1 / 19

KPI ’ s for Measuring & Controlling STO Projects

KPI ’ s for Measuring & Controlling STO Projects. E.J. (Ted) Lister Lister Management Inc. Agenda. Project Controls / Project Management Definitive Definitions The 4 + Key Performance Indicators Measuring Performance Trending, Forecasting Questions.

eagan
Télécharger la présentation

KPI ’ s for Measuring & Controlling STO Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. KPI’s for Measuring & Controlling STO Projects E.J. (Ted) Lister Lister Management Inc.

  2. Agenda • Project Controls / Project Management • Definitive Definitions • The 4+ Key Performance Indicators • Measuring Performance • Trending, Forecasting • Questions

  3. Project Controls / Project Management Overview… • You must be able to measure, in real-time, the status of your project based on KPI’s and their set Targets • Projects need to be both controlled and managed • It’s important to understand what you can control, and what you cannot; what you can manage, and what you cannot • A method of measuring needs to be established for both controlling and managing the project

  4. Project Controls / Project Management Overview – cont’d… • Establish Project Controls at project kick-off • Work-list / Work-scope • Budget • What-if scenarios / Risk Management • KPI’s and Targets • Project Management begins at Work-list cut-off • Work Management (Direct) • Resource Management (Indirect)

  5. Definitive Definitions • Planned Value • Estimate of Wrench-hours for an activity • Earned Value • % complete of a planned activity based on field status • Actual Value • Cost measurement; also used to measure worker performance • Longest Job • Zero-float, determines the duration of the outage • Not to be confused with critical path, which accounts for risk

  6. Definitive Definitions – cont’d • S-Curve • Chart of values distributed along wrench-hour/time x y axis • Baseline • A snapshot of the initial plan/schedule before feed-out • Performance • Earned vs. Planned, Actual vs. Earned, Actual vs. Planned • What-if Scenarios • Leveling a programmed plan to determine the best case scenario based on cost, schedule duration, and wrench-hours

  7. The 4+ Key Performance Indicators In Order of Magnitude… • Safety, Health & Environment • Worker Performance • Wrench-time (76.7% direct in a 10 hour shift) • QA/QC (rework) • Schedule (earned vs. planned) • Cost (actual vs. planned) • Direct • Indirect

  8. The 4+ Key Performance Indicators Setting Key Performance Targets… • Safety, Health & Environment = +5000 points • Worker Performance • Wrench-time (Direct) = 75% • QA/QC = 0 Rework • Schedule (Feed-in – Feed-out) = 31 Days • Cost = $41.2M • Direct (Wrench-hours x $45.00/h) = $18.7M • Indirect (115% of Direct) = $21.5M • Planning, Pre-Work, Post, Contingency = $1.5M

  9. The 4+ Key Performance Indicators Safety, Health & Environment… • Set positive targets for SH&E • Earn points each shift for 0 incidents (150 points) • Earn points for ProAct card reporting (150 points) • Earn points for audits (200 points) • Lose points for recordable incidents • A lost-time incident takes you into the negative with no chance of recovery • Incentives are based on positive numbers

  10. The 4+ Key Performance Indicators Worker Performance… • Set realistic direct wrench-time for worker performance • No more than 75% • Remember, once you determine direct wrench-hours all indirect resources and logistics are based on this number • If you don’t use strategic planning to support this number your chances of achieving this target will be diminished • Use productivity factors based on: season, location, worker experience, resource availability (inspectors, cranes, etc.)

  11. The 4+ Key Performance Indicators Schedule… • Establish a schedule in your planning software with a clearly defined WBS (Work Breakdown Structure) and Phase • The WBS is a vertical hierarchy of physical locations • The Phase is a horizontal section of work types • Use What-if Scenarios to determine the longest job (series of planned activities with no float) • Control the longest job; manage the remaining tasks

  12. The 4+ Key Performance Indicators Cost… • The cost is based on Work-scope + Indirects + Contingency = Budget • Costs can only be controlled through Work-scope changes • Costs are managed, not controlled, through performance • Costs need to be measurable based on direct and indirect; found and added; WBS and Phase

  13. 100% Or Total Planned Man-hours Original Man-hour Overrun Schedule Slippage STATUS = % COMPLETE or MHRS Schedule Variance New Scheduled Man-hours New schedule affected by activities not completed as per schedule plus added and extra work Original Baseline Scheduled Man-hours Earned Man-hours Original Target Current Day New Target Focus on Work Ahead History TIME Measuring Performance Project Performance S-Curve… • Baseline Planned • Earned Value - WP • Actual Value - $ • Found/Added Work • Historical Trend • Forecast

  14. Measuring Performance • Baseline… • Save your project as a baseline comparative project just prior to feed-out • Use the baseline for variance reporting and historical reference

  15. Measuring Performance Updating… • It imperative that field status reporting is done prior to the end of each shift for each scheduled activity • The programmer will update the project in the planning software as a percentage complete (earned value) • Actual hours can be tracked in the planning software, or accounting software, from timesheets • The programmer must advance the project to the current status date and time

  16. Measuring Performance Updating – cont’d… • No uncompleted work can ever appear behind the status date line • Use earned value % complete; do not try to capture actual start and finish times

  17. Trending and Forecasting Using S-Curve Data… • Trending performance should begin between day 3 – 5 to establish data to forecast probable target completions • Use trending and forecasting to control the project Work-scope

  18. Trending and Forecasting Reporting… • A daily one-page report should be generated to illustrate the status of each KPI • Additional information can also be included: • New Critical, All Critical • Found Work, New Work, Delays • Weather, POB, etc.

  19. E.J. (Ted) Lister Lister Management Inc. akaboreese@hotmail.com

More Related