1 / 19

Linac4 & SPL Status of preparation and Opportunities M. Vretenar (R. Garoby)

Linac4 & SPL Status of preparation and Opportunities M. Vretenar (R. Garoby). SPL (1). SPL = Superconducting Proton Linac a 4 MW / 3.5 GeV linear accelerator to: increase the performance of the CERN high energy accelerators (PS, SPS & LHC)

ccarr
Télécharger la présentation

Linac4 & SPL Status of preparation and Opportunities M. Vretenar (R. Garoby)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Linac4 & SPLStatus of preparation and OpportunitiesM. Vretenar (R. Garoby) DAPNIA 9/01/2006

  2. SPL (1) SPL = Superconducting Proton Linac a 4 MW / 3.5 GeV linear accelerator to: • increase the performance of the CERN high energy accelerators (PS, SPS & LHC) • address the needs of future physics experiments with neutrinos and radio-active ion beams DAPNIA 9/01/2006

  3. SPL (2) • Initial design (Conceptual Design Report 1): • “optimized” for a neutrino factory • assumed the use of LEP cavities & klystrons up to the highest energy • Revised design in progress (CDR 2): • based on updated physics’ requests • using 704 MHz RF and bulk Niobium cavities • in collaboration with CEA-Saclay & INFN-Milano • to be published in 2005 • Up-to-date information is available: • on the CERN EDMS • on the SPL site: http://project-spl.web.cern.ch/project-spl/ DAPNIA 9/01/2006

  4. SPL stages Three stages are planned: • Stage 1: 3 MeV test place Þ development and test of linac equipment, beam characterization • Stage 2: Linac4 • New linac replacing the present injector of the PS Booster (Linac2) • Front-end of the future SPL Þ improvement of the beams for physics (higher performance and easier operation for LHC, ISOLDE etc.) • Stage 3: SPL • New injector for the PS, replacing the PS Booster • New physics experiments using a high proton flux Þ improvement of the beams for physics and possibility of new experiments DAPNIA 9/01/2006

  5. Linac4 design 3MeV 40MeV 90MeV 160MeV DTL CCDTL SCL Drift Tube Linac 352 MHz 13.6 m 3 tanks 5 klystrons 4 MW Cell-Coupled Drift Tube Linac 352 MHz 25.2 m 24 tanks 8 klystrons 6.4 MW Side Coupled Linac 704 MHz 28 m 20 tanks 4 klystrons 12.5 MW 3MeV line (H- source, IPHI RFQ, chopper line) Duty cycle: 0.1% phase 1 (Linac4) 15% phase 2 (SPL) 4 different structures, (RFQ, DTL, CCDTL, SCL) 2 frequencies Total Linac4: 86.3 m , 18 klystrons Beam current: 40 mA (avg. in pulse), 65 mA (bunch) DAPNIA 9/01/2006

  6. Linac4 Schedule Linac4 (160 MeV, H-) will double the intensity and brightness of the beam out of the PSB.  Support by the DG for a decision on construction at end 2006. Tentative schedule: • 2005-06 Continuation of R&D • 2006 (end) Linac4 Design Report(basic design frozen) • 2007 Detailed design (=execution drawings!), definition of construction strategy, attribution of contracts • 2008-09 Construction • 2010 End of installation and commissioning DAPNIA 9/01/2006

  7. Linac4 collaborations INDIA: klystron power supplies CHINA: quadrupoles, bendings, buncher IPHI HIPPI ISTC # 2888 & 2889 SCL ISTC # 2875 Network of collaborations for the R&D phase, via EU-FP6, CERN-CEA/IN2P3, ISTC, CERN-India and CERN-China agreements. The same network should support the construction of Linac4. DAPNIA 9/01/2006

  8. Shunt Impedance Effective shunt impedance ZT2 along Linac4 Superfish calculation, not scaled • The section between ~90 MeV and ~200 MeV is the most difficult for modern linacs: • DTL-like structures present a sharp decrease in shunt impedance. • Superconducting structures are not yet effective (low real estate gradient). • Usual p-mode NC structures (CCL, SCL) at double frequency are considered expensive. DAPNIA 9/01/2006

  9. The nominal Linac4 solution: a Side Coupled Linac RF power source: 4 MW, 704 MHz klystrons similar to SNS – (offer from Thales) DAPNIA 9/01/2006

