An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Installation of micromegas in ATLAS Status report

  2. MBT0 • New chamber being built • Lower resistivity along strips (10–20 MΩ/cm) • Fix of some HV connection problems • New drift electrode (FR4, non-transparent) • Better gas tightness • Chamber expected to be ready end of this week

  3. MMSW • Four planes with two readout coordinates each • All materials were finally last Wednesday at CERN • PCBs were baked and measured; good results • By Friday the Kapton layer was laminated onto the PCBs • This week the resistive strips will be applied • Beginning of next the bulk (mesh) will deposited • Chambers are expected to be ready end of next week • Plan: test chambers with cosmics in the lab for one or two days

  4. MMSW measurement results Scatter of position of strip ends Strip # x y x y 6 5 4 1 2 3 Relative distances between targets for the five PCBs

  5. APV25 • All components are in firm in Neuchatel (Hybrid SA) that does the hybrid assembly • Hope to have hybrids end of January/ 1st week of Febr.

  6. Installation in ATLAS • First visit in UX15 last Wednesday • Measured cable lengths (except for SW) – 25m from rack to PP • List of parts needed • HV and ethernet cables from USA15 to PP are already in place (S. Malyukov); we need to install the connectors • Gas from MPI Ar:CO2 rack in Sector 14 (Thanks) • Gas piping to MBT0 will be done by J. Godlewski et al. • Next visit tomorrow morning • Measure the SW cables length; agree on support and cable routing • Agree on installation dates