1 / 6

Carr School Update

Carr School Update. 3/5/14. Elevator and Classroom Additions.

cherie
Télécharger la présentation

Carr School Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Carr School Update 3/5/14

  2. Elevator and Classroom Additions Work is nearly complete. Containment to be removed in the coming weeks. Hourly checks on the space temperature have ensured proper environment for the masonry work. The elevator itself just arrived to the shop and will be on site within the week.

  3. Windows Windows are approximately 80% complete. Special care has been taken to ensure that the install is high quality, with an eye for air sealing and envelope integrity.

  4. Mechanical Systems Most of the HVAC work is complete. A few more air handlers to be installed, some small things to button up, and in about 4 weeks we’ll be firing up the new high efficiency condensing boilers.

  5. Electrical, Plumbing, Sprinkler, and Data All interior trade work is moving along quickly. Systems are mostly installed, and things like pressure testing, safety checks, and final wiring are underway.

  6. Interior Finishes Almost all of the walls are closed up. Plastering is almost complete, and we’ve started painting.

More Related