1 / 32

L. Waganer Consultant for ARIES Project/UCSD/DOE ARIES-Pathways Project Meeting 4-5 April 2011

Addressing Lingering Cost Questions. L. Waganer Consultant for ARIES Project/UCSD/DOE ARIES-Pathways Project Meeting 4-5 April 2011 Bethesda, MD. Questions Remain on Several Cost Topics. The cost of the enriched Lithium and Li 17 Pb 83

erica
Télécharger la présentation

L. Waganer Consultant for ARIES Project/UCSD/DOE ARIES-Pathways Project Meeting 4-5 April 2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Addressing Lingering Cost Questions L. Waganer Consultant for ARIES Project/UCSD/DOE ARIES-Pathways Project Meeting 4-5 April 2011 Bethesda, MD Page 1

  2. Questions Remain on Several Cost Topics • The cost of the enriched Lithium and Li17Pb83 • The cost of the Main Heat Transfer and Transport system • The added cost for safety and nuclear grade materials • Validation of Turbine-Generator System Costs Page 2

  3. The Cost of the Enriched Lithium and Li17Pb83 PS, The more accurate atom percentage per Laila El-Guebaly is Li15.7Pb84.3 Page 3

  4. UWTOR-M Cost of Enriched Li17Pb83 The cost of lithium and Li17Pb83 in the previous ARIES Systems Code was (roughly) based on the 1982 UWTOR-M data, which was not referenced or substantiated. The cost of 35% enriched Li was quoted at $410/kg in 1982$ or $811 in 2009$*. (UWTOR-M) The cost of 35% enriched Li17Pb83 was quoted at $6.35/kg in 1982$ or $12.56 in 2009$*. The linear extrapolation suggests the use of enriched lithium is mixed with natural lithium to obtain the desired enrichment (not cost effective) The U.S. discontinued the production of large-scale lithium enrichment in 1963 with no production basis since. Therefore no large-scale enrichment production or cost basis exists Page 4 * 2009$/1982$ = 1.979

  5. Proposed Li Enrichment Costs A new scaling law is needed for the enrichment of lithium to provide incentive to develop new enrichment processes • A cost of $1000/kgfor 90% enriched lithium was selected as opposed to the escalated $2300/kg cost projected by UWTOR-M data • A curve between natural and 90% enrichment was developed to indicate an ever increasingly difficult enrichment process • The 90% enrichment point and the curve are only notional targets to provide attractive breeder and coolant costs and to stimulate process research and development Page 5

  6. “Difficulty” in Forming Li17Pb83 Eutectic Several technical papers (below) documented the process of forming the Li17Pb83 eutectic with no difficulty using simple processes and hardware. The more accurate atom % is Li15.7Pb84.3 , but the coolant atom % need only to be in the lower temperature regime. • The Li17Pb83eutectic melts at 235ºC as opposed to lithium at 180.54ºC and lead at 327.5ºC • The referenced experimental processes below used commercially-pure Li and Pb for their tests. • Common solder is a typical eutectic Ref 1, U. Jaunch, V. Karcher, and B. Schlutz, “Thermo-Physical Properties in the System Li-Pb,” by, KfK report 4144, September,1986 Ref 2, D. W. Jeppson. “Summary of Lithium-Lead Alloy Compatibility Tests” Westinghouse Hanford Company report, WHC-EP-0202, dated January 1989 Page 6

  7. Commercially Available Lithium The demand for lithium has increased since the 1980s due to greater usage in glass industries, metal alloying and high capacity batteries • In Sept 2008, www.metalprices.com lithium prices were $78/kg • In 7/2009, Chemetall-Lithium provided a ROM estimate for 99.9% pure natural lithium in large quantities at $75-85/kg. [No resource problem foreseen. They have their own mines.] • In March 2011, the LME price was averaging $62.3/kg including VAT. (99.0% pure, China) • For the present, we should adopt $80/kg as anatural lithium baseline cost Page 7

  8. Commercially Available Lead The demand for lead remains relatively stable, but the costs have shown recent fluctuations • In July 2009, the LME lead price was $1.628/kg • In 2009, the RotoMetals web site had 99.9% pure at $1.85/kg and around $2.00/kg delivered (surcharge ~$0.35) • In March 2011, the LME price was averaging $2.46/kg including VAT. (99.97% purity (minimum) conforming to BS EN 12659:1999 ) • For the present, we should adopt $3.00/kg as alead baseline cost Page 8

