1 / 24

Fiber Optic Transmitter

Fiber Optic Transmitter. Electrical Department. Performance Against Goals. Goal: To assemble and build a working Fiber Optic Transmitter. To work as a team. Complete assigned activity’s on schedule. Actual performance towards goal:

elda
Télécharger la présentation

Fiber Optic Transmitter

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Fiber Optic Transmitter Electrical Department

  2. Performance Against Goals • Goal: To assemble and build a working Fiber Optic Transmitter. • To work as a team. • Complete assigned activity’s on schedule. • Actual performance towards goal: • With team work the assigned activity’s were successfully completed and turned in on schedule.

  3. Key activity’s to be completed • The Fiber Optic Transmitter Project took 15 weeks to complete. • Each week a different activity was assigned to be completed. • Each team member would contribute to the completion of that weeks activity.

  4. Key Milestone’s • Week One: • Introduction to PCB Layout: • Class discussed software choice’s for project ( Smart works or CAD) • Week Two: • Assigned Teams and project • Selected Team Members Eric Vega, Dana Roscoe, Bill Leinauer, Derek Beck

  5. Key Milestone’s • Week Three: • Introduction to PC Layout 23000. • Using Smart works to complete this activity. • Familiarize ourselves with the software. • Breadboard transmitter

  6. Activity 23000

  7. Key Milestone’s • Week Four, Five and Six. • Hand draw schematic wiring diagram on .2 grid paper • Compare each team members schematics. • Least jumpers • Size of proposed PC board. • Location of components. • Redraw selected and improved design on Electronic Workbench.

  8. Activity # 23005

  9. Activity #23007

  10. Key Milestone’s • Week Seven • PCB Layout on Smart works • 2X Plot on B size vellum

  11. Activity #23012

  12. Key Milestone’s • Week Eight ( A critical part of project) • Compare Electronic Workbench schematic to completed smart work schematic. • Check for right chips, designators, leads and proper wiring. • Color each connection with different colors to ensure correct connections.

  13. Activity #23020

  14. Key milestone’s • Week Nine • After making sure all connections are correct, duplicate schematic onto smart works. • Plot actual schematic on Mylar. • Mylar will be used to etch PC board.

  15. Activity #23025

  16. Key Milestone’s • Week Ten • Use Excel to make a parts list • Must include all required materials . • Reference designators, part and description, quantity,identification number, value, tolerance and ratings.

  17. Key Milestones • Week 11 • Complete a drill plan. • Use Excel to designate a symbol for each drill size. • List the amount of holes needed for each drill size. • Indicate location on smart work diagram.

  18. Activity #23030

  19. Key Milestones • Week 12 • Etch board • Drill pads • Decide type of enclosure for project

  20. Etching The Board

  21. Key Milestones • Week 13 • Soldering devices and jumpers.

  22. Key Milestones • Week 14 • Troubleshooting and final checks

  23. Fiber Optic Transmitter Receives parallel data from prolog and sends it over fiber in a serial form to the receiver. By using fiber the transmit rate is limited by the devices at both ends. Finished Product

  24. Questions & Comments

More Related