Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014

Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014. Overview of Project Schedule. Existing Site and Traffic Pattern. 575 Herndon Parkway Parcel #225. 593 Herndon Parkway Parcel 227. 198 Van Buren Parcel #226. Pavilion Site.

casimir-lel
Télécharger la présentation

Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Herndon Station - North Pavilion Construction Town of Herndon – Town Council August 6, 2014

  2. Overview of Project Schedule

  3. Existing Site and Traffic Pattern 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Pavilion Site

  4. Existing Underground SWM 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Pavilion Site

  5. PHASE 1.1 - Target Start: February 2016, Duration: 1 Month • Install Fence 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Pavilion Site

  6. PHASE 1.1 - Target Start: February 2016, Duration: 1 Month • Install Fence • Clear & Grade 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226

  7. PHASE 1.1 - Target Start: February 2016, Duration: 1 Month • Install Fence • Clear & Grade • Demo Staircase 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Laydown

  8. PHASE 1.1 - Target Start: February 2016, Duration: 1 Month • Install Fence • Clear & Grade • Demo Staircase • Install Retaining Wall 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Laydown

  9. PHASE 1.1 - Target Start: February 2016, Duration: 1 Month • Install Fence • Clear & Grade • Demo Staircase • Install Retaining Wall • Build Construction Access 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Laydown

  10. PHASE 1.2 - Target Start: February 2016, Duration: 1 Month • Install Fence • Clear & Grade • Demo Staircase • Install Retaining Wall • Build Construction Access • Install Fence 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Laydown

  11. PHASE 1.2 - Target Start: February 2016, Duration: 1 Month • Install Fence • Clear & Grade • Demo Staircase • Install Retaining Wall • Build Construction Access • Install Fence • Demo Median 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Laydown

  12. PHASE 1.3 - Target Start: February 2016, Duration: 1 Month • Install Fence • Clear & Grade • Demo Staircase • Install Retaining Wall • Build Construction Access • Install Fence • Demo Median • Construct New Aisle 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Laydown

  13. PHASE 1.3 - Target Start: February 2016, Duration: 1 Month • Install Fence • Clear & Grade • Demo Staircase • Install Retaining Wall • Build Construction Access • Install Fence • Demo Median • Construct New Aisle • Relocate Dumpster • Pave to Existing • Permanent Traffic Shift 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Laydown

  14. PHASE 2 - Target Start: March 2016, Duration: 2 Months • Relocate Existing Utilities • Install New Utilities • Relocate Transformer 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Laydown

  15. PHASE 3 - Target Start: May 2016, Duration: 4 Months • Erect Service Crane • Excavate • Install Footings • Install FDN/SOG • Concrete Columns/Beams • Install Precast Concrete 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Crane Pavilion Laydown

  16. PHASE 4 - Target Start: September 2016, Duration: 5 Months • Install Escalators • Erect Pedestrian Bridge 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Crane Pavilion Laydown

  17. PHASE 4 - Target Start: September 2016, Duration: 5 Months • Install Escalators • Erect Pedestrian Bridge • Install Curb & Gutter • Install Pavers • Install Sidewalks • Install Finishes 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Crane Pavilion Laydown

  18. PHASE 5 - Target Start: February 2017, Duration: 2 Months • Remove Service Crane 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 Construction Access 198 Van Buren Parcel #226 Pavilion Pavilion Site

  19. PHASE 5 - Target Start: February 2017, Duration: 2 Months • Remove Service Crane • Install Sidewalk 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Pavilion Pavilion Site

  20. PHASE 5 - Target Start: February 2017, Duration: 2 Months • Remove Service Crane • Install Plaza & Sidewalk • Install Landscaping 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Pavilion Pavilion Site

  21. PHASE 5 - Target Start: February 2017, Duration: 2 Months • Remove Service Crane • Install Plaza & Sidewalk • Install Landscaping • Remove Fencing 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Pavilion Pavilion Site

  22. Parking Impacts – Parcels 225 and 227 575 Herndon Parkway Parcel #225 593 Herndon Parkway Parcel 227 198 Van Buren Parcel #226 Pavilion Pavilion Site