1 / 26

Final Presentation

Minerva Engineering. Final Presentation. Introduction. John Kats- Project Manager Ryan Schipper- Project Editor Matt Lash- Project Engineer/Client Contact Peter Flynn- Project Engineer Stephen Rowe- Project Engineer. PARAGON. Josh Reed- Client Contact. Overview. Overview

flavio
Télécharger la présentation

Final Presentation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Minerva Engineering Final Presentation

  2. Introduction • John Kats- Project Manager • Ryan Schipper- Project Editor • Matt Lash- Project Engineer/Client Contact • Peter Flynn- Project Engineer • Stephen Rowe- Project Engineer PARAGON Josh Reed- Client Contact

  3. Overview • Overview • Preliminary Investigation • Layout Options • Final Work • Summary

  4. Preliminary Feasibility Study • Site Visit • Zoning • Market investigation • Environmental Site assessment

  5. Codes and Regulations • Greenfield, Indiana Code of Ordinances • Hancock County, Indiana Code of Ordinances • Hancock County, Indiana Stormwater Technical Standards Manual • INDOT & AASHTO • International Building Code • American Standard of Testing Methods (ASTM)

  6. Geotechnical Investigation Field Work and Testing • Located Utilities • Determined sampling points • Bag Samples • Tube Samples • Wildcat Dynamic Cone Penetration Tests

  7. Geotechnical Investigation Soil Sampling Locations

  8. LEED Analysis • Researched requirements • Evaluated point criteria • Determined feasibility

  9. Decision Matrix A systematic approach for determining lot layout Criteria used for rating layout design options: • Estimated Cost • Expected Income • Amenities

  10. Decision Matrix Explanation of Estimated Cost:

  11. Decision Matrix Explanation of Estimated Income:

  12. Decision Matrix Explanation of Amenities:

  13. Decision Matrix Assessment of Layout Options:

  14. Site Layout Option 3 • 10 Estate Lots • 41 Custom Home Lots • 31 Zero Maintenance Lots

  15. Roadway and Pavement • Subdivision Control Ordinances • 34 feet wide from gutter to gutter • 4 foot sidewalks on either side

  16. Rain Garden • Bioretention area • Designed to not be a wetland • List of acceptable plant life in Central Indiana • Incorporated into Stormwater System

  17. Erosion & Sediment Control Phase I Plan

  18. Erosion & Sediment Control Phase II Plan

  19. Erosion & Sediment Control Curb Inlet Protection Outlet Protection Drop Inlet Protection

  20. Stormwater Management • Design of pipes • Retention Ponds • Rain Garden • LID

  21. Wastewater Management • Tie-in to Greenfield Wastewater Management • Placement of Pipes

  22. Grading Plan Before After

  23. Detail of Phase I • Substantial Cut • Cut can be used for the burm

  24. Construction Cost Estimate Estimation for roads, sidewalks, curb and gutter, excavation, utility hook-ups, erosion and sediment control and landscaping Unit pricing was found using the RS Means Manual

  25. Cost Summary

  26. Questions?

More Related