Galesburg CUSD 205

Galesburg CUSD 205. Operation Rebuild - Achievement. Steele Charrette #1. Galesburg C USD 205 · Dewberry · Russell Construction Company · Metzger Johnson

cian
Télécharger la présentation

Galesburg CUSD 205

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Galesburg CUSD 205 Operation Rebuild - Achievement Steele Charrette #1 Galesburg CUSD 205 · Dewberry · Russell Construction Company · Metzger Johnson IEFM Consulting Engineers · Bruner, Cooper & Zuck · Johnson Building Systems

  2. . Building improvements to increase student achievement . Building improvements to increase property values and attract new residents . Optimize resources in order to achieve the “biggest bang for the buck” . Create jobs . Don’t raise property taxes . Keep projects on time and budget .Maximize State and Federal funding opportunities Project Goals, Objectives and Guiding Principles

  3. Phase 1 Summary Galesburg CUSD 205 · Dewberry · Russell Construction Company · Metzger Johnson IEFM Consulting Engineers · Bruner, Cooper & Zuck · Johnson Building Systems

  4. Construction Grand Opening charrette/ planning charrette/ planning charrette/ planning 100% SD 100% DD 100% CD Bid / Award July – Aug 2012 Sept 2012 – Aug 2013 August 1, 2013 Jan-Feb 2012 ----------- March – July 15 2012 ------------ Design and Construction Process Galesburg CUSD 205 · Dewberry · Russell Construction Company · Metzger Johnson IEFM Consulting Engineers · Bruner, Cooper & Zuck · Johnson Building Systems

  5. $ $$ $$$ $$$$ $$$$$ Cost to make Changes ManyBig Picture Decisions Decisions FewBig Picture Decisions Process Construction Grand Opening charrette/ planning charrette/ planning 100% SD 100% DD 100% CD Bid / Award Technical Documentation Conceptual Process Design and Construction Process Galesburg CUSD 205 · Dewberry · Russell Construction Company · Metzger Johnson IEFM Consulting Engineers · Bruner, Cooper & Zuck · Johnson Building Systems

  6. Board of Education Administration/ BOE Building Committee Construction Grand Opening charrette/ planning charrette/ planning 100% SD 100% DD 100% CD Bid / Award SES Core Group Implementation Committee Design and Construction Process Galesburg CUSD 205 · Dewberry · Russell Construction Company · Metzger Johnson IEFM Consulting Engineers · Bruner, Cooper & Zuck · Johnson Building Systems

  7. Charrette Process . Visual Brainstorming . MeaningfulCommunity Input Galesburg CUSD 205 · Dewberry · Russell Construction Company · Metzger Johnson IEFM Consulting Engineers · Bruner, Cooper & Zuck · Johnson Building Systems

  8. 1st Priority 2nd Priority 3rd Priority Function/Attributes/Look Galesburg CUSD 205 · Dewberry · Russell Construction Company · Metzger Johnson IEFM Consulting Engineers · Bruner, Cooper & Zuck · Johnson Building Systems

  9. Steele Charrette #1 Jan 30 Mon 3:30 pm at SES Steele Charrette #2 Feb 06 Mon 3:30 pm at SES G205 Implementation Committee Feb 09 Thu 3:30 pm at SES G205 Building Committee Feb 13 Mon 5:00 pm at Admin G205 Board of Education Feb 13 Mon 7:00 pm at Admin Next Step - Charrette Schedule Galesburg CUSD 205 · Dewberry · Russell Construction Company · Metzger Johnson IEFM Consulting Engineers · Bruner, Cooper & Zuck · Johnson Building Systems