WITSML IMPLEMENTATION IN ONGC By Naresh Kumar Oil and Natural Gas Corporation Ltd. India

WITSML IMPLEMENTATION IN ONGC By Naresh Kumar Oil and Natural Gas Corporation Ltd. India. ABOUT ONGC. ONGC Oil and Natural Gas Corporation Ltd. Corporate Office, Dehradun (INDIA) Registered Office, New Delhi (INDIA). National Oil Company with Asset Based Structure. NR. ER. WR.

delila
Télécharger la présentation

WITSML IMPLEMENTATION IN ONGC By Naresh Kumar Oil and Natural Gas Corporation Ltd. India

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WITSML IMPLEMENTATION IN ONGC By Naresh Kumar Oil and Natural Gas Corporation Ltd. India

  2. ABOUT ONGC

  3. ONGC Oil and Natural Gas Corporation Ltd Corporate Office, Dehradun (INDIA) Registered Office, New Delhi (INDIA) National Oil Company with Asset Based Structure • NR • ER • WR Western Offshore Basin Western Onshore Basin Krishna Godavari Basin • CR Cauvery Basin • MR CBM BPM Basin Assam & A Arakan Basin Frontier Basin • SR Operates in diverse logistics In On land & Offshore areas

  4. EPINET PROJECT OF ONGC

  5. Integrated E&P Database Compliance of industry standards & best practices Single validated E & P data base throughout ONGC EPINET OBJECTIVE Flow of analytical & interpretation Data to EPINET Web based reporting And current E&P data flow into EPINET

  6. EPINET Sites & Networking CBM-MBP Basin Kolkata IDT/ GEOPIC/ OBG Tel Bhawan Frontier Basin, Dehradun E&D Dte Dehradun KDMIPE Dehradun Rajastan Project, Jodhpur Sibsagar Nazira Asset, Nazira IRS/Ahmedabad Asset Ahemdabad A&AA Basin Jorhat Mehsana Asset, Mehsana Cachar Project, Silchar Cambay Project, Cambay W.Onland Basin Baroda Tripura Asset Agartala Ankleshwar Asset, Ankleshwar IOGPT, Mumbai W.Offshore, Basin Mumbai Mumbai High/ Neelam/ Bassien Assets, Mumbai Rajahmundry, Asset Rajahmundry Krishna Godavari, Basin Rajahmundry RO Chennai W A N EPINET System Phase-I Scope Karaikal Asset,Karaikal LAN EPINET System Phase-II Scope Cauvery Basin, Karaikal Blue Site- Phase-I scope Red Site- Phase-II scope

  7. EPINET WORK FLOW INSTITUTES/RGL ASSET/BASIN Forward Base - Geology Lab. - Well Data ASSET/ - Reservoir Lab. - Reservoir Data Forward Base - Geochemistry Lab. - Production Data Server - Cultural Data - ML Data SERVICES BASIN Navigation & Composite Log - Well - Bid Monitoring Data - Drilling - Lease Data - Interpreted Data (Basin) BASIN - Interpreted Data ( Instt .) - Logging Server - RGL - Geophysical Post Stack 2D&3D Original Logs Corporate ReplicaServer Server E&D Dte

  8. EPINET Scenario PROJECT DATABASE SeisDB Seismic Archival AssetDB Physical Assets Other data-bases Finder E&P Master on-line LogDB Log Archival Forms / Reports Direct PC Access Web Application SmartMap GIS EPINET DATABASES

  9. WITSML IMPLEMENTATION

  10. WITSML FOR REAL TIME OPERATION

  11. WITSML FOR REAL TIME OPERATIONS Well-site / platform • ONGC, Paradigm and Halliburton developed a software (2003). • Interact & Insite (2004 onwards) • LWD/MWD objects. • Used for Geo-steering in Mumbai High. Visualization Center (VRC)

  12. PANNA MUKTA TAPTI (PMT) PROJECT

  13. PMT PROJECT • Introductory Meeting held in Kolkata in Jan 2006 during SPG. • Attended by representatives from ONGC, BG & Reliance. • It was decided to go ahead with the Pilot in PMT JV because of its multi-operators environment.

  14. DATA OBJECTS • Data Objects for Stage-I (Drilling+G&G centric) • Log Object (MWD, LWD, Wireline) • Well / Wellbore object (well header information) • Trajectory object • Mud log object • Stage-II planned as Production centric

  15. PMT PROJECT • Status: • Developed Fields. • EOR/IOR Phase • Now changed idea to implement PRODML which was earlier planned in Stage II.

  16. WITSML IN SCADA PROJECT

  17. WITSML IN SCADA PROJECT • AN ENTERPRISE-WIDE SCADA (SUPERVISORY CONTROL AND DATA ACQUISITION) SYSTEM. • WITSML COMPLIANT SERVER.

  18. SCADA THREE-TIER STRUCTURE EPINET ICE EPINET Process Complex URAN Trombay Corporate Data Center TIER -3 Drilling SCADA at IDT TIER -2 Offshore Asset Data Center Onshore Asset Data Center TIER -1 GGS HAZIRA Plant CPF Process Complex CTF Typical On-shore Asset Western Offshore Assets

  19. EPINET WORK FLOW INSTITUTES/RGL ASSET/BASIN Forward Base - Geology Lab. - Well Data ASSET/ - Reservoir Lab. - Reservoir Data Forward Base - Geochemistry Lab. - Production Data Server - Cultural Data - ML Data SERVICES BASIN Navigation & Composite Log - Well - Bid Monitoring Data - Drilling - Lease Data - Interpreted Data (Basin) BASIN - Interpreted Data ( Instt .) - Logging Server - RGL - Geophysical Post Stack 2D&3D Original Logs Corporate ReplicaServer Server E&D Dte

  20. THE CHALLENGE

  21. SEAMLESS INTEGRATION OF SAP & EPINET WITH SCADA FROM WITSML COMPLIANT SCADA • TIME STAMPED DATA WILL FLOW INTO ICE-SAP FOR BUSINESS COMPUTATIONS. • THE E & P DATA WILL FLOW TO EPINET.

  22. SAP Ice Integrated SCADA-EPINET-ICE System Managers for Business Information Drilling, G&G, Prod SCADA System MIS Reports 1 Web portal 3 Capture Data End Users Third Eye, IIWS Collaborative Teams Data Historian High Frequency Database Manual entry ... Transfer Decimated Data Epinet Master Data Well References Validation Done at Assets, basins Domain Experts 2 EPINET Team Validate / QC Export validated data in prescribed formats ( templates) to be loaded by the EPINET team Data Loaders (Lab, Institute etc.) Data Transfer Data Access by Users

  23. Thank You