html5-img
1 / 5

HiRadMat WG 2&3 team meeting

HiRadMat WG 2&3 team meeting. Agenda. Activities for next weeks + perturbations TNC cleaning Beam line removal TCX block removal Survey reference points. TNC cleaning : status. Visual inspection OK

blade
Télécharger la présentation

HiRadMat WG 2&3 team meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HiRadMat WG 2&3 team meeting Agenda • Activities for next weeks + perturbations • TNC cleaning • Beam line removal • TCX block removal • Survey reference points

  2. TNC cleaning : status • Visual inspection OK • Smear tests taken where contamination was the highest: reduction by a 10 factor (all smear tests < contamination level) • Endelleft on last Tuesday after equipment decontamination + RP checks • Dosimetry below estimates (collective dose 2.2 mSv where 3.2 was estimated)

  3. Beam line removal DIMR completed: https://edms.cern.ch/document/1058846/1 Work in 5 phases: 1- Equipment located between 2 fences  DONE 2- Equipment ready for move in front of T9 (1 magnet + blocks)  DONE 3- Prepare remaining equipment in front of T9 (vacuum disconnection) 4- Remove remaining equipment in front of T9 5- Remove 2 monitors at the end of TNC (4 blocks to be moved)

  4. TCX block removal Movie

  5. Survey reference points

More Related