  9. 6313 tonnes $151 M $62 M A Reasonable Li17Pb83 Cost Estimate An updated Li17Pb83 cost estimate was developed using the current commercially available lead and lithium prices as well as my postulated lithium enrichment costs. • Up to 60% enrichment, lead is the more costly constituent in Li17Pb83 • New natural lithium cost is close to UWTOR-M but ARIES-AT was 3X higher • ARIES-AT 90% enriched Li was 22% lower than UWTOR-M • Lower lithium and lead costs plus the new $1000/kg enriched Li reduces costs by >50%. Recommend adopting new Enrichment Cost Table Page 9

  10. The Cost of the Main Heat Transfer and Transport System Page 10

  11. The Main Heat Transfer and Transport System is Thought to be too Expensive • The previous MHTT costs were equal to the magnets and the sum of the FWB and Shields, which seems excessive • MHTT contains only piping, IHX, insulation, pumps and storage tanks • It does not have to handle an intense neutron environment, disruptions, are simple shapes and simple maintenance • Suggest it being in the range of 125K to $150K for a single coolant primary system LSA = 1 factor of 0.60 applied The previous MHTT costs estimated Li, LiPb and He systems with a single equation. A second equation was provided for H2O and OC. It would be more appropriate to use a nominal Pth of 2000 MWth as opposed the previous value of 3500 MWth. This does not change the baseline cost and is only a minor correction of the leading coefficient. (see graph on a subsequent page) Page 11

  12. Power Core Turbine Loop Primary Loop IHX Brayton A B C D E Intermediate Loop Turbine Loop F G H I Liquid Metal Sodium Gas Direct Cycle Direct Cycle Dual coolant Dual coolant Direct Cycle Dual coolant Dual coolant Direct Cycle Dual coolant Possible MHTT ConfigurationsBlanket and Divertor May Use Different Fluids Page 12

  13. More MHTT Definition Is Needed • The prior slide illustrated possible MHTT combinations: • LM vs. gas • Primary/intermediate/turbine loops • Blanket/shield with or separate from divertor • More detailed data is required for better estimates • Thermal power from Blanket, Hot Shield, and Divertor by coolant type and by loop • Added pump work that can be recovered in each loop • There should be a tally of thermal powers at exit of power core, exit from IHX, exit of Intermediate Loop (if used) and entrance to Turbine (this would be the Gross Thermal Power value) • Include safety or nuclear cost adders Page 13

  14. Comparing Old and New MHTT Algorithms The previous ARIES 3500 MWth and adjusted Pth baseline 2000 MWth MHTT algorithms (LSA=1)are the superimposed upper curves The lower curves are the proposed LM and Helium MHTT algorithms (26% less for LM and 35% less for helium) The new curves are for single heat transfer media in the primary loop Note: $228 in equation is Li or He coefficient $265 (1992$) x 1.4323 (inflation) x 0.60 LSA=1 Modified coefficient is 2.28 x 0.735 = 168.0 Compared to Adjusted Prior Algorithms Primary and diverter loops Water and organic coolant: $50 M x (gross thermal power/2000)0.55 (in 2009$) ~ Equal Liquid Metal (Li and LiPb): $125 M x (gross thermal power/2000)0.55 (in 2009$) 26% lower High Pressure Helium: $110 M x (gross thermal power/2000)0.55 (in 2009$) 35% lower Adder for Nb IHX $0.010 M x gross thermal power in MW (in 2009$) Ref. Malang Intermediate loop Sodium or Helium: $50 x (gross thermal power/2000)0.55 (in 2009$) 30% higher Page 14

  15. Procedure for Estimating Dual Coolant Systems Dual coolant systems employ two separate primary loops, all with unique subsystems handling different levels of thermal power. The prior equations will be used with the appropriate fluid power level. The nominal 2000 MWth is shown in blue (a 2500 MWth version is in pink). $125 M for a single 2000 MWth LM coolant $110 M for a single 2000 MWth He coolant Dual coolant systems are definitely more costly than single coolant systems, but they seem to be the better option. Let’s model the MHTT systems to correctly portray them. This is a first approximation. Page 15

