1 / 21

HERA Status

HERA Status. Joachim Keil, DESY (MPY). 59 th Meeting of the Physics Research Committee May 26 th , 2005. Contents. Operation of HERA 04/05 with Electrons Luminosity Performance Major technical Problems Polarization Improvements Schedule 2005 Conclusions.

bree
Télécharger la présentation

HERA Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HERA Status Joachim Keil, DESY (MPY) 59th Meeting of the Physics Research Committee May 26th, 2005

  2. Contents • Operation of HERA 04/05 with Electrons • Luminosity Performance • Major technical Problems • Polarization • Improvements • Schedule 2005 • Conclusions J. Keil : HERA Status

  3. Re-Commissioning with Electrons • HERA electron operation: • More synchrotron radiation (for design currents: 26 kW 36 kW) • Different orbits for e and p in IR • Successful re-commissioning strategy (Oct.-Dec. ‘04): • Set up/check HERA-e with positrons • Move magnets in IR • Continue with electrons • Beam-based alignment; check of optic and correction; … • Start with electrons was smooth: No big problems found! • But: It was necessary to move H1 by x=7 mm due tolimited space in GO magnet on left side • Delay in schedule: • Quadrupole GN NL20 had a burnt coil • Vacuum leak at GI07 NR J. Keil : HERA Status

  4. Trajectories for e-/p and e+/p in IR GM GM GM GM GG,HG 7.5 mm GI - GO,HO p beam for e- p + p-beam for e+ e--beam - - GI GI + e+-beam + + GJ - GJ BO e Radial orbit shift at IP of 7.5 mm between electron and positron operation J. Keil : HERA Status

  5. Parameters of Run ‘04/05 with Electrons Design 2005 with e- For e-: Vacuum, RFFor p: Pre-accelerators Beam-Beam effects For p: Long. instability Hour glass factor included in design! J. Keil : HERA Status

  6. Beam Currents • Peak currents for run ‘04/05 with electrons (150 bunches): • Ipmax = 102 mA • Iemax = 40 mA • Proton single bunch current is high:Would be 123 mA with 180 bunches! • Electron current was limited first by H1 background (vacuum) • No progress increasing the electron beam current in the last monthsslow conditioning of RF cavities, transmitter problems and vacuum • Switch to 180 bunches if 40 mA electrons can be routinely filled; but dust trapping probability will be higher! J. Keil : HERA Status

  7. Specific Luminosity • High specific luminosity with electrons for 2004/05 run: Ls = 1.8 - 2.2 1030 cm-1·s-1·mA-2 • Specific Luminosity is larger than the design value of Ls = 1.84 1030cm-1·s-1·mA-2 • One reason for higher specific luminosity compared to last year with positrons (1.2 -1.61030) is the smaller proton emittance and bunch length • Calculated specific luminosity based on measured beam parameters can describe the measurements of H1 and ZEUS sufficiently good overestimated J. Keil : HERA Status

  8. Integrated Luminosity 04/05 • Integrated luminosity is 95.3 pb-1 in 156 days (start: Dec. 17th, 2004) • Best run delivered 1.1 pb-1 within14 hours • On average 0.61 pb-1/d (number for last year: 0.41 pb-1/d) • Mid of May was best so far:HERA delivered 1.17 pb-1/d • New record peak luminosity ofL= 5.071031 cm-2·s-1 was achieved • But: high proton background and many spikes until BU SR coil was identified as the culprit fixed in April! J. Keil : HERA Status

  9. Integrated Luminosity Luminosity production rate with electrons in 2005 is higher than 2004 for positrons! (ZEUS) J. Keil : HERA Status

  10. HERA e--Lifetime • Again: Sudden lifetime reduction and lifetime recovery during electron operation • At the same time increased beam loss measured • Observed for I > 30 mA since January ‘05; but number of events is fortunately rare at the moment • Theory: trapping of positive ionized dust particles by the negative charged electron beam • Source of dust: Ion getter pumps (dipole pumps were already replaced in shutdown 1997/98) • If the number of bunches is increased, the probability of dust trapping gets higher Lifetime event 4.5.2005 J. Keil : HERA Status

  11. HERA Operational Statistics 2005 Relative large amount of faults is reducing the efficiency of operation; fraction for e- and p-injection times have decreased, fraction of luminosity-run increased since ‘04. Main problems for faults and delays in ‘05 were due to magnet problems, cryogenics, power supplies, PETRA and problems with the proton quench protection. J. Keil : HERA Status

  12. Major technical problems • Nov. 2004: • Burnt coil of proton quadrupole magnet GN NL 20 Coil exchanged • Dec 2004: • GI NR 7 vacuum leak; broken feed through of NEG pump • Jan. 2005: • Ground fault proton quadrupole magnet GN NL 23 Coil exchanged • Feb. 2005: • Cryogenic compressor failure quick repair but p-ring warmed up (1 week) • Apr. 2005: • Periodic p-background spikes shorted coil of BU-magnet SR; coil exchanged (4 days) • May 2005: • Vacuum leak in p-chamber between GM proton quadrupoles NR welding of seam; bad vacuum (since 1 week) J. Keil : HERA Status

