EDRP & Smart Metering Update 4 th February 2010 Richard Westoby, Andrew Monks and Ian Lansley

EDRP & Smart Metering Update 4 th February 2010 Richard Westoby, Andrew Monks and Ian Lansley. Agenda. EDRP Key Learnings Key Learnings and Insights Consumer Needs Technical and Practical issues Deployment and Design issues Q&A. ‘Consumer Need’ Learnings.

bess
Télécharger la présentation

EDRP & Smart Metering Update 4 th February 2010 Richard Westoby, Andrew Monks and Ian Lansley

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EDRP & Smart Metering Update4th February 2010Richard Westoby, Andrew Monks and Ian Lansley

  2. Agenda • EDRP Key Learnings • Key Learnings and Insights • Consumer Needs • Technical and Practical issues • Deployment and Design issues • Q&A

  3. ‘Consumer Need’ Learnings • Customers want choice on how they receive information and customers more interested in saving money than saving energy • Displays, paper or web probably all required to meet different customer needs • Customer messages and propositions need to be simple to understand • Interventions received via multiple media seen as wasteful and confusing

  4. ‘Consumer Need’ Learnings • Displays • Visual ‘traffic’ lights generally well received • Pricing on display needs remote updating and consumer prefers pricing to be fully inclusive with explanation • Electricity and gas units not always understood • Prepayment meters need extra information on displays • Prepayment buttons on meter need to be well labelled and friendly • Low signal power creates customer concerns if ‘no comms’ message • Some customers refused displays as didn’t want one or too technical • Paper Information with Bill or in Post • Shifting consumption from peak to off-peak; positive response from consumers but some difficulty understanding the principle • Graphs and benchmarking need simple explanations • Some customers regard paper as wasteful • Web • Only 40% customers provided email addresses for this intervention • Website needs simple access with easy user name / password rules • Password lockouts caused customer concern • Some customers not interested in web access or turned off by process to reach the graphical screens

  5. Deployment Learnings • Difficult locations need technical solutions: • Basements, block of flats and remote geographical locations (eg; islands, highlands) not addressed and will require comms solutions to be developed • Meter not readily accessible eg; boxed in meters • Community approach has positive impact on reducing energy consumption; however this approach would need substantial adaptation for a national roll out • In urban and suburban areas it is difficult to identify what is a community • New smart meter / display solutions take 12-18 mths to develop, test and pilot • Skilled trained installer workforce necessary; training and availability will be an issue

  6. Summary • Need for consumer choice of media and simple messages • A key driver is consumer cost saving leading to energy saving • Geographic approach aids communication and local support for rollout • Manufacturers and system integrators must improve their quality control and testing to reduce faults and data issues • Complexity must not be underestimated for national rollout due to the numbers of parties and the number of process elements involved • Interoperability required between meter types (eg; gas and electric) and displays across HAN and WAN • Need to address difficult sites / meter locations • Skilled trained installer workforce necessary; training and availability will be an issue

  7. Energy made better