An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. UK CALICE plans Birmingham, Cambridge, Imperial, Manchester,RAL,RHUL,UCL

  2. Bid to funding agency • Went to the funding agency in February • Asked for £2.5M over the next 3 years for 5 workpackages • Iterations between committees • Emerge with cut-down and delayed scheme costing £2.7M over the next 4 years • EuroDet makes up a lot of the shortfall CALICE collaboration Meeting, DESY

  3. Workpackage 1: Complete the testbeam program • All institutes, with David Ward in charge • Analysis of test beam data from DESY, CERN and FNAL • Comparison with simulations (WP5) • Firmware and online software upgrades and maintenance • Contributions to data taking, running shifts, etc CALICE collaboration Meeting, DESY

  4. Workpackage 2: DAQ • UCL, Cambridge, Imperial, Manchester and RHUL with Matthew Wing in charge • New RAs at UCL and RHUL • On-board dataflow (Cambridge) • Networking dataflow (UCL/Manchester) • VFE ASIC readout studies (Imperial) • PCI optical receiver cards for off-detector (also part or EuroDET) CALICE collaboration Meeting, DESY

  5. Workpackage 3: MAPS • Birmingham, Imperial and RAL with Paul Dauncey in charge • Monolithic Active Pixel Sensors have detector and (binary) readout on same wafer • Standard CMOS fabrication – halve (?) silicon cost • Much higher granularity – 1 MIP/pixel. Pattern recognition being studied • Less/more material? Less/more heat? • Two rounds of sensor fabrication. First in 2006 • Aim for Beam test with MAPS layer(s) 2008 • New RAs (Birmingham and Imperial) CALICE collaboration Meeting, DESY

  6. Workpackage 4: Thermal+Mechanical • Manchester with Roger Barlow in charge • Work with École Polytechnique (and Lyon?) • Glue studies (literature + ageing). Radiation? • Thermal simulations – need information on design details • Thermal measurements to validate simulations + cooling design • Assembly robot: pattern recognition and placing for 24,000,000 pads CALICE collaboration Meeting, DESY

  7. Workpackage 5: Simulation and Physics • Birmingham, Cambridge, Imperial, RHUL and UCL with Nigel Watson in charge • New posts at RHUL, Birmingham, Cambridge and UCL • Energy flow algorithms • Optimising global detector design • Support of other workpackages • Physics studies: benchmark analyses CALICE collaboration Meeting, DESY

  8. Conclusions • Lots going on over the next few years (and beyond) • Many new posts (split between WPs)– tell your students CALICE collaboration Meeting, DESY