  16. The Added Cost for Safety and Nuclear Grade Materials Page 16

  17. Remember, All Costs Should Assume a 10th of a Kind Plant • Preceding the 10th-of-a-kind plant will be the Demo (a one-of-a-kind plant) maybe a second one-of-a-kind plant and then nine near-identical power plants with learning factors being applied • All estimates should reflect current prices unless resources are limited • All research and development costs would have been amortized and would not apply to the 10th-of-a-kind It would not be appropriate to adopt the costs of prototypes, experimental hardware, or first of a kind subsystems for our 10th-of-a-kind estimate Page 17

  18. The ARIES Philosophy for EstimatingSubsystems Using Material Unit Costs • Raw materials can be estimated using current bulk material quotes • The exception is enriched lithium which has no large production basis • Power core subsystems cost estimates are based on: 1) the raw material cost plus a fabrication factor based on “expert” judgment or • 2) a more detailed bottoms-up fabrication estimate (ref: ARIES-AT VV or ARIES-ST centerpost and monolithic CS TF structural shell) However these procedures do not effectively address the extra cost associated with either Safety or Nuclear systems Page 18

  19. Some Added Costs Are Appropriate for the Safety and Nuclear Subsystems • Higher material quality and fabrication process controls from certified vendors on basic materials and critical components • Increased testing and documentation (traceability) • Higher levels of assembly process control, documentation, inspection and checkout testing However any increased design and analysis efforts would have been borne by the initial plants and is not applicable to the 10th plant • Applicable subsystems might be • Nuclear-rated -FWB, divertor, shield, main VV, RF launchers • Safety-rated – VV doors, VV maintenance ports and doors, RF windows • Not-rated – Magnets, power core structures, LT shields, cryostat, bioshield • What about the Main Heat Transfer and Transport Subsystem? Most other subsystems are analyzed by performance parameters Page 19

  20. Re-Evaluation of Turbine-Generator System Costs Page 20

  21. Turbine-Generator Plant Equipment Costs Slides from April 23-24, 2009 Presentation This account includes the costs for the Turbine Plant equipment to take the thermal energy from the fusion power core and convert it into electrical energy. This system can either be an advanced Rankine (steam) or a Brayton (helium or other gas) turbine fluid or maybe a combined gas cycle turbine. Costs for all studies prior to ARIES-AT have included the Heat Rejection System within TPE Costs. However beginning with ARIES-AT, Heat Rejection System is a separate account Page 21

  22. Prior Turbine-Generator Plant Equip Cost Algorithms Prior ARIES-AT TPE Cost Algorithms Cost(OC, H2O) = EF x $257.55 x (PET/1200) ^.83 Cost(Li, LiPb) = EF x $243.34 x (PET/1200) ^.83 Cost(He) = EF x $208.08 x (PET/1200) ^.70 EF is escalation factor from 1992$ ARIES-AT algorithms • Curves were based on ARIES II-IV algorithms by Delene/Miller • Basis is Titan (PET 1200 MW scaled to .83 or .70 exponent) • Basis updated in 2008 for ARIES-AT(1.2% increase for all) • Cost basis was LSA of 4, but LSA factors were all 1.0 Costs are in 2008$ 0C, H2O • TPE algorithms based on primary fluid makes no sense, instead suggest adopting Rankine (steam) or Brayton (gas)-based algorithms. • The next slide compares reported costs to algorithms used Li, LiPb He Slides from April 23-24, 2009 Presentation Page 22

  23. Chronological Brayton Cycle Grouped and Ordered Primary (H2O or OC) and Steam Primary (He) and Steam or Primary (LiPb) and He Primary (Li), Intermediate (Na), and Steam Primary (LiPb and He) and Steam or He Reported T-G Costs Did Not Match Algorithms ARIES-AT algorithms These data are with Ron Miller’s updated ARIES-AT cost algorithms that are 1.2% higher than the ARIES II-IV costing algorithms Notice that all ARIES estimates are around 16% or more higher than algorithm that should have been used A&E Developed Slides from April 23-24, 2009 Presentation Costs are in 2008$ ARIES-AT algorithms Page 23

  24. New Proposed T-G Cost Algorithms To better represent and parametrically scale T-G costs, these algorithms were proposed: C23 = $350M x (Pth gross/2620)0.70 Rankine = $360M x (Pth gross/2000)0.80 x (ηth gross/.60) Brayton Note: 2620 MW is 2000 MW x 59%/45% Costs are scaled by thermal power and efficiency Page 24

