1 / 11

Arctic2007

Arctic2007. NASA FR: 7P001 NASA Goddard Space Flight Center Wallops Flight Facility Principal Investigator: Dr. Ken Jezek; OSU Byrd Polar Research Center Mission Manager: John Valliant CSC – NASA WFF Code 840. Potential Co-Principal Investigators.

bevis
Télécharger la présentation

Arctic2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Arctic2007 NASA FR: 7P001 NASA Goddard Space Flight CenterWallops Flight Facility Principal Investigator: Dr. Ken Jezek; OSU Byrd Polar Research Center Mission Manager: John Valliant CSC – NASA WFF Code 840

  2. Potential Co-Principal Investigators • Dr. Prasad Gogineni - gogineni@ittc.ku.edu • Mr. William Krabill – William.B.Krabill@nasa.gov • Dr. Keith Raney - Keith.Raney@jhuapl.edu • GSFC Greenbelt • Others?? Arctic20070 TIM 10/10/2007

  3. Documentation Requirements • Flight Requests – OSU and WFF in; others ?? (JHU… suborbital.nasa.gov) • Danish/Canadian Over-flight Clearances • General Experiment Information and Request Worksheet (PIs) • Project Plan (840) • Mission Operations Safety Directive (840) • ECF MOSD (548) • Approval to Proceed (800/840) Arctic20070 TIM 10/10/2007

  4. Reviews / Meetings • Airworthiness Review Board (840/548) • Mission Readiness Review (840) • Final Installation Inspection Review (840/548) – Subsequent Safety of Flight Release • Weekly/Monthly Technical Flight telecons Arctic20070 TIM 10/10/2007

  5. Preliminary Mission Timeline • ARB Review January 16, 2007 • Receive instrumentation March 6, 2007 • Begin upload March 13, 2006 • Complete upload April 13, 2007 • Final Installation and Inspection Review April 16, 2007 • Safety of flight Release April 17, 2007 • Mission Readiness Review April 18, 2007 • Engineering Check Flight April 19, 2007 • Begin Mission April 23, 2007 • Return to WFF on May 14, 2007 • Question; Test flight requests Arctic20070 TIM 10/10/2007

  6. Arctic2007 Basing Options • Thule AFB • Kangerlussuaq (Sondrestrom) • Canada ?? • Iceland ?? Arctic20070 TIM 10/10/2007

  7. Mission Costs • P-3 Subsidized rate at $ 2,500/hr • Transit time ~ 16 hrs round trip • ECF ~ 1-3 hrs • Test Flights ?? • ~ $ 50K non-science hours (ECF, transit) • + MPCs Arctic20070 TIM 10/10/2007

  8. Mission Peculiar Costs • Aircrew Per-Diem (Lodging/M&IE) • Airfield Costs • Deicing • Ramp charges • Administrative Fees • Crew Overtime • Fuel Exceeding Subsidized rate $ 3.00 • Shop Supplies • Engineering/Fabrication Arctic20070 TIM 10/10/2007

  9. Estimated Basing Costs (MPCs) • Assumptions; • 7 air-crew members • 15 hours overtime/day • Thule (per week) • Aircrew Per-Diem (Lodging/M&IE) = $ 64/day = ~ $ 3K • Airfield Costs = $ 0 • Deicing • Ramp charges • Administrative Fees • Crew Overtime = $ 5K • Fuel Exceeding Subsidized rate of $ 3.00 = $0 • WAG for Thule = 8K/week Arctic20070 TIM 10/10/2007

  10. Estimated Basing Costs (MPCs) • Assumptions; • 7 air-crew members • 15 hours overtime/day • Sonde (per week) • Aircrew Per-Diem (Lodging/M&IE) = $ 313/day = ~ $ 15K • Airfield Costs = $ 1700/day = ~$ 12K • Deicing ( not included) • Ramp charges • Administrative Fees • Crew Overtime = $ 5K • Fuel Exceeding Subsidized rate of $ 3.00 (fuel rate $3.70-$4.50) = $4K / day = ~$ 28K • WAG for Sonde = $ 60K/week Arctic20070 TIM 10/10/2007

  11. Cost ?? • Assumption; 40 flight hours/week • 300K + 50K non-science = $350K • 2 weeks Thule = $ 20 K • 1 week Sonde = $ 60 K • Total scenario cost ~ $ 430K Arctic20070 TIM 10/10/2007

More Related