1 / 5

Installation step 4. (3 days)

Installation step 4. (3 days). B. A. A. Install temporary support It’s made of 2 halves; the upper one is brought into position through rotation about axis “A” (to avoid risks for the beam pipe)

dolan
Télécharger la présentation

Installation step 4. (3 days)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Installation step 4. (3 days) B A A • Install temporary support • It’s made of 2 halves; the upper one is brought into position through rotation about axis “A” (to avoid risks for the beam pipe) • It has 4 flaps (“B”) at ±45º for fixation of beam-pipe and SPD supports prior to transfer their load to ITS • Align (survey) temporary support to the beam pipe

  2. Installation step 5. (4 days) • Spoke structure reduces material in front of FMDs and allows for visual inspection • Test FMDs • FMDs have pigtails up to the outer edge of the 3rd cone • Remove 3rd cone lifting tools FMD – Si1 Dummy 3rd cone • Fix support for beam pipe and FMD (“3rd cone”) to temporary support • The 3rd cone is made of two halves containing the FMDs • lifting tools allow for slow and accurate positioning of 3rd cone Lifting tool

  3. Installation step 6. (2 days) • Mount and adjust monitoring system of bellow movements • Responsibility ALICE • Non-touching capacitive sensors are proposed • Mount and adjust 1st support to the beam pipe • Responsibility AT/VAC • Survey Lifting tool

  4. Installation step 7. (8 days) Temporary support 3rd cone SPD services Section 2 SPD cone • Install the two SPD half-cylinders (Resp. ALICE) • Two half cylinder/cones • Specific installation tools are being designed • SPD services (cables, fibres & capillaries) are pre-assembled in the cones • Fix the two, coupled, SPD half-cylinders to temp. support, above the 3rd cone, using a 2nd series of bolts & precision plugs • SPD fixed in cantilever mode to temp. support, SPD pigtails on RB24 side unconnected • Remove section 2 of beam pipe support (Resp. AT/VAC)

  5. Installation step 8. (7 days) Temp.Support • Mount and adjust 2nd support to the beam pipe (resp. AT/VAC) • Survey • Outer ITS, SPD & beam pipe are now an integral unit SPD SDD SSD TPC/C4 • Slide outer ITS onto SPDs (Responsibility ALICE) • Transfer load of SPD and 3rd cone (beam pipe) from temporary support to ITS • Connect SDD and SSD on RB26 side • Final fixation of SPD pigtails on RB24 side to ITS cone

More Related