350 likes | 597 Vues
People. Team MembersDwayne Stammer - CprEFrancois Munyakazi
E N D
1. Viking Pump Flow Manager - Phase 2 Senior Design
May 06-12
2. People Team Members
Dwayne Stammer - CprE
Francois Munyakazi – EE
Dan Paulsen – CprE/EE
Faculty Advisor
Nicola Elia
Client Info
Viking Pump Inc.
3. Outline Introduction and problem statement – Dan Paulsen
Design and implantation – Dwayne Stammer
Schedule, financial, and closing – Francois Munyakazi
Future Work – Team
4. Definitions Flow meter: An instrument used to measure pressure, flow rate, and discharge rate of a liquid, vapor, or gas flowing in a pipe
Set point: The speed that a pump has to rotate in order to achieve a given flow or output pressure
Viscous: Having a relatively high resistance to flow
QVGA: 4x6 inch high resolution touch screen, has onboard analog voltage inputs and outputs
5. Problem Statement Design a system to do the following
Control a pump to maintain a given flow using only speed, pressure, and temperature measurements
Provide an easier user interface to control flow rate and other working parameters
Provide access to system through serial bus
6. Why? Why is this valuable?
Measuring flow for viscous fluids is very hard
Less parts needed to build a pumping system
Has many other uses such as batch flow, and error detection
Inline meters to measure flow can hinder flow performance
Problems with current system
Hardware out of date
User interface is outdated and difficult to use
7. System Use System will be configured and run by trained technicians
Will operate in harsh “factory floor” environments
Temperatures ranging from 40° to 120°F
Long periods of use
8. Assumptions Inputs from the system will be:
Inlet pressure – input voltage
Outlet pressure – input voltage
Temperature of the fluid – input voltage
Current pump speed – input voltage pulse - 60 pulses/revolution
Outputs to the system will be:
4-20mA signal to DC Drive
9. Limitations The controller must be able to operate in a real time environment
The software implementation must be portable
The controller solution must be economical
The controller must be able to control the actual flow within 0.25% of the set point
10. End Product Implementation for basic prototype that properly controls pump system
Documentation of controller and source code
11. Problem Definition Current flow manager is difficult to use and obsolete
User interface needs updated to a much more intuitive interface
Will be solved using a new touch screen interface
Hardware used is no longer available because it was custom made to the application
Will be solved using over the shelf parts
Writing software with different hardware platforms in mind
12. System Overview
13. System Overview Four inputs
Inlet pressure
Output pressure
Fluid Temperature (to determine viscosity)
Pump RPM
One output
Desired motor speed
14. Previous Model Outdated User Interface
15. Previous Model
16. Updated Model Touch screen user interface
Updated C code
Standardized equipment (not as much customized circuitry required)
PC interface with more advanced GUI features
17. Updated Model Standardized equipment
18. Updated Model PC interface
19. Updated Interface Circuitry
20. Updated Graphical Interface The flow menu will allow the user to input and update the desired flow rate. This design is preliminary and should be modified to include greater functionality.The flow menu will allow the user to input and update the desired flow rate. This design is preliminary and should be modified to include greater functionality.
21. Initial Performance Measurement
22. Updated Flow Manager
23. Algorithm Performance
24. Schedule
25. Personal Effort
26. QVGA Repair $250 Provided by Senior Design
Pump equipment $0 Donated by Viking
Miscellaneous parts $175 Viking/Group members
Poster $40 Group members
Total material cost: $465
Total material cost
Labor (839hrs @ $11.00) $9,229.00
Materials 465.00
Total cost of project: $9,694.00
7,525.50 Previous group
Project Total thus far $17,219.50
Project Costs
27. What Went Well Some part were easy to get from common store
Design of project was easy, important decisions already made by previous team
Communication between components was fairly well
Good Coordination between team members
28. What Didn’t Go Well Understanding the definition of the project
Learning how to interface with the pump
QVGA was damaged because we did not understand how the pieces should work together.
Dealt with odd behavior with parts which were out of the scope of our project.
Communication with sensors and QVGA
29. Knowledge Gained Learned the control algorithms for pump flows
Learned How to program the QVGA
Developed team communication
Learned how to effectively distribute work loads among team members
Learned how to better work with clients while keeping a project on track
30. Risk Management Anticipated risks
Loss of code
Loss of team member
Anticipated risks encountered
Loss of team member
John Taylor went to internship
Cliff Pinsent graduated
Unanticipated risks encountered
Damage of the QVGA
31. Work Completed Repair QVGA
Acquired model from Viking
Studied algorithm and controllers
Designed and prototyped GUI screens
Detected I/O of QVGA
Wrote C code and serial code
Build pump interface between QVGA and pump
Designed circuitry for sensor testing and QVGA
32. Work Completed Cont. 80% Completed writing / debugging the C code to control flow
80% write and implement the full GUI
Created a methodology for the QVGA to be controlled via serial comm.
33. Closing The previous version of the product
Pros: Has a very large success
Cons: User interface
The lack of user friendliness of the device even thought it is still the best device on the market
34. Closing Cont. Viking Pumps needs a well-designed flow control manager
To be used with already existing pumps.
Cost effective
Portability
Moving from one hardware to another without major software rework
35. Questions?