An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. X-ray Pump-Probe Instrument David Fritz XPP Instrument Scientist June 9, 2009

  2. Outline Overview XPP Update from previous FAC Component Status Design Procurement and Fabrication Early commissioning?

  3. XPP Instrument Overview

  4. Update from Fall FAC • Received advanced procurement approval December 18, 2009 for: • Sample Goniometer • Detector Mover • Final Instrument Design Review successfully held Feb 24, 2009 • Procurement authorization for everything except OPA, multipass amplifier • Baseline change request processed to include large offset monochromator system for XPP • Procurement documents were reviewed at the XCS advanced procurement review April 24, 2009 and the documents are being updated

  5. Laser Tables and Enclosure • Completed design of laser containment system and optical table layouts • Design review November 14, 2008 • Laser tables are fabricated and are in storage in the control room. • Anchor holes are drilled and tables are ready to be installed once granite is installed • Enclosure PO placed April 20, 2009 5’ x 12’ 5’ x 6’

  6. X-ray Optics Tables • Completed final design of X-ray optics tables • Final design review January 26, 2009 • Granite PO placed April 14, 2009 • Expected to be delivered in July w/ rails installed • Anchor holes for the earthquake restraints already drilled

  7. Sample Goniometer • Received advanced procurement authorization Dec. 18, 2008 • Goniometer PO awarded to Huber April 1, 2009 • Expected to be delivered in April 1, 2010 • Vendor site visit scheduled for July 17, 2009

  8. Detector Mover • Received advanced procurement authorization Dec. 18, 2008 • Robot basing design study completed in January, 2009 • Robot PO awarded March 31, 2009 • Expected to be delivered this week • Robot support design review held May 22, 2009 • Detailed fabrication drawings in process • Robot software PO in process

  9. Hutch Facilities • Work benches and storage cabinets received and installed • Tools and tool boxes PO placed March 24, 2009 • Expected to be delivered and installed in August • Raised floor PO in process (req submitted March 10) • Cable trays are here

  10. Laser Equipment • RFP issues for 20 Ghz Oscilloscope • Various optics and optomechanics PO’s in process • Much more to be procured over the next 6 months • Hopefully procurement authorization will be given for OPA and multipass amplifier shortly so req’s can be placed

  11. Updated Schedule FY08 FY09 FY10 FY11 Preliminary Design Reviews • X-ray Optics Support Tables – August 2008 • Detector Mover Support – May 2009 XPP Advanced Procurement Review – November 2008 Final Instrument Design Review – February 2009 Final Design Reviews • Optical Table Layout\Containment – November 2008 • X-ray Optics Support Tables – January 2009 • Detector Mover Support – May 2009 CD-3 - July 2009 Award PO • Sample Goniometer – April 2009 • Hutch Facilities – June 2009 • Detector Mover – March 2009 • X-ray Optics Support Tables – April 2009 • Laser Containment System – April 2009 • Optical Tables – April 2009 • Detector Mover Support – July 2009 Receive • Optical Tables – May 2009 • Hutch Facilities – August 2009 • X-ray Optics Support Tables – July 2009 • Laser Containment System – July 2009 • Detector Mover – June 2009 • Sample Goniometer – April 2010 • Detector Mover Support – September 2009 Ready for User Run – July 2010

  12. Early Commissioning? X-ray support tables are expected to be installed in July Vacuum transport can/will be installed in the summer as well Prototype X-ray diagnostics will be ready in the fall Would be extremely beneficial to receive some early “machine time” to test prototype diagnostics, optics, materials, etc… 4-8 hours per week??? This would significantly reduce the risk and commissioning time allocated to the dedicated XPP instrument commissioning