT projects. • Often IT project estimates for software development are doubled because of the history of cost overruns Information Technology Project Management, Fifth Edition, Copyright 2007

  18. Cost Estimating • A budgetary estimate is used to allocate money into an organization’s budget. • Many organizations develop budgets at least two years into the future. • Budgetary estimates are made one to two years prior to project completion. • The accuracy of budgetary estimates is typically -10% to +25% • A budgetary estimate that actually costs $100,000 would range between $90,000 to $125,000. Information Technology Project Management, Fifth Edition, Copyright 2007

  19. Cost Estimating • A definitive estimate provides an accurate estimate of project costs (most accurate of the three types). • Definitive estimates are used for making many purchasing decisions for which accurate estimates are required and for estimating final project costs. • For example, if a project involves purchasing 1000 personal computers from an outside supplier in the next three months, a definitive estimate would be required to aid in evaluating supplier proposals and allocating the funds to pay the chosen supplier. • Definitive estimates are made one year or less prior to project completion • Accuracy range is normally -5% to +10% Information Technology Project Management, Fifth Edition, Copyright 2007

  20. Types of Cost Estimates • It is important to provide supporting details (assumptions, project scope, WBS, etc) used in computing estimates so that it will be easier to prepare updates as needed or similar estimates on other projects. Information Technology Project Management, Fifth Edition, Copyright 2007

  21. Cost Management Plan • A cost management plan is a document that describes how the organization will manage cost variance on the project • For example, how to respond to proposals from suppliers that are higher or lower than estimates • A large percentage of total project costs are often labor costs, so project managers must develop and track estimates for labor • Many organizations estimate the number of people or hours they need by department or skill over the life cycle of a project Information Technology Project Management, Fifth Edition, Copyright 2007

  22. Maximum Departmental Headcounts by Year • The table below shows the maximum number of people Northwest Airlines determined to assign to each year of the project by department • Note the small number of contractors; contractors generally have higher labor costs than in-house employees Information Technology Project Management, Fifth Edition, Copyright 2007

  23. Cost Estimation Tools and Techniques • Analogous or top-down estimates:use the actual cost of a previous, similar project as the basis for estimating the cost of the current project • How similar the current and previous project are determines the accuracy of the estimate. Using a different language or hardware can skew the estimate • Bottom-up estimates or Activity Based Costing : involve estimating individual work items or activities and summing them to get a project total • The smaller the work items, the better the estimate but these estimates are usually time intensive and expensive to develop Information Technology Project Management, Fifth Edition, Copyright 2007

  24. Cost Estimation Tools and Techniques • Parametric modeling:uses project characteristics (parameters) in a mathematical model to estimate project costs • For example, a model might provide an estimate of $50 per line of code for a s/w development project based on the programming language, level of expertise of the programmers, size and complexity of the data involved, etc • Some models may be simpler such as a $10,000 ballpark estimate per workstation in a large office automation project based on history of similar projects during the same time period Information Technology Project Management, Fifth Edition, Copyright 2007

  25. Typical Problems with IT Cost Estimates1 • Estimates are done too quickly • Many estimates must be done quickly, before clear system requirements have been produced • Lack of estimating experience • The people developing the costs estimates often don’t have much experience, especially on large projects • There is not enough accurate, reliable project data available on which to base estimates • Human beings are biased toward underestimation • Senior team members make estimates based on their skill level but should take into account the junior people on the project • Management desires accuracy but wants to spend less in order to win a bid or internal funding • Top management never forgets the first estimate and rarely, if ever, remembers how approved changes affect the estimate. • The PM must keep the communication lines open at all times _______________________________________________________________ 1.DeMarco, Tom, Controlling Software Projects, New York:Yourdon Press, 1982. Information Technology Project Management, Fifth Edition, Copyright 2007

  26. Sample Cost Estimate • See pp. 277-281 for a detailed example of creating a cost estimate for the Surveyor Pro project described in the opening case • Before creating an estimate, know what it will be used for, gather as much information as possible, and clarify the ground rules and assumptions for the estimate • If possible, estimate costs by major WBS categories • Create a cost model to make it easy to make changes to and document the estimate Information Technology Project Management, Fifth Edition, Copyright 2007

