Welcome. E-Series Supplier Offsite. May 19, 2003 1-4 p.m. ~Agenda~. Welcome & Introductions Recent program changes Upcoming '05 E-Series Build Schedule and MRDs Review '05 E-Series Launch processes/support requirements Q & A Break-out groups by functional area (PMT) Regroup & wrap-up.

galeno
Télécharger la présentation

Welcome

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Welcome 1

  2. E-Series Supplier Offsite May 19, 2003 1-4 p.m. 2

  3. ~Agenda~ • Welcome & Introductions • Recent program changes Upcoming '05 E-Series Build Schedule and MRDs • Review '05 E-Series Launch processes/support requirements • Q & A • Break-out groups by functional area (PMT) • Regroup & wrap-up 3

  4. 2005MY E-Series Timing * Four units for 2006MY IVD program 4

  5. 2005 E-Series Timing Proposal 5

  6. CY 03 E-SeriesPrototype Builds & Key Testing Dates 6

  7. E- Series Build Schedule 7

  8. Extraordinary Launch Actions • Supplier Off site • Parts shipment before MRD • Prototype customer sign-off drive • On-line PCNs & Containment plans • Model year ’04 &’05 AIMS coordination • In addition to the static sign-off the “customer” of the vehicle will have a short drive for final sign-off with VE. 8

  9. On-Site E-Series Build Team 9

  10. Van Born Warehouse • Hours of operation currently are 10 hours. (6 AM – 4:30 PM) Monday-Friday. • Weekends are dependent upon customer demand. • Holiday hours for Memorial Day are yet to be determined. CONTACTS 10

  11. Daily Meeting Cadence • Morning meetings @ NMPDC Conference Rooms 7110 & 7111. (Daily from 7:00 – 8:30 am) • PCN’s, AIM’s, Shortage & Red Borders • Call-in #’s Ford net number is 32-36737 • The supplier/outside number is 1-800-367-3840 [participant code # 44798520]. • Change Control @ PDC 2D-B73 (M/W/F 1:30 – 2:30 pm) • Call-in# is 1-800-367-3840 [participant code# 8219706] 11

  12. On-line PCN & Containment Plan Systemwww.containment.ford.com • VN127 MY05 builds starting with the AP4 build (4/14 MRD) have started to use the on-line system. • Provides a single on-line source for creating, approving, tracking PCNs and Containment Plans • Accessible on the Ford intranet • Provides cross attribute notification for Containment Plans • Provides a complete report out for any vehicle • Data mining – to track & access changes from build to build 12

  13. Supplier Expectations • Enter delivery date into GPIRS,within 48 hrs of receiving order (If not DDL, contact William Oglesby with Date) • Ship the parts early (vs. delivering on MRD) • Confirm that you have received all PO’s required to support E-Series prototype builds and the correct quantity (if rate/flow enter Red Border) • Maintain delivery integrity, builds cannot be compromised. 13

  14. Supplier Expectations • Red Borders should be submitted as early as possible. No Red Borders after June 2nd! • All suppliers that slip their promise date must report the issue at the daily Build Shortage Meeting (7:30 am at NMPDC) • Late deliveries will require an 8D report, and will be reviewed with management. 14

  15. (AIMS 6 Day Release Process)Day 1 - 2 • Upon issue identification, screening & binning at Wall Meeting: • AIMS is issued with agreed upon design/process resolution with supplier, VO & PD. • Write & raise CR to ‘A’ status & submit process sheet if required. 15

  16. Day 3 (AIMS 6 Day Release Process) • Resolution/CR with containment plan/AIMS review questions answered cost/timing to Change Control; • Authorization of CR; CAD Kick-off (Authorization is at agreed upon Not-To-Exceed piece cost/tooling amount. • Also, D&R Engineer must alert CBG buyer (in purchasing program management, EMILES/JGRUBB4) of approved concern #, scope of design change, affected part #'s/supplier(s)- D&R Engineer should also alert buyer if new part sourcing is required). 16

  17. Day 4 – 5 & Day 6 (AIMS 6 Day Release Process) • (Day 4-5) • Report out on CAD progress; • drawings complete, into CAD and ready for release. •  (Day 6) • Release – AIMS issue closed. 17

  18. Day 7 - 8(AIMS 6 Day Release Process) • Design change only situations: • WIPS will automatically source the design new level to incumbent supplier. • Buyer will issue OK to proceed RFQ to Supplier. • New part situations: • Buyer will issue source only to new agreed upon supplier and will issue OK to proceed RFQ for future PO/TO issuance. 18

  19. Day 9 – 10 & 11 (AIMS 6 Day Release Process) • (Day 9-10) • Supplier enter SPROM into DDL and issue alert is required.   • (Day 11) • VO review and disposition alert. 19

  20. Build Issues 20

  21. Current Rating: Green 21

  22. CP Lock & Load • May 2nd – BoM frozen for June 2nd MRD builds / Any changes now will only be authorized in Change Control for NO-BUILD or Safety reasons and require signed containment plan. 22

  23. Missed Commitments • First Day – Into night letter • Second Day – Immediate notification to Elaine Haas CNE and meeting scheduled. • Third Day – Report to D. Grandinett and W. Osborne 23

  24. In Closing • Actual Ship dates must be provided for each build phase. • Suppliers providing early delivery of parts will not be penalized. • Missed Commitment dates are taken seriously and will be escaladed to management and will require an 8D. • No Design changes, with the exception of NO BUILD or SAFETY issues, will be accepted. • Your continued Support is Appreciated and Recognized. 24

  25. Q & A 25

  26. Breakout Session 26

  27. Break Out • PMT Leads will facilitate review of parts not yet received in Van Born Warehouse as of 5/16/03. • Please provide signed containment form to your PMT Lead for your part(s) before leaving today. 27

  28. Regroup • To those suppliers who have met the MRD of 6/2 thank you for your support. • Those suppliers who will be late and NOT meet the MRD of 6/2 please remain for a red border session. 28