1 / 9

Repair of Reinforced Concrete of Existing Nuclear Power Plants (RCTG)

Repair of Reinforced Concrete of Existing Nuclear Power Plants (RCTG). Chiara Ferraris, NIST Nathan Sauer, SIMCO Technologies. Objectives. Categorize codes and standards related to concrete repair in NRC documents

dian
Télécharger la présentation

Repair of Reinforced Concrete of Existing Nuclear Power Plants (RCTG)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Repair of Reinforced Concrete of Existing Nuclear Power Plants (RCTG) Chiara Ferraris, NIST Nathan Sauer, SIMCO Technologies

  2. Objectives • Categorize codes and standards related to concrete repair in NRC documents • Identify relevant repair concrete codes and standards missing from the NRC documents • Identify technologies and new research that could translated in to new standards and codes to be adopted by an SDO • Identify new technology and research needs to fill knowledge gaps in existing concrete repair codes and standards

  3. Expected Results • Inventory of relevant NRC standards with gaps and overlaps analysis. • Review of current citation of concrete codes and standards in NRC regulatory documents • Recommendations for revision or new development of concrete repair standards

  4. Table of content • Introduction • Objectives overview • Inventory of NRC documents • Evaluation of the concrete structure • Concrete repair strategy and design • Repair implementation • Monitoring quality control • Conclusions • Index of Standards documents

  5. Overall recommendations • NRC should have a mechanism to evaluate any new version of an SDO document and determine its adoption or clearly state the reason for rejection • Develop a repair code specific for nuclear structures • Increase/sponsor research on the effects of radiation on concrete, combined with the effect of temperature exposure over a long period of time.

  6. Overall recommendations (2) • Standardized process from NRC should be implemented to pre-approve new technology and materials • Develop models for prediction of service life of repairs, especially taking into account the interaction with the concrete substrate • Develop models for evaluation of remaining service life of a damaged structure.

  7. Overall recommendations (3) • Develop standard test methods to evaluate a structure for repair, quality control and quality assurance.

  8. Schedule • July 2011: TG was approved by NESCC • November 2012: Final report to ballot • January 2013: address comments • February 2013: publication

  9. Questions? Comments?

More Related