  27. Surveyor Pro Project Cost Estimate Information Technology Project Management, Fifth Edition, Copyright 2007

  28. Surveyor Pro Software Development Estimate Information Technology Project Management, Fifth Edition, Copyright 2007

  29. Cost Budgeting • Cost budgeting involves allocating the project cost estimate to individual work items over time • The WBS is a required input to the cost budgeting process since it defines the work items • An important goal is to produce a cost baseline • A time-phased budget that project managers use to measure and monitor cost performance • Estimating costs for each major project activity over time provides management with a foundation for project cost control • Cost budgeting also provides info for project funding requirements –at what point(s) in time will the money be needed Information Technology Project Management, Fifth Edition, Copyright 2007

  30. Surveyor Pro Project Cost Baseline • The Surveyor Pro project team could use the cost estimate (slide 27) along with the project schedule and other info to allocate costs for each month as below *Numbers are rounded, so some totals appear to be off. Information Technology Project Management, Fifth Edition, Copyright 2007

  31. Cost Control • Project cost control includes: • Monitoring cost performance • Ensuring that only appropriate project changes are included in a revised cost baseline • Informing project stakeholders of authorized changes to the project that will affect costs • Many organizations around the globe have problems with cost control Information Technology Project Management, Fifth Edition, Copyright 2007

  32. Media Snapshot • Australia: problems with the installation of an ERP system at Crane Group Ltd. led to an estimated cost overrun of $11.5 million • India: as many as 274 projects currently under implementation in the Central sector are suffering serious cost and time overruns. Only 65 are being monitored on a regular basis • Pakistan: Pakistan has sustained a cost overrun of Rs 1.798 billion (over $30 million U.S. dollars) in the execution of the 66.5 megawatt Jagran Hydropower Project in the Neelum Valley. Caused by massive mismanagement, embezzelment of funds and unapproved changes in the project • United States: Northern California lawmakers were outraged over Governor Arnold Schwarzenegger's announcement that commuters should have to pay construction costs on Bay Area bridges. Cost of one of the bridges has grown from $1.1 billion to $5.1 billion Maybe it takes the Terminator to help control costs! Information Technology Project Management, Fifth Edition, Copyright 2007

  33. Cost Control Performance review meetings can be a powerful tool to help control project costs Knowing you have to report on your progress is an incentive for people to perform better Performance measurement is another important tool for cost control There are many general accounting approaches for measuring cost performance but earned value management is a tool unique to project management 33 Information Technology Project Management, Fifth Edition, Copyright 2007

  34. Earned Value Management (EVM) • EVM is a project performance measurement technique that integrates scope, time, and cost data • Given a baseline (original plan plus approved changes), you can determine how well the project is meeting its goals • You must enter actual information periodically to use EVM • Was a WBS item completed or approximately how much of the work was completed • Actual start and end dates • Actual cost • More and more organizations around the world are using EVM to help control project costs Information Technology Project Management, Fifth Edition, Copyright 2007

  35. Earned Value Management Terms • The planned value (PV), formerly called the budgeted cost of work scheduled (BCWS), also called the budget, is that portion of the approved total cost estimate planned to be spent on an activity during a given period • Actual cost (AC), formerly called actual cost of work performed (ACWP), is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period • $20,000 AC to accomplish task over two weeks - $15K AC week 1and $5K week 2 • The earned value (EV), formerly called the budgeted cost of work performed (BCWP), is an estimate of the value of the physical work actually completed • EV is based on the original planned costs for the project or activity and the rate at which the team is completing work on the project or activity to date Information Technology Project Management, Fifth Edition, Copyright 2007

  36. Rate of Performance • Rate of performance (RP) is the ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity • Brenda Taylor, Senior Project Manager in South Africa, suggests this term and approach for estimating earned value • For example, suppose the server installation was halfway completed by the end of week 1; the rate of performance would be 50% because by the end of week 1, the planned schedule reflects that the task should be 100% complete and only 50% of that work has been completed • The EV would thus be $5,000 after week 1 ($10,000*50%) Information Technology Project Management, Fifth Edition, Copyright 2007

  37. Earned Value Calculations for One Activity After Week One Information Technology Project Management, Fifth Edition, Copyright 2007

