1 / 5

TIDVG2014 Production and installation Status

TIDVG2014 Production and installation Status. 30 /07/2014 – “TIDVG Follow-up Meeting”. Ivo Leitão. General Planning TIDVG2014 . Graphite. A luminium. Tungsten. Lower Yoke. Core. U pper Yoke. Copper. Necessary operations to produce the TIDVG2014:

dalton
Télécharger la présentation

TIDVG2014 Production and installation Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TIDVG2014Production and installation Status 30/07/2014 – “TIDVG Follow-up Meeting” Ivo Leitão

  2. General Planning TIDVG2014 Graphite Aluminium Tungsten Lower Yoke Core Upper Yoke Copper • Necessary operations to produce the TIDVG2014: • Prepare spare yokes  Disassemble TIDVG2004 (radioactive) and remove old core. • Prepare new coreFinalize the bake-out and place temperature sensors. • Assemble and test TIDVG2014 (alignment survey + water leak test). • Remove TIDVG2013 (damaged TIDVG presently installed in BA1 - SPS). • Install, test and bake-out the new TIDVG2014. OK OK Ongoing To be completed To be completed

  3. Completed Tasks • Assembly of the TIDVG2004 + Pressure test (EN/STI, HE/HH & DGS/RP) OK Bldg. 954

  4. Operations for Next Weeks • Week 28/07 – 01/08: • Installation of the PT100’s on the core & transport to Bldg. 954. • Assembly of the TIDVG2014 & water leak test. • External cabling preparation • Alignment survey • Acceptance of TIDVG2014 (Project milestone!) • Week 04/08 – 08/08: • BA1-SPS area preparation • Week 11/08 – 15/08: • Removal of TIDVG2013 • Installation of TIDVG2014 • Following weeks: • Bake-out in tunnel

  5. Thank You 30/07/2014 – “TIDVG Follow-up Meeting” Ivo Leitão

More Related