1 / 30

Infrastructure planning and management

Civil Engineering Dept. Master Program. Infrastructure planning and management. Lecture(3). 2013-2014. Sequence of Studies for a Single Major – Infrastructure Projects.

elizebeth
Télécharger la présentation

Infrastructure planning and management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Civil Engineering Dept. Master Program Infrastructure planning and management Lecture(3) 2013-2014

  2. Sequence of Studies for a Single Major – Infrastructure Projects A typical complete planning and implementation process involves a five-stage sequence of reports, documents, and actions for the project

  3. Sequence of Studies for a Single Major – Infrastructure Projects

  4. First Sage: Preliminary (Or Reconnaissance) Report This stage consists of office studies, field studies, and the preparation of a report. This report should answer the following questions:

  5. First Sage: Preliminary (Or Reconnaissance) Report Office studies Using available information contained in previous reports, maps, and data. Much of this information may be available from state, and local governmental agencies. Utilities, private firms and other sources. Basic materials include soils data; water quality information on environmental conditions, and population and socio-economic data. Field reconnaissance and surveys studies It is needed to confirm the office studies, to suggest changes in the layouts and estimates, and to obtain detailed information concerning additional matters

  6. Second Stage: Feasibility Report This report is authorized in case of the available data in the preliminary report is not enough and needs more clarification and details.

  7. Feasibility Report Contents

  8. Feasibility Report Contents

  9. Feasibility Report Contents

  10. Third Stage: Final Design and Preparation of Contract Documents • Contract documents include plans and specifications that are sufficiently detailed to obtain tenders (bids) from qualified construction and equipment contractors. The plans (drawings) and specifications are based on additional studies of the details of project works, the logistics of construction, other aspects related to temporary and permanent facilities, and the performance of contractors. • The sponsor and its engineers and financial specialists review the tenders made by contractors.

  11. Fourth Stage: Construction When traditional contracts are employed for the purchase of construction and equipment, additional detailed drawings needed during construction are prepared by the sponsor's engineers and by the contractors subject to the sponsor's approval. Payments to the contractors are usually made based on measurements of work in progress or completed, in accordance with the terms of the contract documents. Usually, a percentage of each payment is withheld by the sponsor and released only when the work is entirely completed and accepted.

  12. Fifth Stage: Operation The sponsor may employ outside engineers and other consultants to assist in operation for a limited period, train operators, prepare manuals for operation and maintenance, and monitor the performance of the various facilities. The operating rules may be changed on the basis of experience during the operation of the project.

  13. Formulation of a Major Engineering Project • The engineers (or the interdisciplinary team of specialists) who participate in project formulation define the location and arrangement of project components, with sufficient details concerning their sizes and functions, so that realistic cost estimates and other studies determining feasibility can be prepared. • During project formulation, the planner starts with an understanding of the needs to be satisfied and/or the problems to be solved; evaluates the available data and other pertinent information; carries out other investigations; and conceives a plan to utilize land, water, and other resources to meet the project needs and problems.

  14. Factor affecting on Selection among Alternatives

  15. Factor affecting on Selection among Alternatives

  16. Uncertainties must be Assessed Primarily by Engineering Judgment

  17. Project Costs

  18. Needs Assessment • Concept of ‘need’ used casually • Can refer to both ‘need’ for repair as well as ‘need’ for new capacity • It is difficult to judge how much infrastructure a region or a society ‘needs’ and how ‘need’ is measured • Economic viability? Growth? • What is a better approach?

  19. Approach to Defining Needs • From NCPWI 1986 - needs considers: • Consumer Demand • Recognition that demand changes • Consumer willingness to pay • Benefit-cost analysis

  20. Other Issues on Needs • Instead of focusing on conditions, establish future investment priorities • Instead of simply finding cost to repair, consider cost of alternatives with same effect • Consider infrastructure ‘output’ as measure instead of condition • Funding needs to match area of influence, e.g. federal money for federal interests

  21. More Issues • Needs assessments should distinguish: • Safety or structural defects • Capacity shortages • Upgrading to new standards • Current and future demands

  22. Life Cycle Cost Analysis (LCCA) • A ‘life cycle’ is the entire length of time from design, planning, construction, operation, maintenance, and decommissioning/demolition • It is important to understand the cost implications of design decisions across the life cycle • Also important to understand where in the life cycle that total costs occur

  23. Expected Service Life Estimates • Airport Buildings - 150 yrs • Runways - 50 yrs • Bridge Decks - 50 • Bridge Sub-/superstructure - 125 • Tunnels - 200 • Sports Complexes - 300 • Electricity/telephone lines - 400 • Any comments?

  24. Life Cycle Cost Influences

  25. Project Costs Capital cost Capital recovery costs ( or ownership costs) are incurred by purchasing assets to be used in production and service. Usually Capital costs are nonrecurring (one time costs), where as operating costs recur as long as an asset is owned. Annual cost It is include the maintenance and operation item applies to labor, supplies, and replacement of short-lived equipments and materials.

  26. Homework

  27. You were selected to design a pumping station in your region . 1. What are the studies to be prepared for this station? 2. Determine a form to estimate the capital and annual cost?

More Related