  38. Earned Value Formulas Information Technology Project Management, Fifth Edition, Copyright 2007

  39. Earned Value Formulas • Negative numbers for cost and schedule variance indicate problems in those areas • If CV is negative it means that performing the work cost more than planned • A negative SV means that it took longer than planned to perform the work • CPI can be used to estimate the projected cost of completing the project based on performance to date (EAC) • =1:the planned and actual costs are the same; <1: over budget; >1: under budget • SPI can be used to estimate the projected time to complete the project • =1: on schedule; <1 behind schedule; >1 ahead of schedule Information Technology Project Management, Fifth Edition, Copyright 2007

  40. Earned Value Chart for Project after Five Months • EAC = $122,308 = BAC/CPI = $100,000/.81761 • ETC = 12.74 months = Original Time Estimate/SPI = 12 months/.94203 Information Technology Project Management, Fifth Edition, Copyright 2007

  41. Earned Value Chart • The chart helps visualize how the project is performing. • If the project goes as planned, it will finish in 12 months at a cost of $100,000 • The actual cost line is always right on or above the earned value line. • Interpretation: This means costs are equal to or more than planned • The planned value line is pretty close to the EV line, just slightly higher in the last month • Interpretation: The project has been right on schedule until last month when the project fell behind schedule Information Technology Project Management, Fifth Edition, Copyright 2007

  42. Earned Value Chart Many commercial organizations do not use EV management Because IT projects do not have good planning information, tracking performance against a plan might produce misleading information Estimating percentage completion of tasks might also produce misleading information. What does it mean to say a task is 75% complete after 3 months? 1 more month is needed to finish? Will finish after spending an additional 25% of the planned budget? Could very well be no to both of those question. To simply EV management, Use percentage completion of 0(not started), 50 (in progress) and 100 (completed) Or, enter and collect EV data at summary levels of the WBS 42 Information Technology Project Management, Fifth Edition, Copyright 2007

  43. Project Portfolio Management Many organizations collect and control an entire suite of projects or investments as one set of interrelated activities in a portfolio Five levels for project portfolio management Put all your projects in one database Prioritize the projects in your database Divide your projects into two or three budgets based on type of investment Automate the repository Apply modern portfolio theory, including risk-return tools that map project risk on a curve 43 Information Technology Project Management, Fifth Edition, Copyright 2007

  44. Benefits of Portfolio Management • Schlumberger saved $3 million in one year by organizing 120 information technology projects into a portfolio • 80% of the prjects overlapped • 14 separate projects were trying to accomplish the same thing • META Group research shows that: • Organizations that evaluate information technology projects by what their business impacts are and what their potential business values will be implement projects that result in 25 percent more improvement to the bottom line • Business executives state that using project portfolio management allows managers to make decisions faster and with more confidence Information Technology Project Management, Fifth Edition, Copyright 2007

  45. Best Practice • A global survey released by Borland Software in 2006 suggests that many organizations are still at a low level of maturity in terms of how they define project goals, allocate resources, and measure overall success of their information technology portfolios • Some of the findings include the following: • Only 22 percent of survey respondents reported that their organization either effectively or very effectively uses a project plan for managing projects • Only 17 percent have either rigorous or very rigorous processes for project plans, which include developing a baseline and estimating schedule, cost, and business impact of projects • Only 20 percent agreed their organizations monitor portfolio progress and coordinate across interdependent projects • The most successful organizations are taking a holistic view of focusing, managing and measuring their IT efforts with an integrated combination of best practice processes, training and technology Information Technology Project Management, Fifth Edition, Copyright 2007

  46. Best Practice 46 • The most successful organizations are taking a holistic view of focusing, managing and measuring their IT efforts with an integrated combination of best practice processes, training and technology • Unfortunately, most organizations today are not taking that approach Information Technology Project Management, Fifth Edition, Copyright 2007

  47. Using Software to Assist in Cost Management • Spreadsheets are a common tool for resource planning, cost estimating, cost budgeting, and cost control • Many companies use more sophisticated and centralized financial applications software for cost information • Project management software has many cost-related features, especially enterprise PM software • Several companies have developed methods to link data between their project management software and their main accounting systems Information Technology Project Management, Fifth Edition, Copyright 2007