Nationwide DGPS Project Status

This report provides an update on the nationwide DGPS project, including operational sites, coverage goals, progress on site assessments and property surveys, and partnership with various organizations.

Télécharger la présentation

Nationwide DGPS Project Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Nationwide DGPS Project Status

  2. NAVCEN Mission Statement • The Coast Guard Navigation Center promotes safe, secure, and efficient transportation on United States’ waterways by providing: • Operational and technical support for electronic navigation systems • Quality positioning, navigation and timing signalsLORAN NDGPS DGPS NAIS • Accurate and timely waterways information services.

  3. Maritime / Nationwide DGPS Currently 86 operational sites: USCG NAVCEN is the Operational Control for all sites. Newly commissioned Maritime Information Operations Center (MIOC) Nationwide DGPS Partnership: USCG Maritime  39 sites Dept of Transportation  38 sites U. S. Army Corps of Engineers  9 sites

  4. USCG Maritime Coverage • USCG funds & maintains 39 sites. - Maritime navigation and ATON Positioning

  5. U. S. Army Corps Coverage • US Army Corps of Engineers funds & maintains 9 sites. - Inland Waterway Coverage • - ATON, Navigation, Underwater Surveying & Dredging Slide 7

  6. DOT Funded Coverage • US Dept of Transportation funds 38 sites which are operated & maintained by the USCG and contract support. • Precision Agriculture, Intelligent Transportation Systems,Positive Train Control. Slide 8

  7. Nationwide DGPS Coverage Planning & Verification

  8. N/DGPS Project Status Report

  9. Nationwide Single Coverage Goal Sites Required for the 98% Single Coverage Goal • Sage Junction, ID (New Build) • Marshall, TX (New Build) • Big Lake, TX (New Build) • Patten, ME (New Build) • St. Mary's, WV (New Build) • Bliss, ID (New Build) • Tucson, AZ (New Build) • Carlsbad, NM (New Build)

  10. Sites Required for the 98% Single Coverage Goal

  11. NDGPS Coverage 98% Coverage

  12. Prepping a Site Find a Candidate Property Conduct a Site Assessment Complete an Environmental Investigation under the guidelines of the Programmatic EA (FONSI) Complete a Real Property Survey - Includes Soil Boring Samples Complete the Installation Design Plan Complete the Property Use Agreement (Lease/Purchase/ISSA)

  13. NDGPS FY08 Progress • Bliss, ID (AKA Gooding New Build) • Site Assessment Completed • Property Survey (Scheduled for June 16th-20th: Completed!) • SF299 RP Document In Progress By USCG (BLM Property) • EA Underway Through FHWA • IDP (Scheduled for June 9 w/Property Survey: Completed!) • Tucson, AZ (New Build) • Site Assessment Completed • Property Survey Completed • SF299 RP Document In Progress By USCG (BLM Property) • EA Underway Through FHWA Pending Biological Evaluation & PW • Public workshop (Scheduled for May 22nd:Completed!) • IDP (90% Complete Pending Results Of The EA)

  14. NDGPS FY08 Progress • Carlsbad, NM (New Build) • Site Assessment Completed • Property Survey Completed • SF299 RP Document In Progress By USCG (BLM Property) • EA Underway Through FHWA Pending Public Workshop • IDP Package Completed • Additional Items: • Archaeological Survey letters sent to Native American tribes on 25 Jan 08. • Public workshop (Scheduled for May 20th: Completed!)

  15. NDGPS FY08 Progress • Sage Junction, ID (AKA Idaho Falls New Build) • Site Assessment Completed • Property Survey (Scheduled for June 9th-13th : Completed!) • Lease Negotiations Pending • EA (Scheduled to commence w/Property Survey) • IDP Pending Results Of The EA • St Marys, WV (New Build) • All Preparations Completed • Site Ready For Construction (Scheduled for AUG 11th- SEP 26th) • SOVT (Scheduled for SEP 29th – OCT 3rd)

  16. NDGPS FY08 Progress • Marshall, TX (New Build) • Site Assessment Completed • Property Survey Completed • EA Completed (FONSI signed on 17-Jun-08 and received by CG) • IDP Completed • Lease Negotiations Pending • Big Lake, TX (New Build) • Site Assessment Completed • Property Survey Completed • EA is Underway Through the FHWA • IDP Completed • Lease Negotiations Pending Results of the EA

  17. NDGPS FY08 Progress • Georgetown, TX (New Build) • Site Assessment Completed • Property Survey Completed • EA Completed • IDP Completed • Lease Negotiations Pending FOC Requirements • Card Sound, FL (Miami Replacement & New Build) • All Preparations Completed Except Frame Relay (FR) Circuit Delivery • NAVCEN Requesting Onsite Survey Through Provider • Construction Is Pending SFWMD Permit (ETA Week of June 12th : Received) - Zoning Letter for Class 4 Miami Dade County Permit

  18. Maritime DGPS Progress FY08 • Salinas, PR (New Build) • Site Assessment Completed • Property Survey Completed • Interference Study (IS) Requested by USAF (Pending) • EA Pending Commencement (IS) • IDP Pending EA • Lease Pending • Eglin AFB, FL (Mobile Point Replacement & New Build) • Site Assessment Completed • Property Survey Completed • Interference Study (IS) Requested by USAF • EA Pending Commencement (IS) • IDP Pending EA • Lease Pending/Construction Pending Clearance of County Permits

  19. Maritime DGPS Recap Upgraded Receivers & Antennas: L1/L2 (L2C) Geodetic Grade Accuracy is typically 1-3 meters (10 meters published) Much better accuracy has been observed from prototype recap sites. Testing is in progress to determine typical accuracy measurements. New system architecture is easier and less expensive to upgrade as new technologies become available. 22 Slide 22

  20. Engineering Upgrades RS/IM RECAP (CRIA)RTCI UPGRADE SITE DATE OF INSTALL SITE DATE OF INSTALL Driver, Virginia 31-Jan-2008 Greensboro, North Carolina 14-Mar-2005 New Bern, North Carolina 19-Feb-2008 Macon, Georgia 06-Apr-2005 Kensington, South Carolina 22-Feb-2008 Hudson Falls, New York 01-May-2008 Tampa, Florida 07-Mar-2008 Dandridge, Tennessee 08-May-2008 Aransas Pass, Texas 21-Mar-2008 Flagstaff, Arizona 04-Jun-2008 English Turn, Louisiana 18-Mar-2008 Albuquerque, New Mexico 10-Jun-2008 Angleton, Texas 03-Apr-2008 Moriches, New York 07-Apr-2008 Cape Canaveral, Florida 04-Mar-2008 Reedy Point, Delaware 29-Apr-2008 Lompoc, California 06-May-2008 Cape Mendocino, California 14-May-2008 Tamp, Florida 20-May-2008 Wisconsin Point, Wisconsin 18-Jun-2008 Gustavus, Alaska 18-Jun-2008 Biorka Island, Alaska 25-Jun-2008 Brunswick, ME 09-Jul-2008 Pickford, MI 23-Jul-2008

  21. Card Sound, FL

  22. LT Bion J. Holbrook Bion.J.Holbrook@uscg.mil 703-350-7125 Cell 703-313-5939 Work