An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Briar & Little Sugar Creek Watersheds Draft Floodplain Maps ASFPM – Louisville, KY Robert Billings, PE, PH, CFM Flood Mitigation Project Manager Charlotte-Mecklenburg Storm Water Services May 18, 2011

  2. Mecklenburg County North Carolina Land Area: 549 square miles Mecklenburg County includes the City of Charlotte and the towns of Cornelius, Davidson, Huntersville, Matthews, Mint Hill, and Pineville (8 NFIP Communities)

  3. Local Flood Mapping • Current maps are result of County-wide FIS completed in February 4, 2004 at a cost of $2,000,000 • 350 miles of detailed study streams • 32 watersheds • FEMA and Community flood fringe and floodway • Data reproduced in state-wide format effective March 2, 2009 • 182 panels, paper and digital forms • Remapping began in 2007 on two basins , expanded in 2008 to include the majority of the remainder of the county

  4. Public Meetings Using Technology to Involve the Public in the Remapping Process • Charlotte-Mecklenburg and draft flood map meetings • New Technology • A different approach to public meetings

  5. Meeting Purpose • Gather public input on draft Floodplain Maps • Show new Risk Communication Products • Show how information can be used • Increase understanding of flood risk “Sandwich Approach” Public Input Land Use Task Force Draft Floodplain Mapping Open House Flood Insurance Rate Maps (Compliance Period)

  6. Why Floodplain Maps Change Flood Risk Changes Over Time Climatological Changes Natural & Man Made Land Changes Technological Advancements • Better Data • Improved computer models • Enhanced Map Products • Extended Historic Rainfall Records • Changes in Rain Intensity, Duration, Frequency, etc. • Natural Geomorphic Stream Changes • Development within the Watershed

  7. Floodplain Mapping History • Protecting Life and Property • Community Sustainability & Resiliency • Communicate& Reduce Flood Risk Why are “Floodplains” Mapped? Uses for Flood Risk Information • Flood Insurance • Regulate New Development • Flood Preparedness • Planning • Mitigation • And more…..

  8. Floodplain Mapping History Current Maps 2004, 2009 1% annual chance Flood First Maps Dated 1978 – 20041% annual chance Flood Current Maps available online with additional property information

  9. What is Changing

  10. What is Flood Risk

  11. Using New Flood Map Products • Knowing your flood risk is the first step intaking actions toward Reducing your risk.

  12. Next Steps - Mapping Schedule

  13. Online Flood Map Review • http://mapserver.mecklenburgcountync.gov/fmr/ • Public Review & Comment Period closesNovember 16th

  14. Public Meetings Three Public Meetings were organized during September and October of 2010 • The website address of the FMR application was published prior to the meetings • The meetings began with a brief introduction and floodplain 101 presentation • After the introduction, the attendees were asked to find a staff member or open laptop station to view the new floodplain data

  15. On-Line Survey Results Meeting attendees were asked to complete a brief online survey related to the mailers, meetings and FMR application • One-on-one sessions with laptops and Storm Water Services staff were helpful to me. 60% Strongly Agree • I would have preferred a traditional meeting with one formal presentation. 80% Disagree • Not including the public meeting, I have looked at the draft floodplain maps online. 90% Yes

  16. Tim Trautman, PE, CFM Flood Mitigation Program Manager (704) 336-7357 Tim.Trautman@ MecklenburgCountyNC.gov Robert Billings, PE, PH, CFM Floodplain Mapping Project Manager (704) 432-0907 Robert.Billings@ MecklenburgCountyNC.gov Thank You