CFC ANCOP ROTARY HOMES. ANswering the Cry of the Poor. Shelter Program. INSTALLATION OF FORMS. INSTALLATION OF FORMS. Progress Report July 18, 2012. First Cluster-Maynilad Funded Houses. CONCRETE POURING. SITE DEVELOPMENT. FACTORS THAT CONSTRIBUTED TO THE DELAY

fifi
Télécharger la présentation

ANswering the Cry of the Poor

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CFC ANCOP ROTARY HOMES ANswering the Cry of the Poor

  2. Shelter Program

  3. INSTALLATION OF FORMS

  4. INSTALLATION OF FORMS

  5. Progress Report July 18, 2012 First Cluster-Maynilad Funded Houses

  6. CONCRETE POURING

  7. SITE DEVELOPMENT

  8. FACTORS THAT CONSTRIBUTED TO THE DELAY • Condition of the site. • Difficulty in mobilization considering the simultaneous • work going on in the same area (house construction • and site development) • Lack of power supply. • Beneficiaries need to support the financial and material • requirements of their family. • Weather • Suitable site for forms fabrication. • Familiarization with the new technology.

  9. WHAT PROGRESS HAVE WE ACCOMPLISHED AFTER JUNE 18? FIRST CLUSTER CONSISTING OF 14 HOUSES

  10. WE ARE NOW AT THE 2ND FLR

  11. PROGRESS IN THE CONSTRUCTION FROM JUNE 18, TO JULY 18, 2012: • Concrete slab for the model unit. • Completion of 2nd floor tie beam. • Additional Panel. • Completion of ground floor for the 14 units.

  12. Program of works: • JULY • 3rd week-finish the wall partition for the 2nd floor of the first row. • 4th week-finish the walls of the 2nd row. • AUGUST • 1st week-put the c-parlenes and possibly the long span color roof. • 2nd week-fabrication and installation of doors and windows. • 3rd week-installing the kitchen zink and labatory and other finishing works. • Aug.24-BUILD DAY. (PAINTING)

  13. DAYS WORK/UNIT MONTHACTIVITY NO. OF DAYS FEB - GROUNDBREAKING/CLP MARCH - CLP/EXCAVATION APRIL - CLP/EXCAVATION 15 MAY - FOOTING AND TIE BEAM 26 JUNE - CONSTRUCTION OF GROUND FLOOR 25 JULY - GROUND FLOOR, 2ND FLR BEAM AND WALL PARTITION 13 ___ TOTAL NO. OF DAYS WORK 79 === NO. OF DAYS SPEND PER UNIT TO THIS DATE: (79 DAYS DIVIDED BY 14 UNITS) 5.642857