1 / 11

CALTRANS COMPONENT REPAIR MODELS

CALTRANS COMPONENT REPAIR MODELS. by Stuart D. Werner for presentation at Third Tri-Center Workshop Las Vegas NV October 13-14, 2004. BASIS FOR MODELS: Judgment/Experience of Caltrans Staff. Bridges Tom Harrington and Steve Sahs Approach Fills Kirsten Stahl, Dan Adams, Minh Ha Tunnels

draco
Télécharger la présentation

CALTRANS COMPONENT REPAIR MODELS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CALTRANS COMPONENT REPAIR MODELS by Stuart D. Werner for presentation at Third Tri-Center Workshop Las Vegas NV October 13-14, 2004

  2. BASIS FOR MODELS:Judgment/Experience of Caltrans Staff • Bridges • Tom Harrington and Steve Sahs • Approach Fills • Kirsten Stahl, Dan Adams, Minh Ha • Tunnels • Randy Anderson, Ray Mailhot, Umakant Dash, Bob Delbarrio • Roadway Pavements • Bill Farnbach, Tinu Mishra, Brian Weber, Leo Mahserelli

  3. REPAIR MODELS: Purpose • For a Given Damage State, Repair Models will Estimate: • Repair Costs • Repair Durations • Functionality (Traffic State) during Repairs • These will Differ for Different Regions of U.S. due to Differences in: • Available Repair Resources • Component Construction, Maintenance, and Repair Practices

  4. REPAIR MODELS:Component Functionality (i.e., Traffic State) • Percent of Pre-EQ Traffic-Carrying Capacity that can be Accommodated by Component while Repairs are Proceeding • Varies with Time after EQ • To Reflect Estimated Rate of Repair of Damaged Component • REDARS Currently Represents Reduced Functionality as: • Reduced Lanes • In Practice, Can Also Use Other Metrics, e.g., • Reduced Speeds • Load Restrictions

  5. REPAIR MODELS:Role in REDARS Analysis (For One EQ/Simulation and Four Previously-Selected Post-EQ Times) • Repair Models Estimate Traffic States for All Components in Roadway Network • After Damage States have been Estimated • For Damaged Components • Their Roadway Link will Have Reduced Traffic-Capacity • System-State Model of Entire Roadway Network is Formed (shows all link traffic-carrying capacities throughout network) • Transportation Network Analysis Procedure is Applied to System-State Model (estimates post-EQ travel times)

  6. REPAIR MODELS:Assumption 1 • Current REDARS Repair Models • Assume Required Repair Resources are Immediately Available • However, if There are Many Damaged Components: • Available Repair Resources will be Stretched • This will Increase Repair Times Given in Repair Model

  7. REPAIR MODELS:Assumption 2 • Use California (Caltrans) Repair Models as Default: • Only Region in U.S. with Significant Recent Experience in Actual Post-EQ Highway-Roadway Repairs • For Other Regions of U.S. • Caltrans Repair Models can be Frame of Reference (Starting Point) • Should be Modified to Account for Differences in Repair Resources/Practices, Construction Practices, etc.

  8. BRIDGE REPAIR MODEL: ASSUMPTIONS

  9. BRIDGE REPAIR MODEL: DEFAULT TRAFFIC STATES

  10. BRIDGE REPAIR MODEL: DEFAULT REPAIR COSTS • Repair Cost = Repair Cost Ratio (RCR) x Replacement Cost (REP) • Default Replacement Cost = $150/ft2 x Bridge Deck Area • $150/ft2 is Caltrans unit cost for typical cast-in-place prestressed concrete box-girder bridge in Northern California • Default Replacement Cost and RCR can differ for other materials of construction and regions of U.S.

  11. DEFAULT REPAIR COST MODELS: OTHER COMPONENTS • Approach Fills • Due to EQ-Induced Settlement • Based on California Construction/Repair/Maintenance Practices, and Typical RCRs and REPs • Assumed Settlement Ranges for Damage States 1, 2, and 3 • Roadway Pavements • Due to EQ-Induced Permanent Ground Displacement (PGD) • Based on California Construction/Repair/Maintenance Practices, and Typical RCRs and REPs • Assumed PGD Ranges for Damage States 1 through 5 • Tunnels • Due to Ground Shaking and PGD • Based on Construction and Maintenance Practices for Caldecott Tunnel through Oakland-Berkeley Hills

More Related