1 / 7

Hybrid Pixel R&D After BTeV

Hybrid Pixel R&D After BTeV. As of two years ago: FNAL-designed readout chip had two minor fatal flaws. No system demonstration had yet been done. An “extended closeout” R&D program was approved 1 more readout chip submission. Pixel R&D refocused on ILC. Two system tests approved:

couellette
Télécharger la présentation

Hybrid Pixel R&D After BTeV

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Hybrid Pixel R&D After BTeV • As of two years ago: • FNAL-designed readout chip had two minor fatal flaws. • No system demonstration had yet been done. • An “extended closeout” R&D program was approved • 1 more readout chip submission. • Pixel R&D refocused on ILC. • Two system tests approved: • Telescope for the forward direction of PHENIX (at RHIC) • Test beam telescope • Both efforts in collaboration with LANL & Columbia U.

  2. Sensor & FPIX2.1 wafers FPIX2.1 fabricated on wafer with “TripT” for D0; fatal flaws fixed; 11 wafers purchased by LANL for PHENIX, 11 by FNAL to support R&D - 2 required for MTest telescope. Sensor wafers produced for PHENIX by CiS (LANL has agreed to donate the x4 sensors for use in MTest)

  3. Sensors & ROCs probed – yield is high Typical FPIX2.1 wafer map Typical sensor IV curve

  4. Hybridization – solder bump bonding done by VTT (Finland) VTT bump-deposition process flow Production orders placed ~10/15/07 Delivery of hybrids is the schedule driver. X-ray made at FCC

  5. Test beam telescope Half-plane = three 1x4 modules Station = two half-planes offset by active area of sensor read out by 1 FPGA 2 stations upstream of DUT & 2-4 downstream (precision x & precision y)

  6. MT6-1A Assets • Climate controlled hut. • Aluminum table on rails allows entire setup to be removed from beam. • Dark box with feed throughs for signals, power, & cooling fluid. • Remotely controlled motors determine (x,y) position of both ends of box. • Local chiller provides closed loop cooling system • CAEN power system can provide LV & sensor bias (“HV”). • Plenty of quiet power is available.

  7. Schedule • Goal = installation in February 2008 (depends on delivery of bump bonded hybrids). • First user = LHCb. • Hybrid pixel telescope will measure every beam particle with good timing and moderate precision (5-10 m). • Anticipate the addition of one station with very high precision (& probably much less good time resolution), such as MAPS.