An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MICE Collaboration meetingMay 31st – June 3rd 2009RALTim Hayler, Andy Lintern DRAFT SEQUENCE OF EVENTS STEPS 1 - 3

  2. Draft sequence of eventsdepending on deliveries and ISIS schedule • Install TOF1 and KL in place for step 1 • Run step 1 (Sep 2009) • Remove TOF1 and KL (move downstream) • Install spectrometer solenoid (SS1) in step 2, in beam, position. Cool down, run to full current. • Install diffuser • Test diffuser • Perform quench test • Test diffuser • Remove diffuser • Move SS1 to parked step 2 position (This operation defines the space needed upstream of SS, is there enough room?). Install tracker into bore and align. • Move SS1 with tracker back into beam position. • Install diffuser, V plate in front of SS1 and TOF1 into cage. • Install TOF2 and KL downstream of SS1. • Run step 2 (Q4 2009)

  3. Install KL and TOF1 in place for STEP 1

  4. Remove TOF1 and KLInstall SS1 in step 2 positioncool down run to full current

  5. Install diffuserTest diffuserPerform quench testTest diffuserRemove diffuser

  6. INSTALL TRACKER Install and align the tracker into SS1 whilst in the parked, step 2, position. (This operation defines the space needed upstream of the SS, is there enough room?)

  7. Move tracker and SS1 back into the in beam position for step 2 • Install diffuser • Install V plate and TOF1 cage • Install TOF2 and KL

  8. STEP3