SECOND NATIONAL STEERING COMMITTEE FOR THE ESTABLISHMENT OF CMAs IN SOUTH AFRICA

SECOND NATIONAL STEERING COMMITTEE FOR THE ESTABLISHMENT OF CMAs IN SOUTH AFRICA 8 February 2013. CMA Roll-Out Progress Mpumalanga Regional Office (Olifants-Letaba ). PRESENTATION OUTLINE. Progress Report;

coxs
Télécharger la présentation

SECOND NATIONAL STEERING COMMITTEE FOR THE ESTABLISHMENT OF CMAs IN SOUTH AFRICA

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SECOND NATIONAL STEERING COMMITTEE FOR THE ESTABLISHMENT OF CMAs IN SOUTH AFRICA 8 February 2013 CMA Roll-Out Progress Mpumalanga Regional Office (Olifants-Letaba)

  2. PRESENTATION OUTLINE • Progress Report; • Establishment of the Regional Steering Committee including TOR and stakeholder consultation. • Implementation plan and communication plan. • Business case development. • Support plan required for the project. • Challenges and recommendations.

  3. Progress on the implementation plan and Communication plan • Draft communication plan in place • DWA Mpumalanga and Limpopo Regional office are always in touch. • Schedule meetings to engage each to finalised the draft Communication and implementation plan.

  4. Progress of the establishment of the Regional Steering Committee including TOR and stakeholder consultation • Currently in the process of establishing Regional Steering Committee and drafting TOR. • Meetings have been co-ordinated with DWA Mpum to kick start the process • Database in place of stakeholders to be engaged and participate.

  5. Progress on the development of business case. • No draft Business Case for the CMA , meeting is scheduled by Limpopo between the Management Mpumalanga and Limpopo to delegate a person to run the process

  6. Support plan required for the project. • Need financial support from DWA • The CMA will need capacity building from DWA

  7. Challenges and Recommendation • Strengthen communication