1 / 37

R eclaimed A sphalt P avement in Arizona - Application and Verification

R eclaimed A sphalt P avement in Arizona - Application and Verification. October 3, 2008 Arizona Association of County Engineers. Outline. Introduction Project Overview Existing Pavement Condition Construction and Production Operations Granite/ADOT Test Results Summary. Outline.

bruis
Télécharger la présentation

R eclaimed A sphalt P avement in Arizona - Application and Verification

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Reclaimed Asphalt Pavement in Arizona - Application and Verification October 3, 2008 Arizona Association of County Engineers

  2. Outline • Introduction • Project Overview • Existing Pavement Condition • Construction and Production Operations • Granite/ADOT Test Results • Summary

  3. Outline • Introduction • Project Overview • Existing Pavement Condition • Construction and Production Operations • Granite/ADOT Test Results • Summary

  4. Change in DOT’s

  5. Changing Market Conditions = Renewed Interest in Recycling • Price escalation for construction/rehabilitation and maintenance • Asphalt binder shortages • Polymer shortages • Environmental concerns • Energy concerns • Funding limitations

  6. States Allowance of RAP • 75-percent of States allow at least 10-percent RAP in surface course mixes • More States allow higher percentages in lower lifts

  7. Value of Recycling – Percent Savings Relative to Conventional Materials – Initial Construction* *equivalent square yardsNote: Similar advantages found with Life Cycle Cost

  8. PCI Over Time* *Projects constructed in Arizona

  9. Outline • Introduction • Project Overview • Existing Pavement Condition • Construction and Production Operations • Granite/ADOT Test Results • Summary

  10. Project Layout

  11. Standard Sections

  12. Scope of Work • Partial depth removal of existing asphalt concrete • Placement of dense grade asphalt concrete • Placement of AR-ACFC • Miscellaneous other work • Granite’s Proposal • Use RAP in base course HMA • 6% coarse RAP (3/4-in x 3/8-in) • 9% fine RAP (3/8-in minus) • Note: RAP currently used as shoulder backing and aggregate base on ADOT projects

  13. Standard Section

  14. Outline • Introduction • Project Overview • Existing Pavement Condition • Construction and Production Operations • Granite/ADOT Test Results • Summary

  15. Alligator Cracking Moderate severity alligator cracking Existing pavement prior to rehabilitation

  16. Transverse Cracking Slight to moderate severity transverse cracking Existing pavement prior to rehabilitation

  17. Block Cracking Block cracking Existing pavement prior to rehabilitation Maybe considered combination of longitudinal and transverse cracking

  18. Outline • Introduction • Project Overview • Existing Pavement Condition • Construction and Production Operations • Granite/ADOT Test Results • Summary

  19. Cold Milling Operations

  20. Unprocessed RAP from I-19

  21. Coarse RAP (3/4-in x 3/8-in)

  22. Fine RAP (3/8-in Minus)

  23. Hot Plant Feeders 5 Virgin Aggregate Bins 2 RAP Bins

  24. Hot Plant Cement Silo and Pugmill Virgin Aggregate Scalping Screen

  25. Hot Plant Counter Flow Drum Mixer RAP Conveyor

  26. Paving and Inspection HMA Paving Density Testing

  27. Rolling Operations Echelon Breakdown Rolling Finish Rolling

  28. Finished Mat

  29. Outline • Introduction • Project Overview • Existing Pavement Condition • Construction and Production Operations • Granite/ADOT Test Results • Summary

  30. Granite Test Results – RAP* *Test results based on ignition oven**Standard Deviation – measure of variability

  31. Granite Test Results – RAP* *Test results based on solvent extraction**Standard Deviation – measure of variability

  32. Granite/ADOT Test Results - Gradation • Gradation of aggregate extracted from field mixed samples *Standard Deviation – measure of variability

  33. Granite/ADOT Test Results - Volumetrics • Volumetric properties of field mixed/lab compacted samples *Standard Deviation – measure of variability

  34. Outline • Introduction • Project Overview • Existing Pavement Condition • Construction and Production Operations • Granite/ADOT Test Results • Summary

  35. Recycling Benefits • Conservation • Materials (aggregate and asphalt binder) • Energy (burner fuel, trucking, etc.) • Preservation of environment • Landfill • Green house gases (global warming) • Sustainability • Economics • Reduce first and life cycle cost • Complete reconstruction vs. alternative methods • Increased contractor competition

  36. Questions

More Related