  25. Adding Recently ARIES T-G Reported Costs ARIES-ST, η=45% ARIES-RS, η=46% ARIES-AT, η=59% ARIES-CS, η=43% • Note CS has 50% more Pth, but the same cost • (New algorithms would properly reflect that trend) • RS and ST seem high, compared to new equation • However both reported data and new algorithms are just “estimates” New Proposed T-G Cost Algorithms To better represent and parametrically scale T-G costs, these algorithms were proposed: C23 = $350M x (Pth gross/2620)0.70 Rankine = $360M x (Pth gross/2000)0.80 x (ηth gross/.60) Brayton Page 25

  26. General Atomics Provided Some RelevantTurbine Plant EquipmentCost Data on Gas and Steam Cycles Page 26

  27. Turbine-Generator Learning Curves GA suggested a 0.95 learning curve, but CCGT technology might be better represented with a learning curve of 0.88. (ref. Energy Technology Systems Analysis Program) 0.95 0.88 DOE’s criteria for turbine-generator maturity is 8 GWe (approximately 38 turbine modules or 10 plants) ~ 8 GWe We can apply these learning curve data to the GA turbine cost estimates Page 27

  28. Note: This example has four turbines per plant (Four Turbines) Scaling of GA Data on Turbine-Generator Costs Ken Schultz and Puja Gupta provided gas turbine and steam T-G data Learning curves are referenced from prior chart These quantity learning curve data will be used to estimate the ARIES plants Page 28

  29. Scaling T-G Costs to ARIES-AT • Assume ARIES-AT parameters for CCGT • Pe net = 1000 MWe, Pe gross = 1170 MWe, η = 0.48, Pth = 2440 MWth with four turbine modules at 610 MWth each (red data are new parameters) • 610 MW is probably the present size limit • Learning Curve Scaling: • Four NOAK turbines @ 450 MWth each & 0.88 LC = $260.46M • Size Scaling: • Note that ARIES has used 0.8 size scalingfor LM & He & 0.70 for H20 & OC. • Scaled Unit Cost = UC450 x (Pth/450)0.81 per DOE guidance. C610 = $260.46 x (610/450)0.81 = $333 M, for 2440MWth Combined Cost for Four Turbines at 610 MWth each Page 29

  30. Fit GA Brayton Turbines Onto Existing Curves The GA turbines costs, scaled to NOAK and to a larger size, is just between the proposed 45% and 50% efficient Brayton algorithms ARIES-ST, η=45% ARIES-RS, η=46% ARIES-AT, η=59% ARIES-CS, η=43% GA Brayton Turbines, η=48% Excellent collaborative data for our algorithms Page 30

  31. Conclusions • Use current commodity prices for Special Materials • Adopt $1000/kg for 90% enriched lithium • Use provided table • Better define technical design of Main Heat Transfer and Transport • Piping size, length, pumps, HX, tanks, makeup, pump work, power balance • Continue with new MHTT cost algorithms • Laila should recommend safety and neutron-related cost adders for certain subsystems • Accept new Rankine and Brayton Turbine-Generator Plant algorithms Page 31

  32. Escalating capital costs were also highlighted in the US Energy Information Administration (EIA) 2010 report “Updated Capital Cost Estimates for Electricity Generation Plants“. The US cost estimate for new nuclear was revised upwards from $3902/kW by 37% to a value of $5339/kW for 2011 by the EIA. This is in contrast to coal, which increases by only 25%, and gas which actually shows a 3% decrease in cost. Renewables estimates show solar dropping by 25% while onshore wind increases by about 21%. The only option to increase faster than nuclear is offshore wind at 49%, while the increase in coal with CCS is about the same as nuclear. In the previous year's estimate, EIA assumed that the cost of nuclear would drop with time and experience, and that by 2030 the cost of nuclear would drop by almost 30% in constant dollars.By way of contrast, China is stating that it expects its costs for plants under construction to come in at less than $2000/kW and that subsequent units should be in the range of $1600/kW. This estimates is for the AP1000 design, the same as used by EIA for the USA. This would mean that an AP1000 in the USA would cost about three times as much as the same plant built in China. Different labour rates in the two countries are only part of the explanation. Standardised design, numerous units being built, and increased localisation are all significant factors in China.  Ref: World Nuclear Association, Economics of Nuclear Power, Updated 9 March 2011, http://www.world-nuclear.org/info/inf02.html Some Sobering Economic Projections Page 32

More Related