1 / 11

Transmission : From Policy to Projects One Company’s Perspective November 4, 2011 Clarke Bruno

Transmission : From Policy to Projects One Company’s Perspective November 4, 2011 Clarke Bruno. Anbaric business model States as catalysts. Anbaric – Our Business Model. Anbaric incubates and develops transmission lines to: Integrate regional markets;

gellert
Télécharger la présentation

Transmission : From Policy to Projects One Company’s Perspective November 4, 2011 Clarke Bruno

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Transmission: From Policy to Projects One Company’s PerspectiveNovember 4, 2011Clarke Bruno

  2. Anbaric business model • States as catalysts

  3. Anbaric – Our Business Model • Anbaric incubates and develops transmission lines to: • Integrate regional markets; • Bypass bottlenecks or reduce congestion; and • Bring renewables, esp. offshore wind, to load.

  4. Anbaric – Our Business Model • We rely on states as catalysts, to move from policy to projects: • Competitive, transparent RFP; • Procurement from credit-worthy counterparty; and • Apportion economic risk.

  5. Anbaric-Incubated Projects Neptune Regional Transmission System • From Sayreville, NJ to Long Island NY • 65 mile, 660 MW HVDC line • Total cost - $700MM,COD June 2007 Hudson Transmission Project • From Ridgefield, NJ to Manhattan • 9 mile, 660 MW HVDC • Total cost - $800MM, COD early summer 2013

  6. Anbaric Pipeline -- @$4.5 billion • Integrate regional electricity markets • West Point Project (Albany to Buchanan, NY); • Champlain Wind Link (Plattsburgh, NY to Burlington, VT); and • Green Line (coastal Maine to Boston, MA) • Offshore wind to population centers • Massachusetts @ 2000 MW; • New Jersey @ 1100 MW; and • Hawaii @ up to 600 MW

  7. States – Catalysts • Catalysts • Policy driven vision – ratepayer cost, reliability, competition, renewables, industrial policy, build grid as a public good, RPS goals • Economic benefits – “demand drives deal”

  8. States – Catalysts • From policy to projects • Time and risk • Competitive RFP • Transparent selection process • Fixed price vs. cost plus bid

  9. States – Catalysts • From policy to projects • Roles for incumbent utility, gov’tal entity • Willing counterparty – an entity to sign contract • Shared project risk • Time and risk • Beware: cost allocation

  10. Contact Information Clarke Bruno Anbaric Transmission401 Edgewater Place, Suite 640 Wakefield, MA 01880 Direct: (781) 683-0710 cbruno@anbaricpower.com www.AnbaricTransmission.com