Reconfigurable Transportable Consolidated Automated Support System (RTCASS) Gunnery Sergeant Smith May 2009

Reconfigurable Transportable Consolidated Automated Support System (RTCASS) Gunnery Sergeant Smith May 2009. UNCLASSIFIED. CASS Transition. HYB. to. RT. RF. Double Wide to Single Wide. RTCASS. 3. System Overview.

delling
Télécharger la présentation

Reconfigurable Transportable Consolidated Automated Support System (RTCASS) Gunnery Sergeant Smith May 2009

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Reconfigurable Transportable Consolidated Automated Support System (RTCASS)Gunnery Sergeant SmithMay 2009 UNCLASSIFIED

  2. CASS Transition HYB to RT RF Double Wide to Single Wide

  3. RTCASS 3

  4. System Overview • Reconfigurable Transportable CASS (RTCASS) is a downsized, transportable version of RF CASS that meets the deployability requirements of the USMC and USAF Special Operational Capable forces. • RTCASS must emulate CASS • Run times same as or faster than CASS • All TPS perform same as CASS • Acquisition Objective: 165 • Marine Corps: 153 • AFSOC: 12

  5. System Description • RTCASS consists of: • Eleven (11) assets in a two “bay” stack • Six (6) additional assets in frame assembly • A keyboard, monitor and arm assembly  • Any single RTCASS asset weighs no more than 150 pounds in shipping configuration  • RTCASS electrical and mechanical interfaces replicate the existing CASS hardware and software interfaces

  6. MMF USMC Single Wide MMF KA-18A Delivered with RTCASS installed Reduced footprint Space saving efforts Fold up/down stainless steel table Removable ECU rails Rails will secure against bulkhead (no impact to space) New higher efficiency three ton ECU’s (2) More robust UUT blower Provides the recommended pressure and CFM for the UUT cooling Mounted on ceiling (far right corner) Insulated to avoid hearing conservation program F/W MALS will receive KA-18A’s only These sites already have TPS MMF’s R/W MALS will receiveKA-18A’s and KA-31’s KA-31 is the new TPS MMF 6

  7. Current MMF Action Chits FAC-095 AFMS hose length Not a MMF Program Issue FAC-097 ECU Thermostat locations Recommend moving thermostat location FAC-098 RTCASS MMF’s do not come with load rails Recommend outfitting all MMF’s with holes to support rails FAC-099 Additional OTPS storage MMF’s at MALS-14 7

  8. Future RTCASS Initiatives • Integrating Mainframe CASS High Power module to RTCASS • Available CY 2010 • Will integrate the new CASS CNI ancillary to RTCASS • Tentatively available CY 2012

  9. RTCASS-HP

  10. Mainframe CASS Modernization Status [ 553 ] (Procured 1990 – 2003) Mainframe CASS (Hybrid – RF – CNI – HP – EO) (2004 – 2008 demo) (Procured2003 – 2010) [21] [130+ ] RTCASS RTCASS-HP

  11. RTCASS-HP Plan • Integrate current Mainframe HP Subsystem to RTCASS • Requires physical and S/W integration • Requires TPS conversion & Regression Test Phase • Capitalize on existing CASS HPDTS double- wide vans • Installation VIA round robin at MALS sites • Twoadditional double-wide vans required to support increase from 16 CASS HPDTS to 18 RTCASS-HP

  12. BOEING Step 4 NI Step 5 DRS Step 3 NI MALS REUSE Step 2 Step 1

  13. Fleet Site Requirements • RTCASS-HP Fleet Sites (18 Total – increased from 16) • RADAR only MALS • MALS 11 (Qty 4) • MALS 13 (Qty 2) • MALS 31 (Qty 3) • MALS 41 (Qty 1) • RADAR & ALQ MALS • MALS 12 (Qty 2) • MALS 14 (Qty 6)

  14. RTCASS IOC Fielding Plan RTCASS will be fielded by Platform Allows for orderly OTPS Conversion Accelerates Legacy Equipment Removal and associated Logistics Support. Allows for reallocation of Mainframe CASS for USN use Allows for orderly MOS conversion RTCASS Fielding profile allows for the phased removal of CASS stations and legacy ATE to mitigate any TPS Rehost Issues. RTCASS installed at North Island, then shipped to MALS CASS RF removal based on TPS conversions Anticipates station removal acceleration based on TPS conversion

  15. MALS 11 TSA CASS INSTALLS CFG DATE HYB (1) Installed RF (1) Installed CNI (1) Installed EO3 (1) Installed RFHP (1) Installed RTCASS (4) DEC 09 RTCASS (2) APR 10 RTHP (1) FY 10 LEGACY ATE REMOVAL ATE DATE IMUTS (2) APR 09 NEWTS APR 10 NIATS APR 10 CASS HYB (1) APR 10 CASS RF (1) APR 10 CASS RFHP (1) FY 11 HTS (2) FEB 11 CASS EO (1) FY 11 CASS CNI TBD

  16. MALS 11 CCSP/FOSP CASS INSTALLS CFG DATE HYB (3) CCSP Installed RF (3) CCSP Installed CNI (1) CCSP Installed EO3 (1) CCSP Installed RFHP (2) CCSP Installed EO3 (1) FOSP Installed RTCASS (1) CCSP APR 10 RTCASS (5) CCSP SEP 10 RTHP (2) CCSP FY 11 RTCASS (3) CCSP JAN 11 RTCASS (4) FOSP JAN 11 RTHP (1) FOSP FY 11 LEGACY ATE REMOVAL ATE DATE NEWTS APR 10 NIATS (3) APR 10 CASS RF (3) SEP 10 CASS HYB (3) SEP 10 CASS RFHP(2) FY 11 HTS (4) FEB 11 CASS EO (2) FY 11 CASS CNI TBD