  13. GN Magnet Problem • During recommissioning in Nov. ‘04 the magnet GN NL20 failed (cooling problem) • GN magnet: vertical focussing low beta quadrupole for protons; 12 magnets • Damaged lower inner coil had to be exchanged (six days lost) • In January ‘05 also the magnet GN NL23 failed with ground fault; all four coils were replaced (1 week) • Possible reason: Magnets have been operated with 1638 A during power supply tests in October last year exceeding the manufacturer limit of 1600 A Measures: • Current of power supply limited to 1470 A (max. value for luminosity run) • New coils ordered! J. Keil : HERA Status

  14. BU Magnet Problem • Since January ‘05: Periodic background spikes in combination with vertical orbit movements; not all the time • Reason was shorted coil of BU magnet SR; April:coil exchanged (4 days) • BU bend the protons upwards at end of straight sections; 18 magnets • Six BU-coils in NL (last shutdown) and one coil in SL were already exchanged • Candidate for another short: BU OL Measures: • Measurement of voltage drop of coils • Exchange of all remaining BU coils in next shutdownShutdown delayed until all ordered coils are delivered (shutdown starting at 14th Nov. ‘05) Collimator beam loss rate J. Keil : HERA Status

  15. Polarization Non-colliding bunches: ~50% Colliding bunches: 40% • Even after long tuning polarization is dis-appointing low • Colliding bunches reaches 40% only at end of run (but non-colliding have 55%!) • Influence of beam-beam effect: Polarization is rising due to growth of proton emittance and declining proton intensity • Energy and harmonic bumps are optimized • Problem: Tunes are not optimal for electrons and polarization! Measures: • Electron intensity related effects allows to decrease the tunes at lower electron currentBut: e-background spikes at H1! • Possible solution: Mirror tunes started test with mirror tunes last week! Polarisation History of polarization and single bunch polarization J. Keil : HERA Status

  16. Mirror Tunes J. Keil : HERA Status

  17. Improved e--Transfer Efficiency • Transfer efficiency of El-Weg between PETRA and HERA-e: • HERA I : never reached 100% • HERA-II: sometimes only 30-40% and non-reproducible! • Better efficiency faster filling, less radiation during injection process Measures: • Calculation of a new matched optic for the EL-Weg adapted for HERA-II injection optic • Installation of 6 beam position monitors in last summer shutdown • Checkedmagnet rolls by survey ok! • Measurement of response matrix of the EL-Weg  large error in optics • Measurement of quadrupole calibration curve calibration wrong! • Now: • Transfer efficiency >70% • Efficiency more stable than before • Remaining losses: PETRA extraction J. Keil : HERA Status

  18. Improvement: Proton Tune Controller • Energy ramp of protons is demanding: • Induced eddy currents in super- conductors  Time varying dipole and sextupole fields • Tunes near coupling resonance • Control of beam parameters is done manually by operators watching beam signals and turning knobs; needs much experience! • Nevertheless p-beam often get lost Measure: • Semi-automatic control of tunes was developed; ramping between 70 GeV and 920 GeV and electron refill are now far easier than before! • Coupling and chromaticity control under development J. Keil : HERA Status

  19. Longitudinal Multi-Bunch Feedback Schematic principle • Proton-bunch lengthening due to longitudinal coherent multi-bunch instability • Longer bunches smaller specific luminosity („Hour glass effect“) • Happens during proton ramping Measure: • Installation of an longitudinal multi-bunch feedback system for protrons • Status: Feedback cavity arrived; first measurements done • Installation in next shutdown • Goal: Reduction of bunch length at 920 GeV from 1.6 ns to 0.7 ns (FWHM); realistic? Feedback Cavity J. Keil : HERA Status

  20. Schedule 2005 • Schedule • Start of luminosity operation: 17th Dec. ’04 • Start of shutdown: 14th Nov. ’05 • End of shutdown: End of Jan. ’06 • Luminosity operation: 2nd week in Feb. ’06 • Expectations for integrated luminosity • Until now: Li = 95 pb-1in 156 days • Conservative assumption: Average increase of 0.61 pb-1/d • This includes hardware faults, maintenance days, … • 176 days remaining  Additional 107 pb-1 • Lower bound for 2005: Li 200 pb-1 ? • Can be even more, if hardware problems happen not so frequentlyand electron current can be increased! • Plans for hardware changes in the shutdown • Exchange of all remaining BU coils • Installation of the longitudinal proton feedback cavity J. Keil : HERA Status

  21. Conclusions • High luminosity production with electrons; performanceof HERA has greatly improved • Integrated luminosity up to now with electrons has alreadyexceeded the value with positrons of year 2004 • Background conditions are usually good after sourceof p-background spikes has been found; but there was againa vacuum leak in north! • Polarization with max. 40% disappointing investigation of mirror-tunes has started • Availability of HERA components and operational efficiencyis still too low • HERA will continue luminosity operation until wintershutdown (14th Nov. 2005 – Jan./Feb. 2006) J. Keil : HERA Status

More Related