IBM 1350 Cluster Expansion

IBM 1350 Cluster Expansion. Doug Johnson Senior Systems Developer. Recommendation Summary. Expand the existing IBM E1350 cluster with a BioSciences focus: The proposed expansion, while compatible with our existing system, will have features that form a good fit for Biosciences

cheriec
Télécharger la présentation

IBM 1350 Cluster Expansion

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IBM 1350 Cluster Expansion Doug Johnson Senior Systems Developer

  2. Recommendation Summary • Expand the existing IBM E1350 cluster with a BioSciences focus: • The proposed expansion, while compatible with our existing system, will have features that form a good fit for Biosciences • Proposed expansion would propel the system’s rank to 4th in U.S. academic supercomputing centers • System would be ranked 21st in the overall Top 500 • Will provide researchers with a total of 59TF peak performance • Increased memory from 8.4TB to 17.5TB • Add 240TB of integrated storage • System will be set up for dynamic changes in the operating environment to benefit innovation by the biosciences community • The system will also be suited to many other applications and will fit into our current environment including staff knowledge and capacity

  3. Glenn Cluster Upgrade - Upgrade Details • The cluster expansion will add approximately 500 nodes. • 2 quad-core CPUs per system, 2.3 GHz likely clock speed • 16/24 GB memory (24 GB in ~1/3 of the systems.) • 20 Gbit/sec IB network • 1 Gigabit Ethernet • 500 GB or larger internal disk drive • There will also be approximately 5 larger memory systems with a total of 16 processor cores and 64 GB of memory. • Newer versions of hardware for the IB network will deliver 20 Gb/sec throughput to each cluster node, with a communication latency that is less than half compared to the existing network. • The newer generation of IB network will integrate with the existing network. This will allow parallel applications to be run across the new and existing nodes.

  4. Glenn Cluster Upgrade - Current Project Plan

  5. Glenn Cluster Upgrade - Milestones