  17. MALS 12 CCSP LEGACY ATE REMOVAL ATE DATE TTS JUL 09 DTB NOV 09 IMUTS (2) NOV 09 NEWTS (2) NOV 09 CASS RF (1) JAN 10 NIATS MAR 10 CATIIID (2) MAY 10 RADCOM (2) AUG 10 CASS RF(2) AUG 10 CASS HYB (3) JAN 11 HTS (2) JAN11 CASS RFHP (2) FY 10 CASS EO (2) FY 11 CASS CNI TBD CASS INSTALLS CFG DATE HYB (3) CCSP Installed RF (3) CCSP Installed CNI (1) CCSP Installed EO3 (1) CCSP Installed RFHP (2) CCSP Installed RTCASS (5) CCSP JUL 09 RTCASS (4) CCSP FEB 10 RTHP (2) CCSP FY 10 EO3 (1) FOSP Installed

  18. MALS 13 CCSP CASS INSTALLS CFG DATE HYB (3) CCSP Installed RF (3) CCSP Installed EO3 (1) CCSP Installed RFHP (2) CCSP Installed RTCASS (2) CCSP Installed RTCASS (3) CCSP APR 09 RTCASS (2) CCSP MAY 10 RTHP (2) CCSP FY 10 LEGACY ATE REMOVAL ATE DATE IMUTS (3) JUN 09 CASS RF (1) OCT 09 CASS HYB (3) OCT 09 NEWTS (2) OCT 09 CASS RF (2) AUG 10 CASS RFHP (2) FY 10 CASS EO (1) FY 10 CNI TBD

  19. MALS 14 TSA CASS INSTALLS CFG DATE EO3 (1) Installed RFHP (1) Installed RTCASS (3) Installed RTHP (1) FY 10 LEGACY ATE REMOVAL ATE DATE IMUTS JUN 09 CASS RFHP FY 10 CASS EO (1) FY 10

  20. MALS 14 CCSP/FOSP CASS INSTALLS CFG DATE HYB (1) CCSP Installed RF (4) CCSP Installed CNI (1) CCSP Installed EO3 (1) CCSP Installed RFHP (2) CCSP Installed RTCASS (5) CCSP Installed RFHP (1) FOSP Installed RTCASS (5) CCSP Installed RTCASS (2) CCSP JUN 09 RTCASS (2) CCSP NOV 09 RTHP (2) CCSP FY 10 RTCASS (2) FOSP MAY 10 RTHP (3) FOSP FY 10 LEGACY ATE REMOVAL ATE DATE IMUTS APR 09 CATIIID (2) AUG 09 DTB (3) SEP 09 TTS (3) SEP 09 NEWTS OCT 09 CASS RF (1) JUN 09 RADCOM (3 of 5) FEB 10 HYB (1) MAY 10 RADCOM (2) AUG 10 CASS RF (2) AUG 10 CASS RFHP (3) FY 10 CASS EO (1) FY 10 CNI TBD

  21. MALS 31 CCSP/FOSP CASS INSTALLS CFG DATE HYB (3) CCSP Installed RF (2) CCSP Installed CNI (1) CCSP Installed EO3 (1) CCSP Installed RFHP (2) CCSP Installed RFHP (1) FOSP Installed EO3 (2) FOSP Installed RTCASS (5) CCSP SEP 09 RTCASS (4) CCSP DEC 09 RTHP (2) CCSP FY 10 RTCASS (1) FOSP SEP 09 RTCASS (3) FOSP APR 10 RTHP (1) FOSP FY 10 LEGACY ATE REMOVAL ATE DATE NEWTS (2) AUG 09 CASS RF (2) AUG 10 IATS (2) MAR 10 CASS RFHP (3) FY 10 CASS HYB (3) JAN 11 CASS EO (3) FY 11 HTS (6) JAN 11 CNI TBD

  22. MALS 41 CCSP CASS INSTALLS CFG DATE HYB (2) CCSP Installed RF (2) CCSP Installed CNI (1) CCSP Installed EO3 (1) CCSP Installed RFHP (1) CCSP Installed RTCASS (4) CCSP FEB 11 RTCASS (2) CCSP JUN 11 RTHP (1) CCSP FY 11 LEGACY ATE REMOVAL ATE DATE NEWTS (2) JUN 11 NIATS JUN 11 CASS HYB (2) JUN 11 HTS (3) SEP 11 CASS RF (2) SEP 11 CASS RFHP (1) FY 11 CASS EO (1) FY 11 CNI TBD

  23. R/W MALS SITES SITE RTCASS / DATE MALS 16 CCSP (3) DEC 09 MALS 24 CCSP (3) JUL 15 MALS 26 CCSP (2) JUL 09 (1) SEP 09 (1) MAR 13 (1) JAN 17 MALS 26 TSA (4)Installed 2 CASS RF removed AUG 09

  24. R/W MALS SITES SITE RTCASS / DATE MALS-29 CCSP (1)Installed (1) JUL 09 (1) DEC 10 (1) JAN 17 MALS 36 CCSP (3) JAN 13 (3) JAN 15 MALS 39 CCSP (3) JUL 12 24

  25. R/W MALS SITES SITE RTCASS / DATE MALS 39 TSA (3) JAN 10 MALS 49 CCSP (4) JAN 17 (Res. Regional Maint.) MCAF Quantico (3) JUL 11 – (HMX-1) 25

  26. Questions ?