  10. More on the SCL Chain of cells, coupled via slots and off-axis coupling cells. Invented at Los Alamos in the 60’s. Operates in the p/2 mode (stability). CERN SCL design: Each klystron feeds 5 tanks of 11 accelerating cells each, connected by 3-cell bridge couplers. Quadrupoles are placed between tanks. DAPNIA 9/01/2006

  11. Example: the SCL for SNS DAPNIA 9/01/2006

  12. Side Coupled cells Copper units made of one half accelerating cell and one half coupling cell, precisely machined (0.03mm) and brazed. 2 half cells with magnetic field lines 1 half cell with one half bridge coupler DAPNIA 9/01/2006

  13. SNS SCL Construction Cell precision machining on a lathe – RF measurements after machining and before brazing DAPNIA 9/01/2006 Vertical brazing in the oven – final RF tuning, bead-pull measurement of field in the module

  14. Options for CERN SCL construction Present status of Side Coupled Linac studies: * Studied inside HIPPI, jointly by CERN and LPSC Grenoble. Linac design (CERN), thermal analysis (LPSC), RF errors (LPSC, CERN), cell design. * Cold model will be built by LPSC (2006). * Technological model (Cu, brazed) will be built by BINP-Novossibirsk (2006). * INFN-Naples joins now the collaboration (bridge coupler design, stability). The construction of a Side Coupled Linac requires a difficult integration of technologies: Procurement of forged copper - Precision machining on Cu – First RF tuning before brazing – Brazing – Final RF tuning. Note that these technologies are very similar to those used for RFQ’s! • Options for construction (2007-2009): • Contract with ACCEL (has built the SNS SCL). • Construction in Russia (some interest by BINP). • Construction in Italy (INFN-Na ready, INFN interest still to be checked) • Construction in France…? DAPNIA 9/01/2006

  15. A superconducting alternative to the SCL? SCL can have another meaning: Super Conducting Linac. A SC section could replace the Side-Coupled, providing that we can obtain real-estate gradients ~2.5 MV/m. Needs investment for the cryogenic infrastructure, justified in the optics of an SPL following Linac4. SCL tanks (700 MHz) Spoke cavities (SC) (350 MHz) RF requirements: beam power 2.8 MW - 20 units 100 kW, 352 MHz - 3 klystrons 1 MW, 352 MHz - 1 klystron 4 MW, 704 MHz DAPNIA 9/01/2006

  16. Spoke, 352 MHz Focusing period in present design 90-160 MeV (FODO): ~ 1.5 m  compatible with Triple-spoke Triple-spoke designed at FZJ for HIPPI (E. Zaplatine): 0.78 m cavity length for b=0.5 E0T = 6.4 MV/m no freq. jump * Low efficiency at 90 MeV. * Do we need a double spoke at lower energy (but b=0.35 probably too low)? * Can we fit it in a cryostat ~ 1.2m long (to keep focusing distance)? * Can we feed 8 of these cavities from a single LEP klystron? DAPNIA 9/01/2006

  17. Elliptical, 704 MHz Elliptical cavities at b=0.5 (CEA, INFN) are giving excellent results. Length ~ 0.9m Designed for 12 MV/m. * Require longer focusing period (~1.5 m). * Low efficiency at 90 MeV. * How many cavities can we feed with one klystron? * We could use the SPL-CDR2 layout, with superconducting quadrupoles and long cryostats, but long R&D time for superconducting quadrupoles. DAPNIA 9/01/2006

  18. Summary for SC options • A superconducting option is attractive for the high-energy part of Linac4, but has to compete with the conventional Side Coupled Linac. • As a preliminary step in order to compare options we need layouts (mid 2006 ?) for both spoke and elliptical cavities, with a first beam dynamics analysis to be done in the frame of the HIPPI Activity (see ESAC recommendations). • To compete with the SCL, average real estate gradient should be > 2.2 MeV/m. • The option of cold quadrupoles (as for SPL) can be considered, but time is short to have it fully developed by end 2006. • The RF power system can be a cost driver even for a SC linac, if one cannot drive at least 8 cavities/klystron. DAPNIA 9/01/2006

  19. Global planning RF tests in SM 18 of prototype structures* for Linac4 * Quotes from R. Aymar (Jan.2005) 3 MeV test place ready SPL approval * “in 2009-2010, to review and redefine the strategy for CERN activities in the next decade 2011-2020 in the light of the first results from LHC and of progress and results from the previous actions. “ Linac4 approval * “… in 2006-2007, to decide on the implementation of the Linac 4 and any increased R&D programme, depending on new funds made available and on a new HR policy” CDR 2 DAPNIA 9/01/2006

More Related